Project Accelerate, Matthews (East John Street)
Matthews, Mecklenburg County, North Carolina
Project Accelerate, Matthews (East John Street) is a cancelled data center in Matthews, North Carolina (Mecklenburg County), operated by Crosland Southeast. The public record puts it at 123 acres. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Cancelled
- Operator
- Crosland Southeast
- Facility type
- Data center
- Location
- 1603 East John Street, Matthews, Mecklenburg County, NC, 28105
- Coordinates
- 35.1015, -80.7082 (approximate)
- Power capacity
- Not established from a public source
- Land
- 123 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 8, 2025CancelledDevelopers withdrew the rezoning request; the mayor announced the withdrawal after sustained public opposition. Source: Charlotte Observer (via Yahoo News)
- July 2025ProposedMatthews Board of Commissioners initiated a rezoning for the 123-acre site at 1603 E. John St. for data center use; five two-story buildings were proposed. Source: Charlotte Observer (via Yahoo News)
Opposition and litigation at this site
Yes. Organized local opposition to Project Accelerate, Matthews (East John Street) in Matthews, Mecklenburg County, North Carolina is documented in the public record, without a lawsuit on file in the sources we track. A petition against the project gathered more than 2,700 signatures; residents raised noise, power, water and neighborhood-character concerns.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
A petition against the project gathered more than 2,700 signatures; residents raised noise, power, water and neighborhood-character concerns. Mayor John Higdon attributed the withdrawal to 'overwhelming public distaste'.
Notes on the record
Codenamed Project Accelerate; Engineered Land Solutions worked with Crosland Southeast on the filing. No capacity is recorded: the 'up to 600 MW' figure describes the withdrawn proposal's electricity request, not a built or permitted capacity. The withdrawal date (Oct. 8, 2025) and reason (public opposition) are as reported by the Charlotte Observer. As of September 2026, no new filings or developments were found at this site since.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- TierPoint Charlotte - North Myers · Charlotte · TierPoint11 mi · Operating
- Digital Realty CLT10 (113 North Myers Street) · Charlotte · Digital Realty11 mi · Operating
- PowerHouse Charlotte Campus · Charlotte · PowerHouse Data Centers12 mi · Under construction · 300 MW · Contested
- American Tower Reedy Creek Data Center (East Charlotte) · Charlotte · American Tower12 mi · Proposed · Contested
- Spectrum Charlotte National Data Center · Charlotte · Charter Communications12 mi · Operating · 15 MW
- Flexential Charlotte - South (CLT01/02/03) · Charlotte · Flexential13 mi · Operating · 2.36 MW
- TierPoint Charlotte - Center Park · Charlotte · TierPoint13 mi · Operating
- Flexential Charlotte - North (CLT04/05) · Charlotte · Flexential16 mi · Operating
Questions people ask about this site
Is there opposition to the Project Accelerate, Matthews (East John Street) data center in Matthews?
Yes. Organized local opposition to Project Accelerate, Matthews (East John Street) in Matthews, Mecklenburg County, North Carolina is documented in the public record, without a lawsuit on file in the sources we track. A petition against the project gathered more than 2,700 signatures; residents raised noise, power, water and neighborhood-character concerns.
Has anyone filed a lawsuit over the Project Accelerate, Matthews (East John Street) data center?
No lawsuit over Project Accelerate, Matthews (East John Street) appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Accelerate, Matthews (East John Street) use?
No water withdrawal figure for Project Accelerate, Matthews (East John Street) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Project Accelerate, Matthews (East John Street), and how big is it?
Crosland Southeast is the operator on record. No capacity figure is on record for this site. The site is recorded at 123 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Accelerate, Matthews (East John Street)," updated October 28, 2026, https://suedatacenters.org/data-centers/crosland-southeast-matthews-project-accelerate-nc.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/crosland-southeast-matthews-project-accelerate-nc, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Matthews data center project withdrawn because of 'public distaste,' mayor says · Charlotte Observer (via Yahoo News) · retrieved August 16, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us