Data Center Registry
Tract Branders Bridge Road Data Center Park (withdrawn)
Chesterfield County County, Virginia · All 18 Tract sites
Tract Branders Bridge Road Data Center Park (withdrawn) is a cancelled data center in Virginia (Chesterfield County County), operated by Tract. The public record puts it at announced February 3, 2025, 744 acres. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Cancelled
- Operator
- Tract
- Facility type
- Data center
- Location
- 16100 Branders Bridge Road, Chesterfield County County, VA, 23831
- Coordinates
- 37.2936, -77.4542 (approximate)
- Power capacity
- Not established from a public source
- Land
- 744 acres
- Investment
- Not established from a public source
- Announced
- February 3, 2025
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 1, 2025CancelledTract withdrew the zoning application after the denial recommendation and said it intends to resubmit. Source: Richmond BizSense
- February 3, 2025ProposedTract sought to rezone 744 acres for up to 11 data centers (~2M sq ft). Source: Richmond BizSense
Opposition and litigation at this site
Yes. Organized local opposition to Tract Branders Bridge Road Data Center Park (withdrawn) in Chesterfield County County, Virginia is documented in the public record, without a lawsuit on file in the sources we track. The Planning Commission unanimously recommended denial, citing substandard roads and traffic.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
The Planning Commission unanimously recommended denial, citing substandard roads and traffic. The county transportation department did not recommend approval.
Notes on the record
Tract said it would refile, but no refiling was found. Chesterfield stated in Aug 2026 that it will not approve new data center zoning requests. Baxtel lists the project as cancelled before construction.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Chirisa Technology Park, Richmond (Chester) · Chester · PowerHouse Data Centers4 mi · Under construction · 120 MW · Mixed reception
- Bermuda Hundred Data Center (Old Bermuda Hundred Road) · Chester · Undisclosed (landowner: Washington Single Family Fund3)4 mi · Proposed · In litigation
- Wagner Road Data Center Campus · Petersburg · Wagner Properties5 mi · Permitted
- NuVu County Drive Data Center Campus · Petersburg · NuVu Real Estate8 mi · Permitted · 300 MW
- Menlo Digital Richmond Virginia Data Center (Jamestown Drive) · Petersburg · Menlo Digital8 mi · Permitted · 104 MW
- TWG Data Halifax Road Campus (former Collier Yard) · Petersburg · Warrenton Group (TWG Data)8 mi · Permitted
- PowerHouse CTP-02 · Chester · PowerHouse Data Centers8 mi · Under construction · 50 MW
- Project Peanut · Chester · Google9 mi · Under construction · Contested
Questions people ask about this site
Is there opposition to the Tract Branders Bridge Road Data Center Park (withdrawn) in Chesterfield County County, Virginia?
Yes. Organized local opposition to Tract Branders Bridge Road Data Center Park (withdrawn) in Chesterfield County County, Virginia is documented in the public record, without a lawsuit on file in the sources we track. The Planning Commission unanimously recommended denial, citing substandard roads and traffic.
Has anyone filed a lawsuit over the Tract Branders Bridge Road Data Center Park (withdrawn)?
No lawsuit over Tract Branders Bridge Road Data Center Park (withdrawn) appears in the record we track as of October 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Tract Branders Bridge Road Data Center Park (withdrawn) use?
No water withdrawal figure for Tract Branders Bridge Road Data Center Park (withdrawn) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Tract Branders Bridge Road Data Center Park (withdrawn), and how big is it?
Tract is the operator on record. We hold 18 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 744 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Tract Branders Bridge Road Data Center Park (withdrawn)," updated October 14, 2026, https://suedatacenters.org/data-centers/tract-branders-bridge-chesterfield-va.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tract-branders-bridge-chesterfield-va, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.After thumbs down from commission, developer withdraws, plans to refile 700-acre Chesterfield data center proposal · Richmond BizSense · retrieved October 14, 2026
- 2.Tract: Colonial Heights, VA · Baxtel · retrieved October 14, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us