Data Center Registry
PowerHouse CTP-02
Chester, Chesterfield County, Virginia · All 12 PowerHouse Data Centers sites · Every PowerHouse and Hillwood case on our tracker
PowerHouse CTP-02 is a data center under construction in Chester, Virginia (Chesterfield County), operated by PowerHouse Data Centers. The public record puts it at 50 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- PowerHouse Data Centers
- Facility type
- Data center, AI use confirmed
- Location
- Chester, Chesterfield County, VA
- Coordinates
- 37.3606, -77.3257
- Power capacity
- 50 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Dominion Energy Virginia
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of July 23, 2026. No lawsuit, organized opposition, or contested hearing over PowerHouse CTP-02 in Chester, Chesterfield County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
50MW build-to-suit at Chirisa Technology Parks' Meadowville Technology Parkway campus (Chesterfield County), JV of PowerHouse, Chirisa, and Blue Owl Real Estate; broke ground 2024/2025, CoreWeave is the confirmed GPU/AI-cloud tenant (28MW deal Sept 2023 plus this expansion). PowerHouse's own portfolio page lists 'CTP-02 and CTP-03' as a platform entry; baxtel independently corroborates PowerHouse CTP-02 as a named facility at this campus. Joint venture with Chirisa Technology Parks and Blue Owl Real Estate.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Project Peanut · Chester · Google2 mi · Under construction · Contested
- Bermuda Hundred Data Center (Old Bermuda Hundred Road) · Chester · Undisclosed (landowner: Washington Single Family Fund3)4 mi · Proposed · In litigation
- Chirisa Technology Park, Richmond (Chester) · Chester · PowerHouse Data Centers6 mi · Under construction · 120 MW · Mixed reception
- QTS White Oak Technology Park II (RIC5) · Sandston · QTS Data Centers9 mi · Permitted · Mixed reception
- QTS Richmond 1 DC1 (RIC1, White Oak Technology Park) · Sandston · QTS Data Centers10 mi · Operating
- Wagner Road Data Center Campus · Petersburg · Wagner Properties10 mi · Permitted
- Menlo Digital Richmond Virginia Data Center (Jamestown Drive) · Petersburg · Menlo Digital11 mi · Permitted · 104 MW
- NuVu County Drive Data Center Campus · Petersburg · NuVu Real Estate12 mi · Permitted · 300 MW
Questions people ask about this site
Is there opposition to the PowerHouse CTP-02 data center in Chester?
Nothing on record as of July 23, 2026. No lawsuit, organized opposition, or contested hearing over PowerHouse CTP-02 in Chester, Chesterfield County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the PowerHouse CTP-02 data center?
No lawsuit over PowerHouse CTP-02 appears in the record we track as of July 23, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does PowerHouse CTP-02 use?
No water withdrawal figure for PowerHouse CTP-02 is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates PowerHouse CTP-02, and how big is it?
PowerHouse Data Centers is the operator on record. We hold 12 sites for that company across the registry. Capacity on record is 50 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "PowerHouse CTP-02," updated July 23, 2026, https://suedatacenters.org/data-centers/powerhouse-ctp-02-va.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/powerhouse-ctp-02-va, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Bisnow: CoreWeave data center at CTP's Richmond-area (Meadowville) campus lands $600M loan · PowerHouse Data Centers (JV with Chirisa Technology Parks and Blue Owl Real Estate) · retrieved July 22, 2026
- 2.OpenStreetMap way/1449347339 · OpenStreetMap · retrieved July 22, 2026
- 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us