PowerHouse and Hillwood: The Joliet Technology Center and the $20 Billion Rezoning Now in Court
Powerhouse Hillwood Holding, HW Technology Park Development, and American Real Estate Partners are the developers of the Joliet Technology Center, a 795 acre, 1.8 gigawatt campus valued at $20 billion. Residents sued in May 2026 to void the rezoning, alleging the public notice never said data center. The developers say the notice was adequate and no one asked to cross examine. The record.
PowerHouse and Hillwood on the tracker
- Tracker entries
- One: the Joliet Technology Center rezoning challenge in Will County Circuit Court, pending, with motions heard September 8, 2026
- Who is named
- Powerhouse Hillwood Holding, HW Technology Park Development, and American Real Estate Partners, alongside the City of Joliet
- Hillwood
- A real estate investment and development company headquartered at 3000 Turtle Creek Boulevard in Dallas, Texas, founded in 1988 and part of the Perot family of companies. Its public site describes industrial and logistics, communities, and urban divisions, and does not describe a data center business
- The project
- 795 acres rezoned from agricultural to light industrial, 24 buildings, 6,936,000 square feet, 1.8 gigawatts, valued at $20 billion; annexation agreement approved 8 to 1 on March 19, 2026
- The developers' public case
- Through Hillwood, the developers said the project would generate $2.1 billion for all taxing bodies over 30 years, 7,000 to 10,000 construction jobs, and 700 permanent positions at full operation, per Shaw Local
- Response to the suit
- The developers' attorney argues the plaintiffs had no right to cross examine witnesses at the March 16 council meeting because it concerned an annexation agreement. Shaw Local reported the companies did not respond to its requests for comment on the lawsuit
Key Takeaways
- The entity being sued in Joliet is not a household name. Powerhouse Hillwood Holding is a joint venture holding entity, and the co-defendants are HW Technology Park Development and American Real Estate Partners. Hillwood, the Dallas developer founded in 1988 and part of the Perot family of companies, is the one recognizable name in the group, and its own public site does not describe a data center business.
- Three residents of unincorporated Elwood and a nonprofit sued the City of Joliet and the three developer entities on May 18, 2026 to void the March 2026 rezoning of 795 acres for the Joliet Technology Center, a 24 building, 1.8 gigawatt campus valued at $20 billion.
- The core allegation is notice: the plaintiffs say the February 18, 2026 publication described a zoning category and a project name but never said the words data center, that the city violated the Illinois Open Meetings Act, and that residents were denied cross examination.
- The developers and the city dispute all of it. They argue state law does not require a notice to specify a project's end use, that cross examination rights belong only to owners within 600 feet and none asked, and that voiding a vote taken at an open public meeting is too extreme a remedy.
- Judge Victoria Breslan heard motions on September 8, 2026. Nothing has been decided, and the answer will set the rule for every large campus approval in Illinois.
In this article
Ask who is building the Joliet Technology Center and the honest answer takes three names: Powerhouse Hillwood Holding, HW Technology Park Development, and American Real Estate Partners. Only one of those, Hillwood, is a company most people could look up, a real estate investment and development firm headquartered in Dallas, founded in 1988 and part of the Perot family of companies, whose public site describes industrial, logistics, community, and urban development and says nothing about data centers. That gap between the brand and the entity on the caption is the first thing residents of unincorporated Elwood ran into, and it is a fair description of how most hyperscale campuses arrive. On May 18, 2026, three of those residents and a nonprofit sued the City of Joliet and all three developer entities to void the rezoning behind a 795 acre, 1.8 gigawatt campus valued at $20 billion. The case is pending. Here is what each side is arguing.
Every case on the tracker
- Active litigationIllinoisThe Joliet Technology Center Lawsuit: Residents Challenge a $20 Billion, 1.8 Gigawatt Rezoning
Pending, Will County Circuit Court (filed May 18, 2026); motions heard September 8, 2026
On May 18, 2026, three Elwood residents and a newly formed nonprofit sued the City of Joliet and the developers of the Joliet Technology Center, a 795 acre, 24 building, 1.8 gigawatt campus valued at $20 billion, arguing the March 2026 rezoning from agricultural to light industrial was unconstitutional, the public notice never mentioned a data center, and residents were denied cross-examination. The city calls voiding the vote too extreme a remedy. Judge Victoria Breslan heard motions September 8, 2026.
Every PowerHouse and Hillwood site in the registry
14 sites on the public record in 8 states: 1 operating, 8 under construction, 1 permitted, 4 proposed. 7 carry documented opposition or litigation. 11.0 GW planned. Most contested first.
- Joliet Technology Center · Joliet, ILPermitted · 1.8 GW · In litigation
- PowerHouse Data Centers, Louisville (Camp Ground Road) · Louisville, KYUnder construction · 402 MW · Opposed
- PowerHouse Caldwell County Data Center · Uhland, TXProposed · 4 GW · Contested
- PAX, Pennsylvania Digital I · Carlisle, PAUnder construction · 1.4 GW · Contested
- PowerHouse Charlotte Campus · Charlotte, NCUnder construction · 300 MW · Contested
- Buick City Data Center · Flint, MIProposed · Contested
- Carrollton Industrial Campus · Carrollton, KYProposed · Contested
- PowerHouse 95 · Spotsylvania, VAUnder construction · 800 MW · Mixed reception
- Chirisa Technology Park, Richmond (Chester) · Chester, VAUnder construction · 120 MW · Mixed reception
- PowerHouse Grand Prairie Campus · Grand Prairie, TXUnder construction · 1.8 GW
- PowerHouse Circle T Data Center Campus · Westlake, TXProposed · 300 MW
- PowerHouse Reno Campus · McCarran, NVUnder construction · 65 MW
- PowerHouse CTP-02 · Chester, VAUnder construction · 50 MW
- PowerHouse ABX-1 · Ashburn, VAOperating
The case, and both sides of it
The Joliet plan rezoned 795 acres of farmland at the edge of the city from agricultural to light industrial and annexed it, clearing the way for 24 buildings totaling 6,936,000 square feet and a power demand of 1.8 gigawatts. The Plan Commission heard it on March 5, 2026, the City Council took it up on March 16 and March 19, and the council approved the annexation agreement 8 to 1 on March 19.
The plaintiffs allege the rezoning bears no substantial relation to public health, safety, or welfare and is therefore unconstitutional under Illinois law, that the city violated the Illinois Open Meetings Act, that the February 18, 2026 public notice never described a data center, and that residents were denied the chance to cross examine witnesses. They ask the court to void the March 19 vote.
The defense is specific and, so far, undecided. The city argues the February 18 notice adequately described the project through its industrial classification and its name, and that state law does not require a notice to specify a project's end use. The developers' attorney argues the plaintiffs had no right to cross examine witnesses at the March 16 meeting because it concerned an annexation agreement, that the right belongs only to property owners within 600 feet, and that the meeting video shows no one sought it. On the Open Meetings Act, the city says nullifying a vote taken at an open public meeting is too extreme a remedy for an alleged notice or agenda defect. The defendants also challenge the nonprofit's standing because it was incorporated on June 4, after the suit was filed. Our full report on the Joliet case has every filing and the September 8, 2026 motion hearing.
What the developers say the project delivers
The developers have made their case in public as well as in court. Through Hillwood, they have said the campus would generate $2.1 billion for all taxing bodies, including schools and other units of local government, over 30 years, would create between 7,000 and 10,000 jobs through construction, and would support 700 permanent high paying positions once fully operational. Shaw Local reported those figures and also reported that the city, Hillwood, and PowerHouse Data Centers did not respond to its requests for comment on the lawsuit itself. The city's spokesperson said the city does not comment on pending litigation.
Those promises are the ordinary currency of a hyperscale approval, and they are exactly the terms residents should push to see written into an annexation or development agreement rather than a press release. Our tax abatement guide explains how to read a 30 year revenue projection, and our guide to who pays for data center power covers the 1.8 gigawatt half of the equation.
Illinois is where the notice question gets answered
Joliet is not the only front. The same plaintiffs' firm is challenging a 472 acre campus in Grayslake on a similar theory, and the reason both cases exist is Prince William County, Virginia, where the largest data center approval ever granted was voided because the hearing notice was legally defective. The Joliet defendants are asking an Illinois court to draw that line in a different place, holding that a zoning category and a project name are enough. Whichever way it goes, the ruling will govern how every large campus in the state is noticed and approved.
If a project near you moved from first hearing to final vote in a matter of weeks, the practical lesson from Joliet is to pull the published notice and read it for what it does not say, to request cross examination in writing at the hearing whether or not you live within 600 feet, and to make sure individual neighbors are named alongside any group. Our guide to fighting a proposed data center and our zoning appeal deadlines guide cover the substance and the clock. Our free case review connects you with an independent attorney in our network who handles data center cases in your state, at no cost and with no obligation.
Frequently asked questions
Who is building the Joliet Technology Center?
The developer entities named in the lawsuit are Powerhouse Hillwood Holding, HW Technology Park Development, and American Real Estate Partners. Hillwood is a real estate investment and development company headquartered in Dallas, Texas, founded in 1988 and part of the Perot family of companies. The project is planned at 795 acres, 24 buildings, 6,936,000 square feet, 1.8 gigawatts, and a reported $20 billion valuation.
What is the Joliet data center lawsuit about?
Three residents of unincorporated Elwood and the nonprofit Joliet Residents For Responsible Growth sued the City of Joliet and the three developer entities on May 18, 2026 in Will County Circuit Court. They allege the March 2026 rezoning from agricultural to light industrial was unconstitutional, that the February 18 public notice never described a data center, that the city violated the Open Meetings Act, and that residents were denied cross examination. They ask the court to void the March 19 council vote.
How have the Joliet developers responded to the lawsuit?
Their attorney argues the plaintiffs had no right to cross examine witnesses at the March 16 council meeting because it concerned an annexation agreement, and the defense adds that the right belongs only to owners within 600 feet and none requested it. The city says the notice was adequate and that voiding an open meeting vote is too extreme a remedy. Shaw Local reported the companies did not respond to its requests for comment on the suit.
What has Hillwood said the Joliet project will deliver?
Through Hillwood, the developers said the campus would generate $2.1 billion for all taxing bodies over 30 years, create between 7,000 and 10,000 construction jobs, and support 700 permanent high paying positions when fully operational, according to Shaw Local. Those figures are the developers' projections and have not been tested.
Article sources
Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.
- 1.Hillwood: about page listing the Dallas headquarters, the 1988 founding, the Perot family history, and the company's divisions
- 2.Hillwood: corporate site and division descriptions, reviewed September 3, 2026
- 3.Shaw Local: Lawsuit challenges zoning, approval process for Joliet data center (May 26, 2026), including the developers' project figures and their non response to requests for comment
- 4.Shaw Local: Lawsuit against Joliet data center heading to court hearing (August 18, 2026), including the developers' cross examination argument
Is a PowerHouse and Hillwood data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us