Sue Data Centers

Data Center Registry

PowerHouse Data Centers, Louisville (Camp Ground Road)

Louisville, Jefferson County, Kentucky · All 12 PowerHouse Data Centers sites · Every PowerHouse and Hillwood case on our tracker

Under constructionOpposedAI likelyRecord updated September 10, 2026

PowerHouse Data Centers, Louisville (Camp Ground Road) is a data center under construction in Louisville, Kentucky (Jefferson County), operated by PowerHouse Data Centers. The public record puts it at announced January 2025, 402 MW planned, 153 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
PowerHouse Data Centers
Facility type
Data center, AI use likely
Location
Louisville, Jefferson County, KY
Coordinates
38.1953, -85.8485
Power capacity
402 MW planned
Land
153 acres
Investment
Not established from a public source
Announced
January 2025
Utility
LG&E
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Data center property tax exemption for Louisville/Jefferson County (authorized by Kentucky Legislature in 2024; specific duration not confirmed in available sources), Jefferson County / Louisville Metro, KY, 2024
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. June 2025
    Permitted
    Development Review Committee approves 4-0; property already zoned industrial, no Metro Council vote required Source: Data Center Dynamics
  2. January 2025
    Proposed
    PowerHouse Data Centers and Poe Companies announce Louisville campus at 6001 Camp Ground Road; Kentucky's first hyperscale data center Source: Data Center Dynamics
  3. 2025
    Under construction
    Construction expected to begin 2025; Planning Commission approves revised site plans 6-1 over community objection in March 2026 Source: Louisville Public Media

Opposition and litigation at this site

Yes. Organized local opposition to PowerHouse Data Centers, Louisville (Camp Ground Road) in Louisville, Jefferson County, Kentucky is documented in the public record, without a lawsuit on file in the sources we track. Strong community opposition from Rubbertown-area residents citing energy affordability burdens on low-income customers, environmental and health equity concerns in a historically underserved West End neighborhood.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Strong community opposition from Rubbertown-area residents citing energy affordability burdens on low-income customers, environmental and health equity concerns in a historically underserved West End neighborhood. Multiple public hearings with significant protests. Louisville Party for Socialism and Liberation among opponents.

Source: Louisville Public Media

Power and water

New LG&E switch station to be completed September 2026; initial 130 MW available October 2026; expandable from 335 MW to 402 MW

Public money on the record

ProgramAmountGranted byYear
Data center property tax exemption for Louisville/Jefferson County (authorized by Kentucky Legislature in 2024; specific duration not confirmed in available sources)Not establishedJefferson County / Louisville Metro, KY2024

Notes on the record

Address: 6001 Camp Ground Road, Louisville, KY; near Shively and the Rubbertown industrial district, less than 1 mile from the Ohio River. 153 acres confirmed by DCD. 1.6M sq ft total campus across seven buildings. Operator discussing tenants including major hyperscalers (Google, Amazon, Microsoft named in reports). End tenant not publicly disclosed at time of research. Fix: removed unconfirmed '50-year' duration from tax exemption description, program exists per Kentucky 2024 legislation but specific term length was not confirmed by any fetched source.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Permanent jobs promised
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the PowerHouse Data Centers, Louisville (Camp Ground Road) data center in Louisville?

Yes. Organized local opposition to PowerHouse Data Centers, Louisville (Camp Ground Road) in Louisville, Jefferson County, Kentucky is documented in the public record, without a lawsuit on file in the sources we track. Strong community opposition from Rubbertown-area residents citing energy affordability burdens on low-income customers, environmental and health equity concerns in a historically underserved West End neighborhood.

Has anyone filed a lawsuit over the PowerHouse Data Centers, Louisville (Camp Ground Road) data center?

No lawsuit over PowerHouse Data Centers, Louisville (Camp Ground Road) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does PowerHouse Data Centers, Louisville (Camp Ground Road) use?

No water withdrawal figure for PowerHouse Data Centers, Louisville (Camp Ground Road) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates PowerHouse Data Centers, Louisville (Camp Ground Road), and how big is it?

PowerHouse Data Centers is the operator on record. We hold 12 sites for that company across the registry. Capacity on record is 402 MW. The site is recorded at 153 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "PowerHouse Data Centers, Louisville (Camp Ground Road)," updated September 10, 2026, https://suedatacenters.org/data-centers/powerhouse-louisville-ky.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/powerhouse-louisville-ky, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Planning Commission recommends approval for 1.6m sq ft planned data center in Louisville, Kentucky · Data Center Dynamics · retrieved July 6, 2026
  2. 2.West Louisville data center approved despite opposition · Louisville Public Media · retrieved July 6, 2026
  3. 3.Developers unveil plans for large tech data center in Louisville · PowerHouse Data Centers · retrieved September 10, 2026
  4. 4.Developers unveil plans for large tech data center in Louisville · PowerHouse Data Centers · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us