Stopping a Project
What Communities Give Up: Data Center Tax Abatements, Line by Line
A data center is sold to a county on a property tax number, and that number is usually reduced by a statute or a negotiated deal the public never reads. The mechanisms explained, the qualifying thresholds quoted from the Ohio, Texas, Virginia, Georgia, and Iowa statutes, real packages on record from Barber County, Kansas to Effingham County, Georgia, what the states now say the exemptions cost, and the records a resident can request.
Key Takeaways
- The largest data center subsidy is usually not the local abatement. It is a statewide sales and use tax exemption on servers, cooling, and power equipment that every qualifying project receives automatically by statute. Virginia's exemption alone saved data centers and their tenants $928.6 million in FY23, of which about $683 million was the state share, making it by far the state's largest economic development incentive; the next closest was worth $74 million.
- The qualifying thresholds are written into state law and they are investment tests, not job tests. Ohio requires $100 million of capital investment and $1.5 million of annual payroll. Texas requires $200 million and 20 jobs, or $500 million and 40 jobs for a large data center project. Virginia requires $150 million and 50 jobs at 150 percent of the local prevailing wage. Georgia's threshold falls to $25 million and five jobs in counties under 30,001 people. Iowa requires $200 million and no jobs at all.
- State cost estimates have been revised upward by orders of magnitude. Good Jobs First reports Georgia raising its FY2026 projection by 664 percent to $2.5 billion, Texas rising from $1 billion in FY2025 to $1.3 billion in FY2026, Virginia at $1.94 billion for FY2025, and Ohio at $1.6 billion for 2025 against an initial projection of $135.8 million. Ohio's governor paused new applications in May 2026.
- The arithmetic that communities rarely see: Virginia's FY23 exemption of $928.6 million against the 800 new full-time jobs data centers added that year is roughly $1.16 million per new job. Effingham County, Georgia's $20 billion OpenAI project promises at least 400 long-term jobs, about $50 million of capital investment per permanent job. Good Jobs First says taxpayer costs routinely exceed $1 million per permanent job.
- Not every deal is an abatement. Barber County, Kansas approved Google's Project Helium with 100 percent of ad valorem property taxes and no abatement, a projected $327.5 million over 20 years to local taxing jurisdictions, $5.5 million in community benefit payments, $5 million in road security, and decommissioning security at 125 percent of estimated cost. Mount Pleasant, Wisconsin took no public financial incentives from Microsoft and got a $1.4 billion minimum assessed value guarantee instead.
- The tax decision and the zoning decision are usually separate votes before separate bodies on separate clocks, and only one of them has a statutory appeal deadline. In Effingham County the memorandum of understanding was signed on July 21, 2026 and the project was announced publicly the next day.
In this article
A data center is almost always sold to a county on a tax number, and that number is almost always smaller than it first appears. Three different reductions can apply to the same project at the same time: a statewide sales and use tax exemption that the legislature already granted to every qualifying project, a locally negotiated property tax abatement or payment in lieu of taxes, and a tax increment financing district that redirects the new revenue to the site itself. The first is the biggest and the least visible, because no local body ever votes on it. Virginia's exemption was worth $928.6 million to data centers and their tenants in a single year, and the state's own legislative auditors found it returns 48 cents in revenue for every dollar it costs. This page explains each mechanism in plain English, quotes the qualifying thresholds from the Ohio, Texas, Virginia, Georgia, and Iowa statutes, lays out real packages on record from Barber County, Kansas to Effingham County, Georgia, does the jobs arithmetic with figures the states published themselves, and lists the specific documents a resident can request. It is a reference, not legal or tax advice. Nothing here tells you what your county should do; it tells you what the paper says so you can ask.
Updated September 3, 2026, and how to read this page
Updated: September 3, 2026. Every statute citation, dollar figure, and percentage below was taken from the source listed at the bottom of this page and checked on that date. Where a number comes from a news outlet or an advocacy organization rather than a statute or a government document, we say whose number it is in the sentence itself. Where we do arithmetic on published figures, we show the division so you can check it.
How to cite this page: SueDataCenters.org, "What Communities Give Up: Data Center Tax Abatements, Line by Line," updated September 3, 2026, https://suedatacenters.org/guides/data-center-tax-abatements.
One framing point before the numbers. Tax incentives are a policy choice, and communities that grant them cite real benefits: construction employment, infrastructure that would not otherwise get built, and a much larger tax base once an abatement expires. Those benefits are documented later on this page, including the Virginia county where data centers now supply 31 percent of all local tax revenue. The argument this page makes is narrower. It is that the arithmetic is usually available and is usually not presented, and that a resident is entitled to see it before the vote.
The six mechanisms, and which ones your county actually controls
People use "tax break" for six different things that work in different ways, are granted by different bodies, and are challenged, if at all, in different forums. The single most useful distinction is between a statutory exemption, which the legislature wrote into state law and which every qualifying project receives as of right, and a negotiated local deal, which a county commission, city council, school board, or development authority votes on and can decline.
| Mechanism | What it does | Who grants it | Can a local body say no? |
|---|---|---|---|
| Sales and use tax exemption on equipment | Removes sales tax from servers, storage, network gear, cooling, backup generators, and in some states electricity and construction materials. Usually the largest single subsidy because the equipment is the bulk of project cost and is replaced every few years. | State legislature by statute, administered by a revenue department or a tax credit authority | No. If the project meets the statutory threshold it qualifies, whatever the county thinks. |
| Property tax abatement or exemption | Waives all or part of the real and personal property tax for a set term. Personal property matters most here, because the computer equipment is worth far more than the shell. | County, city, school district, or a state or local development authority | Yes, usually by resolution or ordinance. |
| Payment in lieu of taxes (PILOT) | Substitutes a negotiated schedule of payments for the ordinary tax bill, often by putting title in a development authority and leasing the property back. It can be a discount, a lock on the assessment or millage rate, or both. | Local governing body, industrial development agency, or economic development authority | Yes, and in many states only by ordinance after a public hearing. |
| Tax increment financing (TIF) | Freezes the tax base in a district and diverts the growth above that base to pay for infrastructure or debt inside the district for a term of years. Other taxing bodies, including schools, keep receiving only the frozen base until the district closes. | Municipality or county creating the district | Yes, at district creation and at each amendment. |
| Community benefit payment or agreement | A contractual payment or commitment separate from taxes: cash to the county, road money, school partnerships, hiring and wage commitments, noise and setback limits. | Negotiated between the developer and the local government | Yes. This is the part with the most room to move. |
| Road use and decommissioning security | Not a tax at all. A bond, letter of credit, or cash security that pays to repair haul routes and to tear the facility down and restore the site. The only terms that protect the community from a cost rather than promising it a benefit. | Negotiated, typically inside a road use agreement and a decommissioning agreement | Yes, and the amount and the form of the security are both negotiable. |
Two practical consequences follow. First, if your objection is to the statewide sales tax exemption, the county commission is the wrong room; that argument belongs to the legislature, and several legislatures are now having it. Second, the terms most within local reach are the ones that show up last in the process and get the least public attention: the community benefit schedule, the road security amount, and the decommissioning security.
What the statutes actually require
The qualifying thresholds are the clearest evidence of what these programs are designed to reward. In every state below, the binding test is a capital investment number. Job requirements, where they exist at all, are small relative to the investment, and in Iowa there is no job requirement in the exemption statute at all.
| State and statute | Investment minimum | Jobs and wages | Term and sunset |
|---|---|---|---|
| Ohio R.C. 122.175 | "at least one hundred million dollars at the project site," over three consecutive calendar years for projects beginning in or after 2015 (four years for 2014, six for 2013) | "at least one million five hundred thousand dollars" in annual compensation subject to withholding, beginning on or after the 25th month of the agreement. No headcount minimum | Term "determined by the tax credit authority," with the exemption not to exceed "one hundred per cent" of the tax otherwise owed. No statutory maximum term. Covers equipment, cooling, electrical infrastructure, construction materials, and delivery, installation, and repair charges |
| Texas Tax Code 151.359 (qualifying data center) | "at least $200 million in that particular data center over a five-year period" | "at least 20 qualifying jobs in the county," each paying "at least 120 percent of the county average weekly wage" | 10 years at $200 million to under $250 million; 15 years at $250 million or more |
| Texas Tax Code 151.3595 (large data center project) | "at least $500 million," on a single parcel with at least 250,000 square feet | "at least 40 qualifying jobs," at 120 percent of the county average weekly wage | 20 years from certification |
| Virginia Code 58.1-609.3(18) | $150 million of new capital investment; $70 million in a qualifying distressed locality | 50 new full-time jobs paying "at least one and one-half times the prevailing average wage in that locality"; 10 jobs in a distressed locality | Exemption runs through June 30, 2035, with longer terms available under the adjacent subdivision |
| Georgia O.C.G.A. 48-8-3(68.1) | Tiered by county population: $250 million in counties over 50,000; $75 million in counties of 30,001 to 50,000; $25 million in counties of 30,000 or fewer, in each case "in aggregate expenditures incurred over any consecutive seven-year period" | 25, 10, or 5 "new quality jobs" on the same population tiers | Purchases exempt from July 1, 2018 through December 31, 2031; the paragraph "shall stand repealed by operation of law on January 1, 2032." Missing the threshold requires repayment of all exempted tax with interest within 90 days |
| Iowa Code 423.3(95) | "a minimum investment in an Iowa physical location of two hundred million dollars within the first six years of operation," at a site of at least 5,000 square feet | None stated in the exemption. The listed conditions are the investment, the square footage, sustainable design compliance, registration, and an annual report | Open-ended for the equipment. Electricity and backup generator fuel are exempt for the first 10 years for new construction in cities over 30,000 population and 15 years elsewhere, for property completed on or after June 6, 2025 |
Read the Georgia tier again, because it is the pattern that matters most to small counties. A rural Georgia county of under 30,001 people gives up the sales tax on a data center campus in exchange for a statutory promise of five jobs. Read the Ohio line the same way: $100 million of investment and $1.5 million of payroll, which at a $75,000 average salary is roughly 20 people, with no headcount floor at all.
How common is this? Virginia's legislative auditors counted 34 states with a data center sales tax exemption in 2024, and noted that "all states bordering Virginia provide a sales tax exemption to data centers." Good Jobs First put the count at 36 states in January 2026 and referred to 37 states in June 2026. Nebraska eliminated its data center sales tax exemption in 2026, according to Good Jobs First. Nebraska then went further: Executive Order 26-17, signed July 20, 2026, barred new data centers from the ImagiNE Nebraska Act incentive program, and LB1010, approved April 14, 2026, now requires data center operators to bear decommissioning costs and sign community benefit agreements with affected communities. See our Nebraska page for the full sequence.
What the exemptions cost, in the states' own numbers
Until recently most states did not publish a figure. The ones that now do have revised their estimates upward repeatedly, and by large multiples. Good Jobs First, a subsidy watchdog that tracks these programs, compiled the following in its June 12, 2026 report "Even Cloudier with a Greater Loss of Spending Control." These are the states' own disclosures, gathered by Good Jobs First:
| State | Reported or projected annual cost | Note |
|---|---|---|
| Georgia | $1.9 billion (2025), $2.5 billion (2026), $3 billion (2027) | State and local sales tax combined. The FY2026 projection was raised by 664 percent in January 2026. Georgia localities alone are estimated to lose $1.1 billion in 2026 and $1.4 billion in 2027 |
| Virginia | $1.94 billion (FY2025) | State and local actual costs, after three successive upward revisions between December 2025 and February 2026 |
| Ohio | $1.6 billion (2025) | State share only, against an initial projection of $135.8 million. In 2024 the state lost $555 million and localities a further $166.8 million |
| Texas | $1 billion (2025) rising to $1.6 billion (2028) | State revenue only; Texas does not abate the local sales tax. Cumulative losses of roughly $9 billion projected between 2025 and 2030 |
| Indiana | $655.6 million, 2019 through 2025 | More than 93 percent went to one company, Amazon, which received $50.5 million in 2024 and $561 million in 2025 |
| Pennsylvania | $41 million (2025) to $260 million (2028) | State revenue estimates only |
| North Carolina | $45 million to $57 million annually | A 2015 fiscal note had projected roughly $4 million a year |
The Ohio number produced a policy response. On the heels of reporting by Signal Ohio that the break cost more than $1.5 billion in 2025, Governor Mike DeWine directed state officials to pause consideration of new data center sales tax exemption applications, a step Policy Matters Ohio described on May 28, 2026 as "a clear acknowledgment that something has gone seriously wrong." The pause does not touch existing agreements, which is where the 2025 cost came from.
Two independent state evaluations have asked the harder question, which is whether the exemption pays for itself. Virginia's Joint Legislative Audit and Review Commission found in its December 2024 study that the data center exemption returns 48 cents in state revenue per dollar spent, against 41 cents for the average Virginia incentive, and concluded that "the data center exemption does not pay for itself when considering just the state portion of the exemption cost and the state return in revenue." Georgia's state auditor, using a report prepared by the University of Georgia's Carl Vinson Institute of Government in December 2022, modeled a hypothetical $800 million hyperscale facility and estimated forgone state revenue of approximately $80 million against roughly $19.4 million in additional state taxes during construction and $250,000 to $275,000 a year from operations. That 2022 evaluation assumed 90 percent of Georgia data centers would not exist without the exemption. Good Jobs First reports that a December 2025 update of the same Georgia audit found the opposite direction of travel: that 70 percent of data center projects would have located in Georgia even without the subsidy.
Real packages on record
Four deals, all documented, showing the full range from no abatement at all to a 30 year, 65 percent write-down.
Barber County, Kansas: Google Project Helium, approved August 31, 2026. No abatement. The county's own deal summary and press release state the terms. Google pays 100 percent of applicable ad valorem property taxes with no property tax abatement, projected at approximately $327.5 million over 20 years to local taxing jurisdictions, about $138.4 million of it to the county. For scale, the county's entire assessed valuation is $115,465,673 and its total 2026 ad valorem tax is $6,768,132; the project's projected assessed value alone is $116,875,000. On top of the taxes: $5.5 million in community benefit payments on a published schedule of $500,000 by the end of 2026, $3 million in 2027, $1 million in 2028, and $1 million in 2029; an estimated $1 million to $1.5 million a year in sales tax on Google's electricity purchases; $5 million in road security with pre-construction and post-construction road inventories; and decommissioning security "equal to 125% of the estimated cost to decommission the project." The agreement guarantees a minimum of 300 full time equivalent jobs by the fifth year of operations.
The county headline is not the whole tax picture, though. No county abatement does not mean no subsidy, because the two taxes are levied by different governments. Kansas Senate Bill 98 created a separate state sales tax exemption for a qualified data center, and its enrolled text sets the terms: a firm must invest "at least $250,000,000 in the aggregate by the fifth year of operations," must create "and maintain at least 20 new jobs" within two calendar years of commencing operations, and in exchange "the sales tax exemption shall be valid for 20 years after the date of commencement of operations." Eligible costs expressly exclude the cost of electricity, which is why Barber County still expects sales tax revenue on Google's power purchases. Taking the statute at its floor, and this division is ours, $250 million of qualifying investment against 20 required jobs is $12.5 million per required job, held for twenty years. The county negotiated its property tax to full value. The state exemption sits on top of that and was not the county's to trade away. Two provisions in the same bill cut the other way and are rarely mentioned: SB 98 prohibits public utilities from authorizing discounted economic development electric rates for data centers, and it requires a qualified data center to be reviewed and approved by the Kansas intelligence fusion center before public financial assistance is awarded.
Our report on the Barber County development agreement covers how it was approved, which is its own story.
Effingham County, Georgia: OpenAI, memorandum of understanding signed July 21, 2026. WTOC reported from county records that the PILOT assesses the property at 25 percent of value instead of the standard 40 percent, cutting the property tax bill by 37.5 percent annually for the first 15 years of each project phase, and locks the calculation at the 2026 millage rate for the full 15 years, insulating the company from later local rate increases. The station reported a $20 billion project, at least 400 new long-term jobs averaging 80 per phase, and a buyout option letting the company repurchase the property from the county for $10 when the abatement period ends. The memorandum was signed on July 21 and the project was announced publicly on July 22.
Arkansas: Google in Little Rock, West Memphis, and Conway. The Arkansas Democrat-Gazette reported on June 27, 2026 that PILOT agreements give the company the maximum 65 percent tax abatement for 30 years on both real estate and personal property. On the Little Rock project, a $1 billion first building of about 300,000 square feet with potential expansion to 1.43 million square feet, the paper reported the site would generate over $12.8 million in property tax revenue without the abatement and over $5 million annually with it.
Mount Pleasant, Wisconsin: Microsoft, November 2023. No public incentives. Wisconsin Public Radio reported that under the development agreement "no additional financial incentives for Microsoft will be required by either the village or the county." Instead Microsoft guaranteed a minimum assessed value of $1.4 billion by January 1, 2028, bought more than 1,000 acres for $100 million, and gave the village the ability to close Tax Incremental District 5, created for Foxconn in 2017 and originally scheduled to close in 2047, seven to 14 years early. That is what a TIF looks like when it works in the community's favor: the increment retires the district's debt and then flows to the ordinary taxing bodies.
The jobs arithmetic
A hyperscale campus is one of the most capital intensive structures a community will ever host and one of the least labor intensive once it is running. Virginia's legislative auditors put the operating headcount plainly: several data center representatives told them "a typical 250,000-square-foot data center may have approximately 50 full-time workers," about half of them contract workers, which the auditors compared with one employee per 650 square feet for a distribution center. Across the entire Virginia industry, the largest data center market in the world, direct employees and contract workers together accounted for over 8,000 full-time jobs in FY23, and the industry added more than 800 new full-time jobs that year. Eighty percent of the annual jobs attributed to the industry come from the construction phase, which means the economic case depends on continuing to build.
Set those headcounts beside the subsidies. The divisions below are ours, using published figures:
- Virginia, one year of the exemption. $928.6 million in FY23 savings against the more than 8,000 existing full-time jobs is roughly $116,000 per job in a single year. Against the 800 new full-time jobs added that year it is roughly $1.16 million per new job.
- Georgia, the auditor's own model. Approximately $80 million of forgone state sales tax on an $800 million hyperscale facility with 50 permanent employees is about $1.6 million of forgone state revenue per permanent job, before any local property tax abatement.
- Effingham County, Georgia. A $20 billion investment against at least 400 promised long-term jobs is about $50 million of capital investment per permanent job, on a property assessed at 25 percent instead of 40 percent for 15 years per phase.
- Barber County, Kansas. 300 guaranteed full time equivalents by year five, with 100 percent of property taxes paid. The comparison is not to a cost per job but to what the county would have received had it abated.
Good Jobs First states the general case this way: because these subsidies "favor capital investment, not job creation," taxpayer costs "routinely exceed $1 million per permanent job." The counterweight, and it is a real one, is that Virginia's auditors scored the exemption at 84 jobs added per $1 million spent against 58 for the average Virginia incentive, because construction and supplier employment are counted. Whether a community values a two year construction boom at that price is a political judgment, not an arithmetic one. The arithmetic only has to be on the table.
The other side of the ledger
Communities that approve these projects are not imagining the upside, and a page that ignored it would not be useful. The documented benefits:
- Local tax revenue can be transformative, especially where equipment is taxable. Virginia's auditors found that across the five localities with mature data center markets, data center revenue ranged from less than 1 percent to 31 percent of total local tax revenue. In Loudoun County it was 31 percent and in Prince William 7 percent. Localities used the money to lower real estate tax rates and to build revenue stabilization and reserve funds.
- Abatements expire. A 15 or 30 year PILOT ends, and the property joins the ordinary tax roll at full value, assuming the agreement does not contain a buyout or an extension. That is the central promise made to a county, and it is worth reading the exit provisions to see whether it holds. Effingham County's $10 repurchase option is exactly the kind of clause that determines the answer.
- Infrastructure gets built. Georgia's auditors noted that data center construction "may lead to needed investment" in electricity and water infrastructure and can improve an area's broadband, while also flagging that the facilities are high electricity and water users that could strain local resources during droughts, heat waves, or cold snaps.
- Construction employment is large and real. Georgia's evaluation estimated roughly 4,200 construction jobs and 7,300 total jobs during the roughly two year construction phase of a single $800 million facility.
- Security instruments protect the community. Road and decommissioning securities are the terms that cost the developer money if things go wrong, and they are the ones most often left out. Barber County's $5 million road security and 125 percent decommissioning security are a template worth quoting at a hearing.
The honest summary is that a data center can be a large net gain for a local budget and a net loss for a state budget at the same time, because the property tax accrues locally while the sales tax exemption is mostly a state cost. That is precisely why the two decisions get made in different rooms.
What a resident can request, and when
Almost all of this is public. The problem is that it is public in pieces, held by different offices, and released on request rather than published. Ask for these by name, in writing, under your state's public records act.
- The development agreement and every exhibit, including the road use agreement, the decommissioning agreement and the form and amount of the security, and any community benefit agreement with its payment schedule.
- The abatement or exemption resolution or ordinance, plus the staff report or fiscal analysis prepared for the body that voted on it, and the minutes of that vote.
- The PILOT financial agreement and its full payment schedule, including the assessment ratio, the millage lock if any, the term, escalators, clawbacks, and any buyout or repurchase option. New Jersey's guidance to its own municipalities, Local Finance Notice 2026-13 of August 25, 2026, is a good model of what these documents contain: a long-term PILOT there must be approved by ordinance after a public hearing, with notice to the county chief financial officer and the county commissioners' clerk, cannot exceed 30 years from project completion or 35 years from execution, and requires the entity to submit an annual audit to the mayor and governing body within 90 days of its fiscal year end. A short-term agreement under the state's Five-Year Law must be filed with the state within 30 days of execution. Ask your own jurisdiction which of those documents exists and where it was filed.
- The application to the state program. In Ohio that is the agreement with the tax credit authority. In Georgia it is the application, the certificate of exemption, and the annual reports the operator must file on taxes exempted and quality jobs created. In Virginia, companies using the exemption report annual eligible expenditures and benefits to the state economic development partnership. In Iowa the operator must register and file an annual report each January 31.
- The TIF district's project plan, boundary, base value, and developer agreement, plus any minimum assessed value guarantee, and the annual report showing what the district has collected and what it still owes.
Then work out the calendar, because this is where residents most often lose. The land use decision, a rezoning, a special or conditional use permit, or a site plan, is one vote before one body with a statutory appeal deadline that is commonly 30 days and as short as 10 in Texas. The tax decision is frequently a different vote, before a different body, on a different night, and often has no equivalent appeal clock at all. Our guide to zoning appeal deadlines by state quotes the operative statute in twelve states, and only the land use clock is in it. Ask the clerk three questions in writing: which body approves the tax agreement, when is it noticed for hearing, and is the vote scheduled before or after the zoning vote. Effingham County's memorandum was signed the day before the announcement, which is a reminder that by the time a project is public the tax terms may already be settled.
Finally, be clear about which fight you are in. If the objection is that a statewide exemption is too generous, that is legislative work, and legislatures in Ohio, Georgia, and elsewhere are actively revisiting it. If the objection is that a local abatement gave away too much, that is a vote, a record, and an election. If the objection is that the facility itself is harming your property, through noise, water, air, or construction damage, that is a different body of law entirely; our guides on fighting a proposed data center and who pays for data center power cover the first two, and a free case review connects you with an independent attorney in our network who handles data center cases in your state, at no cost and with no obligation. We do not give legal or tax advice, and nothing on this page is a substitute for counsel who has read your county's actual agreement.
Frequently asked questions
What is the data center tax abatement in Ohio?
Ohio Revised Code 122.175 lets the state tax credit authority exempt an eligible computer data center business from sales and use tax on data center equipment, cooling systems, electrical infrastructure, and construction materials. The project must invest at least $100 million at the site, generally within three consecutive calendar years, and pay at least $1.5 million a year in compensation subject to withholding. The exemption may be up to 100 percent and the term is set by the authority. Governor DeWine directed a pause on new applications in May 2026 after the program's 2025 cost came in far above projections.
What is the data center tax abatement in Texas?
Texas Tax Code 151.359 exempts qualifying data centers from state sales tax on equipment. The facility must have at least 100,000 square feet used by a single qualifying occupant, invest at least $200 million over five years, and create at least 20 jobs paying at least 120 percent of the county average weekly wage. The exemption runs 10 years for investments of $200 million to under $250 million and 15 years at $250 million or more. Section 151.3595 covers large data center projects of at least 250,000 square feet and $500 million with 40 jobs, for 20 years. Texas does not abate the local sales tax.
How much do data center tax breaks cost states?
According to Good Jobs First's June 2026 compilation of state disclosures, Georgia projected $2.5 billion for 2026, Virginia reported $1.94 billion for FY2025, Ohio reported $1.6 billion for 2025 against an initial projection of $135.8 million, and Texas projected $1.3 billion for FY2026 rising to $1.6 billion by 2028. Several states have revised their estimates upward by hundreds of percent as construction accelerated, and 14 states publish no figure at all.
Do data centers pay property taxes?
It depends entirely on the local agreement. Some pay in full: Barber County, Kansas approved Google's Project Helium with 100 percent of ad valorem property taxes and no abatement, projected at about $327.5 million over 20 years to local taxing jurisdictions. Others pay a fraction: Arkansas approved 65 percent abatements for 30 years on Google projects, and Effingham County, Georgia approved a PILOT assessing an OpenAI project at 25 percent of value instead of 40 percent for 15 years per phase. The sales tax exemption on equipment is separate and is granted by state statute rather than locally.
What is a PILOT agreement for a data center?
A payment in lieu of taxes agreement replaces the ordinary property tax bill with a negotiated schedule of payments, often by placing title with a development authority that leases the property back to the company. Terms commonly include a reduced assessment ratio, a locked millage rate, a fixed number of years, and sometimes an option for the company to buy the property back at the end. In New Jersey, for example, a long-term PILOT must be adopted by ordinance after a public hearing and cannot exceed 30 years from project completion.
How many states have data center sales tax exemptions?
Virginia's Joint Legislative Audit and Review Commission counted 34 states with a data center sales tax exemption in 2024 and noted that every state bordering Virginia has one. Good Jobs First counted 36 states in January 2026 and referenced 37 states in June 2026. Nebraska eliminated its exemption in 2026, according to Good Jobs First, and an executive order signed that July also barred new data centers from the state's main incentive program.
How many jobs does a data center actually create?
Fewer than most announcements imply. Virginia's legislative auditors reported that industry representatives described a typical 250,000 square foot data center as having about 50 full-time workers, roughly half of them contractors, and found that data centers statewide accounted for over 8,000 full-time jobs in FY23 while adding about 800 new ones that year. Most employment from these projects is in construction, which is temporary. Permanent operations jobs do tend to pay above average wages.
Can a community stop a data center tax abatement?
A local abatement, PILOT, or TIF is a vote by a county commission, city council, school board, or development authority, and those bodies can decline it or negotiate different terms, usually at a noticed public meeting. A statewide sales and use tax exemption is different: if a project meets the statutory threshold it qualifies automatically, and changing that requires the legislature. Residents can request the agreements and fiscal analyses under state public records law before the vote.
Article sources
Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.
- 1.Kansas Senate Bill 98, enrolled text: qualified data center sales tax exemption, $250,000,000 minimum investment, 20 new jobs, 20 year term
- 2.Nebraska Legislature: LB1010 (2026), Large Load Customer Regulation Act and data center requirements, approved April 14, 2026
- 3.Ohio Revised Code 122.175, tax exemption for computer data center equipment
- 4.Texas Tax Code 151.359, property used in certain data centers, temporary state sales tax exemption
- 5.Texas Tax Code 151.3595, property used in certain large data center projects
- 6.Virginia Code 58.1-609.3, commercial and industrial sales and use tax exemptions, subdivision 18 (data centers)
- 7.O.C.G.A. 48-8-3(68.1), Georgia high-technology data center equipment exemption and minimum investment thresholds
- 8.Iowa Code 423.3(95), sales tax exemption for data center businesses (Iowa Legislature)
- 9.JLARC, Data Centers in Virginia, Report 598 (December 9, 2024): exemption value, jobs, local revenue share, and return per dollar
- 10.JLARC landing page, Data Centers in Virginia (2024)
- 11.Georgia Department of Audits and Accounts, Tax Incentive Evaluation: High-Tech Data Center Sales Tax Exemption (December 2022), prepared by the Carl Vinson Institute of Government
- 12.Good Jobs First: Even Cloudier with a Greater Loss of Spending Control: How Data Center Tax Abatements Undermine Public Budgets (June 12, 2026)
- 13.Good Jobs First: Clouded Judgment: Data Center Subsidies Don't Add Up (published May 8, 2025, updated January 23, 2026)
- 14.Policy Matters Ohio statement: Pause on data center tax break won't address soaring costs (May 28, 2026)
- 15.Barber County, Kansas: Summary of agreement terms with Google regarding Project Helium (August 31, 2026)
- 16.Barber County, Kansas press release: Commissioners announce agreement terms for Project Helium (August 31, 2026)
- 17.WTOC: Records show Effingham County leaders finalized tax break for $20B OpenAI data center day before public announcement (July 29, 2026)
- 18.Arkansas Democrat-Gazette: Data centers planned for Arkansas poised to get millions of dollars in property tax breaks (June 27, 2026)
- 19.Wisconsin Public Radio: Mount Pleasant deal with Microsoft will include no public financial incentives, under agreement (November 13, 2023)
- 20.New Jersey Division of Local Government Services, Local Finance Notice 2026-13, Data Centers (August 25, 2026)
Related reading
- Who Pays for Data Center Power: The Ratepayer Tracker
The numbers behind the electric bill fight: PJM's capacity price rose from $28.92 to $333.44 per megawatt-day in three years, data centers account for $29.4 billion of the last four auctions' capacity costs by the market monitor's count, and the average PJM household faces an estimated $70 a month more by 2028. The running record of what regulators have found, which 23 states have answered with large load tariffs, what those tariffs require, and what a resident can do about a bill.
- How Long Do You Have to Challenge a Data Center Approval? Appeal Deadlines in 12 States
The clock to challenge a data center rezoning, special use permit, or zoning board decision runs from 10 days in Texas to 90 days in Illinois. Statute by statute for 12 states, what starts the clock, which court hears it, and the standing trap that ends cases before they start. Confirm every deadline with counsel.
- How to Fight a Proposed Data Center Before It Breaks Ground
Approval fights are the most successful category of data center litigation. Here is the playbook: reading the rezoning file, spotting notice and open meetings defects, organizing neighbors, referendums and recalls, moratoriums, and the short appeal clocks that decide everything.
- Data Centers and Your Electric Bill: Who Pays for the Power Boom?
When a data center demands power plant-scale electricity, the grid upgrades land on everyone's bills unless regulators stop it. No consumer class action exists yet; the fight lives at utility commissions, and residents can join it. Here is how the cost shift works and how to participate.
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us