Sue Data Centers

Data Center Registry

PowerHouse Grand Prairie Campus

Grand Prairie, Ellis County, Texas · All 12 PowerHouse Data Centers sites · Every PowerHouse and Hillwood case on our tracker

Under constructionNo reception on recordAI confirmedRecord updated July 8, 2026

PowerHouse Grand Prairie Campus is a data center under construction in Grand Prairie, Texas (Ellis County), operated by PowerHouse Data Centers. The public record puts it at 1.8 GW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
PowerHouse Data Centers
Facility type
Data center, AI use confirmed
Location
Grand Prairie, Ellis County, TX
Coordinates
32.6200, -97.0200
Power capacity
1.8 GW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Oncor
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2026
    Under construction
    PowerHouse and Provident developing a 1.8 GW campus in the DFW area (Grand Prairie): 24 buildings across three phases, 1.8 GW switchyard Source: Data Center Dynamics

Opposition and litigation at this site

The record carries no reception finding for PowerHouse Grand Prairie Campus in Grand Prairie, Ellis County, Texas, but it does carry this note as of July 8, 2026: The site was newly rezoned with all permits secured (Feb 2025); no independent reporting documents community support or opposition specific to this Ellis County campus as of 2026-07-08.

Power and water

On-site 1.8 GW switchyard; ERCOT approved the first 500 MW tranche. Provident CEO Leon Backes said the company spent 'the past two years working closely with ERCOT and Oncor.' Oncor is Ellis County's incumbent transmission/distribution utility.

Notes on the record

1.8 GW DFW-area campus (Grand Prairie): 24 buildings across three phases with an on-site 1.8 GW switchyard. Grand Prairie spans Dallas/Tarrant/Ellis counties; the campus is in the Ellis County (southern) portion. Coordinates reflect the southern Grand Prairie / Ellis County zone. Provident cited 'at least $5B in direct construction impact' over the multi-year build-out (Bisnow) and ~$300M for one 360,000-sq-ft building (Dallas Innovates) - neither a confirmed campus capex pledge -> investmentUsd omitted. Ellis County adopted Chapter 312 abatement guidelines (~Oct 2025, $50M threshold); no executed abatement agreement for this campus was found.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the PowerHouse Grand Prairie Campus in Grand Prairie?

The record carries no reception finding for PowerHouse Grand Prairie Campus in Grand Prairie, Ellis County, Texas, but it does carry this note as of July 8, 2026: The site was newly rezoned with all permits secured (Feb 2025); no independent reporting documents community support or opposition specific to this Ellis County campus as of 2026-07-08.

Has anyone filed a lawsuit over the PowerHouse Grand Prairie Campus?

No lawsuit over PowerHouse Grand Prairie Campus appears in the record we track as of July 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does PowerHouse Grand Prairie Campus use?

No water withdrawal figure for PowerHouse Grand Prairie Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates PowerHouse Grand Prairie Campus, and how big is it?

PowerHouse Data Centers is the operator on record. We hold 12 sites for that company across the registry. Capacity on record is 1.8 GW.

How to cite this page

SueDataCenters.org Data Center Registry, "PowerHouse Grand Prairie Campus," updated July 8, 2026, https://suedatacenters.org/data-centers/powerhouse-provident-grand-prairie-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/powerhouse-provident-grand-prairie-tx, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.PowerHouse and Provident to develop 1.8GW campus in DFW, Texas · Data Center Dynamics · retrieved July 7, 2026
  2. 2.Provident, PowerHouse partner on 768-acre Texas data center campus · Bisnow · retrieved July 8, 2026
  3. 3.DOE-funded UTA project tackles cooling costs amid AI data center demand · Dallas Innovates · retrieved July 8, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us