Data Center Registry
Red Oak Campus
Red Oak, Ellis County, Texas · All 6 Compass Datacenters sites · Every QTS and Compass Datacenters case on our tracker
Red Oak Campus is a proposed data center in Red Oak, Texas (Ellis County), operated by Compass Datacenters. The public record puts it at a reported $600 million investment. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Compass Datacenters
- Facility type
- Data center
- Location
- Red Oak, Ellis County, TX
- Coordinates
- 32.5380, -96.8044 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- $600 million
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- 2026ProposedStatus change recorded. Source: Data Center Dynamics
Opposition and litigation at this site
Partly. Both documented support and documented opposition to Red Oak Campus in Red Oak, Ellis County, Texas appear in the record, with no clear majority position. Red Oak City Council approved rezoning for the Compass campus expansion on a 4-1 vote (May 2026) despite residents packing chambers to protest grid stress, noise, traffic, water use, and property-value concerns.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Red Oak City Council approved rezoning for the Compass campus expansion on a 4-1 vote (May 2026) despite residents packing chambers to protest grid stress, noise, traffic, water use, and property-value concerns.
Notes on the record
Second DFW-area Compass site (buildings 3/4). Distinct operator/site from DataBank's separate Red Oak, TX campus (same town, different companies).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Google Red Oak Campus · Red Oak · Google2 mi · Operating · Mixed reception
- STACK DFW02 (Lancaster) · Lancaster · STACK Infrastructure5 mi · Under construction · 500 MW
- Red Oak Campus · Red Oak · DataBank5 mi · Under construction · 480 MW
- PowerHouse Grand Prairie Campus · Grand Prairie · PowerHouse Data Centers14 mi · Under construction · 1.8 GW
- Aligned DFW-03 · Mansfield · Aligned Data Centers16 mi · Operating
- Crow Holdings Stemmons Corridor Data Center Campus · Dallas · Crow Holdings (developed and leased by CleanArc Data Centers)16 mi · Proposed · 245 MW
- Flexential Dallas - Downtown Dallas · Dallas · Flexential18 mi · Operating
- TierPoint Dallas · Dallas · TierPoint19 mi · Operating
Questions people ask about this site
Is there opposition to the Red Oak Campus in Red Oak?
Partly. Both documented support and documented opposition to Red Oak Campus in Red Oak, Ellis County, Texas appear in the record, with no clear majority position. Red Oak City Council approved rezoning for the Compass campus expansion on a 4-1 vote (May 2026) despite residents packing chambers to protest grid stress, noise, traffic, water use, and property-value concerns.
Has anyone filed a lawsuit over the Red Oak Campus?
No lawsuit over Red Oak Campus appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Red Oak Campus use?
No water withdrawal figure for Red Oak Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Red Oak Campus, and how big is it?
Compass Datacenters is the operator on record. We hold 6 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Red Oak Campus," updated July 26, 2026, https://suedatacenters.org/data-centers/compass-red-oak-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/compass-red-oak-tx, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Compass Datacenters looks to expand Red Oak campus · Data Center Dynamics · retrieved July 17, 2026
- 2.DeSoto Tribune, Red Oak data center sparks controversy as expansion moves forward · retrieved July 26, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us