Facility record
Permitted
- Operator
- Warrenton Group (TWG Data)
- Facility type
- Data center
- Location
- 2233 Halifax Road, Petersburg, VA
- Coordinates
- 37.1770, -77.4180 (approximate)
- Power capacity
- Not established from a public source
- Land
- 175 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- February 2026PermittedReceived zoning approval from Petersburg City Council in 2025; council approved an amendment in February 2026 enlarging the project footprint with three additional parcels for access and wetland mitigation. No site plan had been submitted since that approval as of the reporting date. Source: Richmond BizSense
Opposition and litigation at this site
Nothing on record as of September 9, 2026. No lawsuit, organized opposition, or contested hearing over TWG Data Halifax Road Campus (former Collier Yard) in Petersburg, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Six data center buildings on a 175-acre site, the former CSX Collier Yard property, now city-owned. Developed through Warrenton Group's TWG Data arm, with engineering by Timmons Group. No capacity or investment figure published. Coordinates are an approximate geocode of the cited street address.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- NuVu County Drive Data Center Campus · Petersburg · NuVu Real Estate3 mi · Permitted · 300 MW
- Menlo Digital Richmond Virginia Data Center (Jamestown Drive) · Petersburg · Menlo Digital3 mi · Permitted · 104 MW
- Wagner Road Data Center Campus · Petersburg · Wagner Properties4 mi · Permitted
- Bermuda Hundred Data Center (Old Bermuda Hundred Road) · Chester · Undisclosed (landowner: Washington Single Family Fund3)11 mi · Proposed · In litigation
- Chirisa Technology Park, Richmond (Chester) · Chester · PowerHouse Data Centers12 mi · Under construction · 120 MW · Mixed reception
- Project Peanut · Chester · Google13 mi · Under construction · Contested
- PowerHouse CTP-02 · Chester · PowerHouse Data Centers14 mi · Under construction · 50 MW
- QTS White Oak Technology Park II (RIC5) · Sandston · QTS Data Centers23 mi · Permitted · Mixed reception
Questions people ask about this site
Is there opposition to the TWG Data Halifax Road Campus (former Collier Yard) in Petersburg?
Nothing on record as of September 9, 2026. No lawsuit, organized opposition, or contested hearing over TWG Data Halifax Road Campus (former Collier Yard) in Petersburg, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the TWG Data Halifax Road Campus (former Collier Yard)?
No lawsuit over TWG Data Halifax Road Campus (former Collier Yard) appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does TWG Data Halifax Road Campus (former Collier Yard) use?
No water withdrawal figure for TWG Data Halifax Road Campus (former Collier Yard) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates TWG Data Halifax Road Campus (former Collier Yard), and how big is it?
Warrenton Group (TWG Data) is the operator on record. No capacity figure is on record for this site. The site is recorded at 175 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "TWG Data Halifax Road Campus (former Collier Yard)," updated September 9, 2026, https://suedatacenters.org/data-centers/warrenton-group-halifax-road-petersburg-va.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/warrenton-group-halifax-road-petersburg-va, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Documents reveal details on several data center projects in Petersburg's pipeline (archived) · Richmond BizSense · retrieved August 27, 2026
- 2.Documents reveal details on several data center projects in Petersburg's pipeline · Richmond BizSense (via Internet Archive) · retrieved September 9, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us