Data Center Registry
TECfusions Keystone Connect
Upper Burrell Township, Westmoreland County, Pennsylvania
TECfusions Keystone Connect is a proposed data center in Upper Burrell Township, Pennsylvania (Westmoreland County), operated by TECfusions. The public record puts it at announced January 14, 2025, 3 GW planned, 1,395 acres. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- TECfusions
- Facility type
- Data center, AI use confirmed
- Location
- Upper Burrell Township, Westmoreland County, PA
- Coordinates
- 40.5817, -79.7050 (approximate)
- Power capacity
- 12 MW operating; 3 GW planned
- Land
- 1,395 acres
- Investment
- Not established from a public source
- Announced
- January 14, 2025
- Utility
- Not established from a public source
- Power source
- On site gas
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Pennsylvania Redevelopment Assistance Capital Program (RACP), $2 million, Pennsylvania, 2025
- Community reception
- In litigation
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 14, 2025ProposedTECfusions announced acquisition of the 1,395-acre former Alcoa R&D campus and a phased 3 GW AI/HPC campus. Source: TECfusions via PR Newswire
Opposition and litigation at this site
Yes. TECfusions Keystone Connect in Upper Burrell Township, Westmoreland County, Pennsylvania is or has been the subject of litigation over its siting, permitting, or operation. Upper Burrell Township passed a 180-day data-center moratorium in May 2026, but it did not apply to permits already granted to TECfusions for 'Building J', and supervisors approved a land development plan for that building on Aug.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Upper Burrell Township passed a 180-day data-center moratorium in May 2026, but it did not apply to permits already granted to TECfusions for 'Building J', and supervisors approved a land development plan for that building on Aug. 5, 2026 despite the moratorium. Protect PT (an environmental advocacy group) and New Kensington residents Fuller and Allen Uhler filed a land-use appeal against township approvals with the Westmoreland County Court of Common Pleas. More than 50 residents attended an August supervisors meeting, most opposed.
Power and water
On-site natural gas generation with dual utility feeds and microgrid capability; the developer says discussions are under way to export excess power to the local grid.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Pennsylvania Redevelopment Assistance Capital Program (RACP) | $2 million | Pennsylvania | 2025 |
Notes on the record
Adaptive reuse of the former Alcoa research and development campus in Upper Burrell, Westmoreland County: 1,395 acres, 3 GW planned over a six-year buildout, with 12 MW described as immediately available in existing buildings. Awarded a $2 million Pennsylvania RACP grant. Investment total not disclosed by the developer.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Springdale Data Center (former Cheswick Generating Station) · Springdale · Allegheny DC Property Co., LLC5 mi · Permitted · 180 MW · Contested
- Stowe Township Data Center (former railcar plant) · Stowe Township · SunCap Industries20 mi · Proposed · Mixed reception
- Expedient PIT1 (Green Tree / Pittsburgh South) · Pittsburgh · Expedient21 mi · Operating · 1.8 MW
- Ardent Data Centers Pittsburgh (McKees Rocks) · McKees Rocks · Ardent Data Centers (Northern Data Group)21 mi · Operating · 20 MW
- Aliquippa Data Center (former J&L Steel site) · Aliquippa · Five 9s Digital28 mi · Proposed · 496 MW
- Homer City Energy Campus · Homer City · Homer City Redevelopment29 mi · Under construction · 4.5 GW · Mixed reception
Questions people ask about this site
Is there opposition to the TECfusions Keystone Connect data center in Upper Burrell Township?
Yes. TECfusions Keystone Connect in Upper Burrell Township, Westmoreland County, Pennsylvania is or has been the subject of litigation over its siting, permitting, or operation. Upper Burrell Township passed a 180-day data-center moratorium in May 2026, but it did not apply to permits already granted to TECfusions for 'Building J', and supervisors approved a land development plan for that building on Aug.
Has anyone filed a lawsuit over the TECfusions Keystone Connect data center?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does TECfusions Keystone Connect use?
No water withdrawal figure for TECfusions Keystone Connect is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates TECfusions Keystone Connect, and how big is it?
TECfusions is the operator on record. Capacity on record is 3 GW. The site is recorded at 1395 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "TECfusions Keystone Connect," updated September 10, 2026, https://suedatacenters.org/data-centers/tecfusions-keystone-connect-upper-burrell-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tecfusions-keystone-connect-upper-burrell-pa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.TECfusions Unveils Massive 1400-Acre Data Center Project in Pennsylvania, Revitalizing Former Industrial Plant · TECfusions via PR Newswire · retrieved August 17, 2026
- 2.Data Centers in Pennsylvania, Project List & Locations (TECfusions Keystone Connect, Westmoreland, 3,000 MW planned) · Cleanview · retrieved August 17, 2026
- 3.Upper Burrell residents decry transparency as data center progresses despite moratorium and a lawsuit · PublicSource · retrieved September 10, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us