Homer City Energy Campus

Homer City, Indiana County, Pennsylvania

Under constructionMixed receptionAI confirmedRecord updated September 12, 2026

Homer City Energy Campus is a data center under construction in Homer City, Pennsylvania (Indiana County), operated by Homer City Redevelopment. The public record puts it at announced April 2, 2025, 4.5 GW planned, 3,200 acres, a reported $10 billion investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Homer City Redevelopment
Facility type
Data center, AI use confirmed
Location
Homer City, Indiana County, PA
Coordinates
40.5383, -79.1542
Power capacity
4.5 GW planned
Land
3,200 acres
Investment
$10 billion
Announced
April 2, 2025
Utility
PJM (via FirstEnergy Pennsylvania Electric)
Power source
On site gas
On site generation
4.5 GW
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
1,000 permanent; 10,000 construction
Public subsidy
Pennsylvania state grant, natural-gas pipeline interconnection, $5 million, Pennsylvania, 2025
Community reception
Mixed reception
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. April 2, 2025
    Proposed
    Announced as conversion of former Homer City coal plant (retired 2023); $10B project; 3,200 acres; $5M PA state grant; environmental permit challenged by groups Source: The Allegheny Front
  2. 2025
    Under construction
    Ground broken; ~1,200 workers on-site as of 2026; first vertical steel beams raised; GE Vernova turbine deliveries beginning 2026; power targeted 2027 Source: Axios

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Homer City Energy Campus in Homer City, Indiana County, Pennsylvania appear in the record, with no clear majority position. A strong local-revival narrative (an economic anchor after the 2023 coal-plant closure, backed by state officials) meets organized environmental opposition, the air permit drew 500+ comments and Clean Air Council opposition citing ~17M tons CO2e/year, potentially Pennsylvania's largest single pollution source.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

A strong local-revival narrative (an economic anchor after the 2023 coal-plant closure, backed by state officials) meets organized environmental opposition, the air permit drew 500+ comments and Clean Air Council opposition citing ~17M tons CO2e/year, potentially Pennsylvania's largest single pollution source. Developers project ~10,000 construction and ~1,000 permanent jobs.

Source: Spotlight PA

Power and water

Redevelopment of the former Homer City coal plant (Pennsylvania's largest, demolished 2023 to 25) into what developers call the largest US natural-gas plant powering an on-site AI data-center campus, seven GE Vernova 7HA.02 turbines cited at 'up to 4.4 to 4.7 GW' (a ceiling; no confirmed point value). EQT is to supply Marcellus gas; first power is targeted for 2027. PA DEP issued the air-quality plan approval on Nov 20, 2025. Developers describe the redevelopment site as spanning more than 3,200 acres.

A legacy 1,800-acre reservoir (Two Lick) remains available for cooling; NPDES permit PAD320011 (June 2026) covers Two Lick Creek outfalls. No cooling-water volume (MGD) is disclosed.

Public money on the record

ProgramAmountGranted byYear
Pennsylvania state grant, natural-gas pipeline interconnection$5 millionPennsylvania2025

Notes on the record

EPC contractor: Kiewit.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Homer City Energy Campus in Homer City?

Partly. Both documented support and documented opposition to Homer City Energy Campus in Homer City, Indiana County, Pennsylvania appear in the record, with no clear majority position. A strong local-revival narrative (an economic anchor after the 2023 coal-plant closure, backed by state officials) meets organized environmental opposition, the air permit drew 500+ comments and Clean Air Council opposition citing ~17M tons CO2e/year, potentially Pennsylvania's largest single pollution source.

Has anyone filed a lawsuit over the Homer City Energy Campus?

No lawsuit over Homer City Energy Campus appears in the record we track as of September 12, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Homer City Energy Campus use?

No water withdrawal figure for Homer City Energy Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Homer City Energy Campus, and how big is it?

Homer City Redevelopment is the operator on record. Capacity on record is 4.5 GW. The site is recorded at 3200 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Homer City Energy Campus," updated September 12, 2026, https://suedatacenters.org/data-centers/homer-city-energy-campus-pa.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/homer-city-energy-campus-pa, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.In Western Pennsylvania, a former coal town gets a gas-fired data center, The Allegheny Front · The Allegheny Front · retrieved July 5, 2026
  2. 2.Homer City power plant to boost grid as data-center demand rises, Axios Pittsburgh · Axios · retrieved July 5, 2026
  3. 3.Homer City Redevelopment and Kiewit announce country's largest natural-gas-powered data-center campus, GE Vernova · GE Vernova · retrieved July 6, 2026
  4. 4.Homer City Generation Site Redevelopment, Pennsylvania DEP · Pennsylvania DEP · retrieved July 6, 2026
  5. 5.Largest US gas-fired power plant planned for data centers in Pennsylvania, Utility Dive · Utility Dive · retrieved July 6, 2026
  6. 6.New power plants for data centers would worsen pollution, Spotlight PA · Spotlight PA · retrieved July 6, 2026
  7. 7.Homer City Redevelopment and Kiewit Announce Country's Largest Natural Gas-Powered Data Center Campus · Business Wire · retrieved August 2, 2026
  8. 8.Homer City and Kiewit unveil plans for 4.5GW natural gas powered AI data center in Pennsylvania · DataCenterDynamics · retrieved August 2, 2026
  9. 9.GE Vernova to supply seven 7HA.02 turbines for Homer City data center campus · GE Vernova · retrieved August 2, 2026
  10. 10.In Western Pennsylvania, a former coal town gets a gas-fired data center, The Allegheny Front · The Allegheny Front · retrieved August 16, 2026
  11. 11.Project Overview - Homer City Redevelopment · Homer City Redevelopment · retrieved September 12, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us