Data Center Registry
69-71 New Hook Road Data Center (Constable Hook)
Bayonne, Hudson County, New Jersey
69-71 New Hook Road Data Center (Constable Hook) is a proposed data center in Bayonne, New Jersey (Hudson County), operated by Undisclosed. The public record puts it at announced December 3, 2025. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Undisclosed
- Facility type
- Data center
- Location
- 69-71 New Hook Road, Bayonne, Hudson County, NJ, 07002
- Coordinates
- 40.6566, -74.0944 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- December 3, 2025
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- December 3, 2025ProposedOn Dec 3, 2025 the Planning Board took up an amendment to the New Hook Road Redevelopment Plan adding data centers as a permitted use at the site of an existing Delta Storage facility. The council advanced the ordinance on first reading on Dec 17, 2025. Source: GatherGov
Opposition and litigation at this site
Yes. Organized local opposition to 69-71 New Hook Road Data Center (Constable Hook) in Bayonne, Hudson County, New Jersey is documented in the public record, without a lawsuit on file in the sources we track. Residents organized against the plan, and it became an issue in the 2026 mayoral race.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Residents organized against the plan, and it became an issue in the 2026 mayoral race. The council passed a citywide data center ban 5-0 on Aug 12, 2026.
Power and water
GatherGov reports the site would draw power directly from the adjacent Bayonne Energy Center; no MW figure disclosed.
Notes on the record
The site was rezoned at an applicant's request to allow a data center; no site plan filing has been reported. Reporting says the site would draw power directly from the adjacent Bayonne Energy Center, with no capacity figure given. On Aug 12, 2026 the City Council voted 5-0 to ban data centers in all zones citywide. The business administrator said projects on previously approved sites are unlikely to advance because they need further approvals. Status stays 'proposed' because no source states this project was withdrawn or cancelled; a reviewer may judge the citywide ban to be a cancellation. Coordinates are an OSM street-level point on New Hook Road next to Bayonne Energy Center, not the parcel.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DataVerge Brooklyn (Industry City) · Brooklyn · DataVerge5 mi · Operating · 140 MW
- QTS Jersey City (JCY1) · Jersey City · QTS Data Centers5 mi · Operating
- Telehouse New York (Staten Island Teleport) · Staten Island · Telehouse America (KDDI)5 mi · Operating
- 75 Broad Street (Broad Street Connect carrier hotel) · New York · Multi-tenant carrier hotel, NYI / JEMB Realty 'Broad Street Connect'; tenants include HorizonIQ (Internap NYMEXT1), Evocative, Epsilon and Verizon5 mi · Operating · 12.5 MW
- 365 Data Centers NY10 (65 Broadway) · New York · 365 Data Centers6 mi · Operating
- SDC Manhattan (Intergate.Manhattan), 375 Pearl Street · New York · Sabey Data Centers6 mi · Operating · 18 MW
- 60 Hudson Street · New York · Multi-tenant carrier hotel (Hudson Interxchange, Digital Realty, DataBank, Equinix, and 100+ telecom tenants)6 mi · Operating · 15 MW
- 32 Avenue of the Americas · New York · Multi-tenant carrier hotel (Digital Realty, CoreSite, and other carrier/telecom tenants)6 mi · Operating
Questions people ask about this site
Is there opposition to the 69-71 New Hook Road Data Center (Constable Hook) in Bayonne?
Yes. Organized local opposition to 69-71 New Hook Road Data Center (Constable Hook) in Bayonne, Hudson County, New Jersey is documented in the public record, without a lawsuit on file in the sources we track. Residents organized against the plan, and it became an issue in the 2026 mayoral race.
Has anyone filed a lawsuit over the 69-71 New Hook Road Data Center (Constable Hook)?
No lawsuit over 69-71 New Hook Road Data Center (Constable Hook) appears in the record we track as of October 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does 69-71 New Hook Road Data Center (Constable Hook) use?
No water withdrawal figure for 69-71 New Hook Road Data Center (Constable Hook) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates 69-71 New Hook Road Data Center (Constable Hook), and how big is it?
Undisclosed is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "69-71 New Hook Road Data Center (Constable Hook)," updated October 9, 2026, https://suedatacenters.org/data-centers/new-hook-road-data-center-bayonne-nj.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/new-hook-road-data-center-bayonne-nj, retrieved October 11, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Bayonne data center at 69-71 New Hook Road: rezoning and council response · GatherGov · retrieved October 9, 2026
- 2.Bayonne bans data centers citywide in unanimous council vote · HudPost · retrieved October 9, 2026
- 3.Bayonne mayoral candidates spar over data center vote · New Jersey Globe · retrieved October 9, 2026
- 4.OpenStreetMap Nominatim geocode: New Hook Road, Bayonne · OpenStreetMap · retrieved October 9, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us