Sue Data Centers

Data Center Registry

Nebius Vineland Data Center

Vineland, Cumberland County, New Jersey · All 3 Nebius Group sites · Every Nebius case on our tracker

OperatingContestedAI confirmedRecord updated October 22, 2026

Nebius Vineland Data Center is an operating data center in Vineland, New Jersey (Cumberland County), operated by Nebius Group. The public record puts it at announced 2025, 300 MW planned, 106 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

What our reporting adds

Our case file documents this site. Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026). The base record lists the reception as mixed; the case record sets it to contested.

Facility record

Operating

Operator
Nebius Group
Facility type
Data center, AI use confirmed
Location
South Lincoln Avenue, Vineland, Cumberland County, NJ
Coordinates
39.4862, -74.9920 (approximate)
Power capacity
100 MW operating; 300 MW planned
Land
106 acres
Investment
Not established from a public source
Announced
2025
Utility
Vineland Municipal Utilities Authority (supplemental, ~15%)
Power source
On site gas
Cooling
air
Water use
Not established from a public source
Jobs
200 permanent; 1,000 construction
Public subsidy
5-year PILOT (Payment in Lieu of Taxes), Ordinance 2026-3, dollar amount not publicly disclosed, City of Vineland, NJ, 2026 | Five-year payment in lieu of taxes (PILOT) agreement, City of Vineland, NJ, 2026
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. March 2025
    Proposed
    Nebius and DataOne announce phased AI data center in Vineland, NJ; 20-week first-phase build target, total ceiling 'up to 300 MW' Source: Nebius
  2. 2025
    Operating
    First phase completed in approximately 20 weeks (summer 2025); Nebius committed to 100 MW installed capacity by year-end 2025; Microsoft GPU capacity deliveries begin late 2025. Full campus buildout targeting November 2026. Source: Nebius

Opposition and litigation at this site

Yes. Nebius Vineland Data Center in Vineland, Cumberland County, New Jersey is contested. Hearings, public comment, petitions, or organized opposition are on record. Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026).

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026). AI data center off South Lincoln Avenue, Vineland, Cumberland County, operated by Nebius Group; 2.6 million square feet at completion, 300 megawatts, three data rooms already online. City council and mayor formally support the project; PILOT Ordinance 2026-3 adopted unanimously January 27, 2026. Approximately 100 residents rallied in opposition (noise, emissions, water, property values, health concerns). Pinelands Alliance hosted community town hall. Sierra Club and Sustain South Jersey formally oppose, citing construction without final environmental permits, proximity to Pinelands, and lack of public process. NJDEP reviewing air permit and investigating facility's emissions as a single-source with adjacent parcels.

Source: Pinelands Alliance

Power and water

32 high-efficiency natural gas engines generate approximately 85% of facility power; 6 diesel generators for backup. Proposed 1.5-million-gallon LNG storage tank as pipeline contingency (pending approval). NJDEP air permit under review as of early 2026; Sierra Club and Pinelands Alliance objecting to emissions profile. Facility located in Wellhead Protected Area near Kirkwood-Cohansey aquifer.

Developer explicitly states facility will not consume water for equipment cooling (Philadelphia Inquirer, Jan 2026). A four-step exhaust reclamation system on the gas engines (selective catalytic reduction, oxy catalyst, wet scrubbers, biofilters) captures condensate from engine exhaust for recycling, this is emissions control on the power plant side, not IT-equipment cooling. City department figures show 1.1 million gallons/year municipal water draw (Inquirer, Jan 2026); a separate source (WHYY) cites 'up to 20 million gallons annually', discrepancy unresolved, likely reflecting different accounting (total throughput vs. net municipal draw). A water-use figure is omitted due to conflicting figures.

Public money on the record

ProgramAmountGranted byYear
5-year PILOT (Payment in Lieu of Taxes), Ordinance 2026-3, dollar amount not publicly disclosedNot establishedCity of Vineland, NJ2026
Five-year payment in lieu of taxes (PILOT) agreementNot establishedCity of Vineland, NJ2026

Notes on the record

Phase-1 (~100 MW) completed summer 2025 in approximately 20 weeks from March 2025 announcement; full campus buildout targeting November 2026. Total design capacity cited as 'up to 300 MW' in Nebius press releases; DataOne CEO and local/community coverage consistently cite 350 MW; long-term campus potential described as approaching 1 GW. Coordinates are approximate (site: South Lincoln and Sheridan Avenues, East Vineland; Baxtel lists 805 Sheridan Ave). DataOne is the developer/builder, BSO's data center unit (launched 2024) backed by Ardian; CEO Charles-Antoine Beyney; this is DataOne's first US site (previously Grenoble and Lyon, France). Nebius is the ~10-year tenant; Microsoft GPU infrastructure agreement commencing late 2025 under multi-year AI infrastructure deal. Facility is 100% privately funded; DataOne declined a $6.2M city equipment loan amid community backlash. Distinct from Nebius's Independence, MO (Kansas City) site. NJDEP air permit pending as of early 2026; construction proceeded ahead of final permit issuance. DataOne stated 200+ permanent full-time jobs. As of October 2026, Nebius's project page states roughly 200 permanent on-site jobs and roughly 1,000 jobs during construction.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Nebius Vineland Data Center?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Nebius Vineland Data Center in Vineland?

Yes. Nebius Vineland Data Center in Vineland, Cumberland County, New Jersey is contested. Hearings, public comment, petitions, or organized opposition are on record. Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026).

Has anyone filed a lawsuit over the Nebius Vineland Data Center?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does Nebius Vineland Data Center use?

No water withdrawal figure for Nebius Vineland Data Center is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Nebius Vineland Data Center, and how big is it?

Nebius Group is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 300 MW. The site is recorded at 106 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Nebius Vineland Data Center," updated October 22, 2026, https://suedatacenters.org/data-centers/nebius-vineland-nj.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/nebius-vineland-nj, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey · Nebius · retrieved July 7, 2026
  2. 2.We're introducing the 300 MW New Jersey region and expanding to Iceland · Nebius · retrieved July 7, 2026
  3. 3.DataOne to build Nebius data center in New Jersey · Data Center Dynamics · retrieved July 7, 2026
  4. 4.Vineland residents are protesting AI data center as concerns mount over emissions · WHYY · retrieved July 7, 2026
  5. 5.A Town Hall Too Late, Vineland Data Center · Pinelands Alliance · retrieved July 7, 2026
  6. 6.South Jersey's largest data center is being built in Vineland. Some residents say they've had no say in the process. · Philadelphia Inquirer · retrieved July 7, 2026
  7. 7.'Vineland data center makes case for on-site power generation during 6-hour hearing', WHYY, 6 August 2026 · WHYY · retrieved September 14, 2026
  8. 8.'Vineland planning board approves 2nd phase of 300-megawatt data center plan', WHYY, 18 August 2026 · WHYY · retrieved September 14, 2026
  9. 9.What exactly is DataOne building in Vineland? · South Jersey Climate News · retrieved September 21, 2026
  10. 10.Nebius x Vineland, New Jersey · Nebius · retrieved September 21, 2026
  11. 11.City of Vineland, N.J. issues stop-work order to parts of data center · WHYY · retrieved September 21, 2026
  12. 12.Montgomery v. DataOne USA: The Vineland, New Jersey Noise Class Action Filed and Withdrawn in 24 Days · SueDataCenters.org · retrieved September 2, 2026
  13. 13.Government Technology: New Jersey neighbors sue over humming noise from data center (May 2026) · govtech.com · retrieved September 2, 2026
  14. 14.Crowell & Moring: Data center noise litigation 2026, plaintiffs' bar targets AI infrastructure (July 28, 2026) · crowell.com · retrieved September 2, 2026
  15. 15.WilmerHale: Data centers in court, the emerging wave of nuisance, environmental, and land-use litigation (July 13, 2026) · wilmerhale.com · retrieved September 2, 2026
  16. 16.Programs.com: Data center moratoriums by state, tracker and statistics (as of August 26, 2026) · programs.com · retrieved September 2, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us