Nebius Vineland Data Center
Vineland, Cumberland County, New Jersey · All 3 Nebius Group sites · Every Nebius case on our tracker
Nebius Vineland Data Center is an operating data center in Vineland, New Jersey (Cumberland County), operated by Nebius Group. The public record puts it at announced 2025, 300 MW planned. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
What our reporting adds
Our case file documents this site. Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026). The base record lists the reception as mixed; the case record sets it to contested.
Facility record
Operating
- Operator
- Nebius Group
- Facility type
- Data center, AI use confirmed
- Location
- Vineland, Cumberland County, NJ
- Coordinates
- 39.4862, -74.9920
- Power capacity
- 100 MW operating; 300 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- 2025
- Utility
- Vineland Municipal Utilities Authority (supplemental, ~15%)
- Power source
- On site gas
- Cooling
- air
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- 5-year PILOT (Payment in Lieu of Taxes), Ordinance 2026-3, dollar amount not publicly disclosed, City of Vineland, NJ, 2026
- Community reception
- Contested
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- March 2025ProposedNebius and DataOne announce phased AI data center in Vineland, NJ; 20-week first-phase build target, total ceiling 'up to 300 MW' Source: Nebius
- 2025OperatingFirst phase completed in approximately 20 weeks (summer 2025); Nebius committed to 100 MW installed capacity by year-end 2025; Microsoft GPU capacity deliveries begin late 2025. Full campus buildout targeting November 2026. Source: Nebius
Opposition and litigation at this site
Yes. Nebius Vineland Data Center in Vineland, Cumberland County, New Jersey is contested. Hearings, public comment, petitions, or organized opposition are on record. Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026).
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026). AI data center off South Lincoln Avenue, Vineland, Cumberland County, operated by Nebius Group; 2.6 million square feet at completion, 300 megawatts, three data rooms already online. City council and mayor formally support the project; PILOT Ordinance 2026-3 adopted unanimously January 27, 2026. Approximately 100 residents rallied in opposition (noise, emissions, water, property values, health concerns). Pinelands Alliance hosted community town hall. Sierra Club and Sustain South Jersey formally oppose, citing construction without final environmental permits, proximity to Pinelands, and lack of public process. NJDEP reviewing air permit and investigating facility's emissions as a single-source with adjacent parcels.
Power and water
32 high-efficiency natural gas engines generate approximately 85% of facility power; 6 diesel generators for backup. Proposed 1.5-million-gallon LNG storage tank as pipeline contingency (pending approval). NJDEP air permit under review as of early 2026; Sierra Club and Pinelands Alliance objecting to emissions profile. Facility located in Wellhead Protected Area near Kirkwood-Cohansey aquifer.
Developer explicitly states facility will not consume water for equipment cooling (Philadelphia Inquirer, Jan 2026). A four-step exhaust reclamation system on the gas engines (selective catalytic reduction, oxy catalyst, wet scrubbers, biofilters) captures condensate from engine exhaust for recycling, this is emissions control on the power plant side, not IT-equipment cooling. City department figures show 1.1 million gallons/year municipal water draw (Inquirer, Jan 2026); a separate source (WHYY) cites 'up to 20 million gallons annually', discrepancy unresolved, likely reflecting different accounting (total throughput vs. net municipal draw). Reporting 'reportedMgd' field omitted due to conflicting figures.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| 5-year PILOT (Payment in Lieu of Taxes), Ordinance 2026-3, dollar amount not publicly disclosed | Not established | City of Vineland, NJ | 2026 |
Notes on the record
Phase-1 (~100 MW) completed summer 2025 in approximately 20 weeks from March 2025 announcement; full campus buildout targeting November 2026. Total design capacity cited as 'up to 300 MW' in Nebius press releases (sourceRef 0); DataOne CEO and local/community coverage consistently cite 350 MW; long-term campus potential described as approaching 1 GW. Coordinates are approximate (site: South Lincoln and Sheridan Avenues, East Vineland; Baxtel lists 805 Sheridan Ave). DataOne is the developer/builder, BSO's data center unit (launched 2024) backed by Ardian; CEO Charles-Antoine Beyney; this is DataOne's first US site (previously Grenoble and Lyon, France). Nebius is the ~10-year tenant; Microsoft GPU infrastructure agreement commencing late 2025 under multi-year AI infrastructure deal. Facility is 100% privately funded; DataOne declined a $6.2M city equipment loan amid community backlash. Distinct from Nebius's Independence, MO (Kansas City) site. NJDEP air permit pending as of early 2026; construction proceeded ahead of final permit issuance. DataOne stated 200+ permanent full-time jobs; construction job count not disclosed.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Permanent jobs promised
- Land area
Which document closes each gap
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
- Montgomery v. DataOne USA · Dismissed
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- A1 Data Center Campus · Millville · A1 Data Center6 mi · Cancelled · 1.4 GW
Questions people ask about this site
Is there opposition to the Nebius Vineland Data Center in Vineland?
Yes. Nebius Vineland Data Center in Vineland, Cumberland County, New Jersey is contested. Hearings, public comment, petitions, or organized opposition are on record. Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026).
Has anyone filed a lawsuit over the Nebius Vineland Data Center?
The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.
How much water does Nebius Vineland Data Center use?
No water withdrawal figure for Nebius Vineland Data Center is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Nebius Vineland Data Center, and how big is it?
Nebius Group is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 300 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Nebius Vineland Data Center," updated July 7, 2026, https://suedatacenters.org/data-centers/nebius-vineland-nj.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/nebius-vineland-nj, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey · Nebius · retrieved July 7, 2026
- 2.We're introducing the 300 MW New Jersey region and expanding to Iceland · Nebius · retrieved July 7, 2026
- 3.DataOne to build Nebius data center in New Jersey · Data Center Dynamics · retrieved July 7, 2026
- 4.Vineland residents are protesting AI data center as concerns mount over emissions · WHYY · retrieved July 7, 2026
- 5.A Town Hall Too Late, Vineland Data Center · Pinelands Alliance · retrieved July 7, 2026
- 6.South Jersey's largest data center is being built in Vineland. Some residents say they've had no say in the process. · Philadelphia Inquirer · retrieved July 7, 2026
- 7.Montgomery v. DataOne USA: The Vineland, New Jersey Noise Class Action Filed and Withdrawn in 24 Days · SueDataCenters.org · retrieved September 2, 2026
- 8.Government Technology: New Jersey neighbors sue over humming noise from data center (May 2026) · govtech.com · retrieved September 2, 2026
- 9.Crowell & Moring: Data center noise litigation 2026, plaintiffs' bar targets AI infrastructure (July 28, 2026) · crowell.com · retrieved September 2, 2026
- 10.WilmerHale: Data centers in court, the emerging wave of nuisance, environmental, and land-use litigation (July 13, 2026) · wilmerhale.com · retrieved September 2, 2026
- 11.Programs.com: Data center moratoriums by state, tracker and statistics (as of August 26, 2026) · programs.com · retrieved September 2, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us