Nebius Data Center Disputes: The Vineland, New Jersey Noise Case and the Entity That Was Actually Sued
Nebius is an Amsterdam based AI cloud company listed on Nasdaq as NBIS, and it operates the 2.6 million square foot campus in Vineland, New Jersey at the center of the state's first data center noise class action. The named defendant was not Nebius but DataOne USA. What the complaint alleged, why it lasted 24 days, and what the company has and has not said.

DataOne data center in Vineland, New Jersey, photographed 2023-08-20. The DataOne facility off South Lincoln Avenue, with houses along the road. The complaint put 48 to 60 dBA at homes on the record against a 50 decibel overnight limit.
USDA Farm Service Agency / USGS National Map, National Agriculture Imagery Program. Cropped from NAIP 0.3 m aerial imagery, scene m_3907540_se_18_030_20230820. (original)
Nebius on the tracker
- Tracker entries
- Two: Montgomery v. DataOne USA LLC in Vineland, New Jersey, filed May 26, 2026 and voluntarily dismissed without prejudice June 19, 2026; and the Independence, Missouri suit reported filed in Jackson County Circuit Court over the Nebius campus off Bly Road
- Named defendant
- DataOne USA LLC in Vineland. Nebius Group was not a named defendant in the Vineland complaint; it is identified in reporting and on the tracker as the operator of the facility. In the Independence, Missouri suit the reported defendants are the City of Independence, Missouri ADC Holdings LLC and Independence Power Partners LP, again not Nebius
- What the company is
- Nebius Group N.V., an AI cloud company headquartered in Amsterdam and listed on Nasdaq under NBIS. It is an SEC registered foreign private issuer, CIK 0001513845, and filed under the name Yandex N.V. through August 2024
- The facility
- An AI data center off South Lincoln Avenue in Vineland, Cumberland County, New Jersey; 2.6 million square feet at completion, 300 megawatts, three data rooms already online
- Company response
- None documented. No item in the Nebius newsroom addresses the Vineland noise dispute as of September 3, 2026, and no statement from the company appears in the reporting the tracker relies on
Key Takeaways
- Nebius operates the Vineland, New Jersey campus behind the only tracker case connected to the company, but it was not the named defendant. The complaint named DataOne USA LLC, and being precise about that distinction matters if you are trying to bring a claim of your own.
- Two Vineland residents filed a proposed federal class action on May 26, 2026 on behalf of roughly 1,013 households within a mile, alleging a constant industrial hum from generators and cooling equipment at 48 to 60 dBA against a 50 decibel overnight county limit, with a county health department violation notice already on record.
- On June 19, 2026, 24 days after filing, the plaintiffs voluntarily dismissed the case without prejudice. No court ruled on anything, and the claims can be refiled.
- Nebius has not publicly responded to the noise allegations that we can document. Its newsroom carries financial results, financings, and a UK infrastructure expansion, and nothing addressing Vineland.
- The case outlived itself in policy: Governor Mikie Sherrill announced a four part data center plan including statewide noise standards, and New Jersey enacted a Data Center Fair Share Act.
In this article
Nebius Group N.V. is an AI cloud company headquartered in Amsterdam and listed on Nasdaq under the ticker NBIS. It registers with the SEC as a foreign private issuer and filed under the name Yandex N.V. through August 2024. In the United States it is best known to neighbors, not investors, for a 2.6 million square foot campus off South Lincoln Avenue in Vineland, New Jersey, which became the subject of the state's first data center noise class action in May 2026. One point deserves care before anything else: the complaint's named defendant was DataOne USA LLC, not Nebius. Nebius is identified in reporting and on this tracker as the facility's operator. The case lasted 24 days before the plaintiffs withdrew it without prejudice, and what it left behind, a decibel record, a health department notice, and a statewide policy response, is the part that still matters.
Every case on the tracker
- DismissedNew JerseyMontgomery v. DataOne USA: The Vineland, New Jersey Noise Class Action Filed and Withdrawn in 24 Days
Voluntarily dismissed without prejudice, June 19, 2026 (filed May 26, 2026)
On May 26, 2026, two Vineland, New Jersey residents filed a federal class action over a constant industrial hum from a 2.6 million square foot AI data center run by Nebius, on behalf of about 1,013 households within a mile. On June 19, the plaintiffs voluntarily dismissed it without prejudice. What the complaint alleged, why a withdrawal is not a loss, and what New Jersey did next.
- Active litigationMissouriIndependence, Missouri: A 16 Count Suit, a City Owned Power Company, and the Records That Are Actually Public
Reported filed in Jackson County Circuit Court; temporary restraining order reported sought. Filing reported by KSHB 41; we obtained no court record
Residents along Bly Road in the Little Blue Valley filed a 16 count, 52 page suit against the City of Independence, Missouri ADC Holdings LLC and Independence Power Partners LP over the Nebius AI campus, and reported seeking a temporary restraining order. We could not obtain the court record, so here is what we could obtain: the ordinance number, the bond amount, the roll call vote, the moratorium resolutions, the pending zoning and utility ordinances, and what Missouri's Sunshine Law lets a resident demand.
Every Nebius site in the registry
3 sites on the public record in 3 states: 1 operating, 2 under construction, 0 permitted, 0 proposed. 3 carry documented opposition or litigation. 1.8 GW planned. Most contested first.
- Nebius AI Factory (Independence) · Independence, MOUnder construction · 1.2 GW · In litigation
- Nebius Birmingham AI Factory (BHM01) · Birmingham, ALUnder construction · 300 MW · In litigation
- Nebius Vineland Data Center · Vineland, NJOperating · 300 MW · Contested
Which entity is which, and why it matters to you
Large data centers are routinely built and held through entities that do not carry the operating company's name. In Vineland, the residents sued DataOne USA LLC. Nebius Group is the operator identified in the reporting, and the campus is connected in that reporting to a $17 billion agreement to supply Microsoft with AI computing capacity. Our tracker does not document a corporate relationship between DataOne USA and Nebius beyond that operator identification, and neither will this page.
This is not a technicality. If you are considering a claim over a facility near you, the first practical question your attorney will ask is who to name: the site owner of record, the entity on the permits, the operating company, the landlord, or all of them. Suing the wrong entity can cost months, and it is one of the ordinary reasons plaintiffs' firms reset a newly filed case. Property records, the local building and zoning file, and the air or noise permits are where the correct names live, and they are public.
What the Vineland complaint put on the record
The complaint, filed May 26, 2026 in the U.S. District Court for the District of New Jersey, alleged a constant industrial hum from diesel generators and cooling equipment without adequate sound barriers, at 48 to 60 A weighted decibels, exceeding 50 decibels between 10 p.m. and 7 a.m. in violation of county standards. It pleaded private nuisance, public nuisance, and negligence on behalf of about 1,013 households within one mile, and legal analysis of the case notes the county health department had already issued a violation notice.
On June 19, 2026, the plaintiffs voluntarily dismissed without prejudice. That is not a loss and not a win. It is a reset, and it preserves the claims. Our full report on the Vineland case covers the complaint, the withdrawal, and the reasons firms withdraw early.
These are allegations. No court has ruled on them, and we can document no response from Nebius or DataOne USA to any of them. We looked: as of September 3, 2026 the Nebius newsroom carries financial results, convertible note offerings, executive appointments, sustainability reporting, and a UK infrastructure expansion, and nothing addressing the Vineland noise complaints. Silence is not an admission of anything, and we note it only because our standard is to pair every allegation with the operator's answer where one exists.
What the case changed in New Jersey
The numbers in the complaint moved into the policy debate even though the case did not survive its first month. Governor Mikie Sherrill announced a four part regulatory plan for data center development that includes statewide noise standards, the first such state level standard proposed in response to the 2026 noise cases, and New Jersey has enacted a Data Center Fair Share Act addressing who pays for the power large facilities demand. New Jersey municipalities have also adopted permanent local bans at a pace no other state matches, as our moratorium tracker records.
For residents near the Vineland campus or any large AI facility, the Vineland filing reads as a template rather than a verdict: measure at the property line at night, compare to your county or city limit, get the health department on record, and map the affected radius. Our noise lawsuit guide and evidence guide walk through both steps, and the New Jersey page covers the wider picture. If a hum is reaching your home, our free case review connects you with an independent attorney in our network who handles data center cases in your state, at no cost and with no obligation.
Frequently asked questions
Has Nebius been sued over a data center?
Two cases on our tracker involve Nebius operated projects, and in neither is Nebius a reported defendant. In Vineland, New Jersey the named defendant was DataOne USA LLC; two residents filed a proposed noise class action on May 26, 2026 and voluntarily dismissed it without prejudice on June 19, 2026, so no court ruled on the allegations. In Independence, Missouri, KSHB 41 reported that residents filed a 16 count petition in Jackson County Circuit Court naming the City of Independence, Missouri ADC Holdings LLC and Independence Power Partners LP over the Nebius campus off Bly Road; we were not able to obtain that court record.
Who is Nebius?
Nebius Group N.V. is an AI cloud company headquartered in Amsterdam and listed on Nasdaq under the ticker NBIS. It is an SEC registered foreign private issuer with CIK 0001513845 and filed under the name Yandex N.V. through August 2024. It operates the Vineland, New Jersey AI data center campus.
How loud was the Vineland data center according to the lawsuit?
The complaint alleged a constant industrial hum from diesel generators and cooling equipment at 48 to 60 A weighted decibels, exceeding 50 decibels between 10 p.m. and 7 a.m. in violation of county standards, and legal analysis of the case notes the county health department had issued a violation notice. These are allegations that no court has ruled on.
Has Nebius responded to the Vineland noise complaints?
We can document no response. As of September 3, 2026 the Nebius newsroom contains no item addressing the Vineland noise dispute, and no company statement appears in the reporting our tracker relies on.
Article sources
Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.
- 1.Nebius: company page describing the business, Amsterdam headquarters, and Nasdaq listing under NBIS
- 2.Nebius: corporate site and AI cloud platform description
- 3.Nebius: newsroom, reviewed September 3, 2026 for any statement on the Vineland dispute
- 4.SEC EDGAR: Nebius Group N.V., CIK 0001513845, foreign private issuer filings, formerly Yandex N.V. through August 2024
Is a Nebius data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us