Data Center Registry
Microsoft Victory Logistics District Campus
Fernley, Lyon County, Nevada · All 45 Microsoft sites · Every Microsoft case on our tracker
Microsoft Victory Logistics District Campus is a proposed data center in Fernley, Nevada (Lyon County), operated by Microsoft. The public record puts it at announced April 2025, 300.7 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Microsoft
- Facility type
- Data center, AI use likely
- Location
- Fernley, Lyon County, NV
- Coordinates
- 39.6082, -119.2169
- Power capacity
- Not established from a public source
- Land
- 300.7 acres
- Investment
- Not established from a public source
- Announced
- April 2025
- Utility
- NV Energy
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- April 2025ProposedMicrosoft purchased ~300.7 acres at the Victory Logistics District in Fernley, Lyon County (potential data center) Source: Nevada Appeal
Opposition and litigation at this site
Yes. Microsoft Victory Logistics District Campus in Fernley, Lyon County, Nevada is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Lyon County commissioners approved a 6-month countywide moratorium (Resolution 12-26, effective through Jan 22, 2027) on July 23, 2026 that halts receipt/review/hearing/granting of new data-center applications, amid a wave of county data-center controversy.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Lyon County commissioners approved a 6-month countywide moratorium (Resolution 12-26, effective through Jan 22, 2027) on July 23, 2026 that halts receipt/review/hearing/granting of new data-center applications, amid a wave of county data-center controversy.
Notes on the record
~300.7-acre land acquisition at the Victory Logistics District in Fernley, Lyon County. Capacity and timeline not yet announced → proposed. Coordinates are the Fernley area centroid.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Switch CITADEL Campus · McCarran · Switch8 mi · Operating · 650 MW · Supported
- Fleet Data Centers Storey County Campus (South Valley & Peru Ridge) · McCarran · Fleet Data Centers13 mi · Under construction · 400 MW · Contested
- Novva Tahoe Reno Data Center · McCarran · Novva Data Centers13 mi · Operating · 60 MW
- Tract Silver Springs Data Center Park · Silver Springs · Tract14 mi · Proposed · 1.6 GW · Supported
- Colovore Reno 1 (RN01) · McCarran · Colovore15 mi · Permitted
- EdgeCore Reno Data Center Campus · McCarran · EdgeCore Digital Infrastructure15 mi · Under construction · 216 MW
- Switch Tahoe Reno 1 (The Citadel Campus) · McCarran · Switch15 mi · Operating · 650 MW
- Amazon Data Services Reno Data Center Campus · Sparks · Amazon Web Services15 mi · Under construction
Questions people ask about this site
Is there opposition to the Microsoft Victory Logistics District Campus in Fernley?
Yes. Microsoft Victory Logistics District Campus in Fernley, Lyon County, Nevada is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Lyon County commissioners approved a 6-month countywide moratorium (Resolution 12-26, effective through Jan 22, 2027) on July 23, 2026 that halts receipt/review/hearing/granting of new data-center applications, amid a wave of county data-center controversy.
Has anyone filed a lawsuit over the Microsoft Victory Logistics District Campus?
No lawsuit over Microsoft Victory Logistics District Campus appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Microsoft Victory Logistics District Campus use?
No water withdrawal figure for Microsoft Victory Logistics District Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Microsoft Victory Logistics District Campus, and how big is it?
Microsoft is the operator on record. We hold 45 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 300.7 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Microsoft Victory Logistics District Campus," updated July 26, 2026, https://suedatacenters.org/data-centers/microsoft-fernley-nv.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/microsoft-fernley-nv, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Microsoft to buy 300 acres in Fernley's Lyon County Victory Logistics District · Nevada Appeal · retrieved July 7, 2026
- 2.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 3.NNBW / Nevada Appeal (dated Apr 16-17, 2025) · retrieved July 25, 2026
- 4.Yahoo News · retrieved July 26, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us