Amazon Data Services Reno Data Center Campus
Sparks, Storey County, Nevada · All 54 Amazon Web Services sites · Every Amazon case on our tracker
Amazon Data Services Reno Data Center Campus is a data center under construction in Sparks, Nevada (Storey County), operated by Amazon Web Services. The public record puts it at announced January 23, 2026.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Amazon Web Services
- Facility type
- Data center, AI use likely
- Location
- 3800 Peru Drive, Sparks, Storey County, NV, 89437
- Coordinates
- 39.5177, -119.4794 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- January 23, 2026
- Utility
- NV Energy (Sierra Pacific Power Company)
- Power source
- Grid
- Cooling
- Hybrid
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- March 6, 2026Under constructionNNDA announced Amazon had begun local hiring; AWS said 'As our first buildings come online, we are focused on hiring locally.' Source: Northern Nevada Development Authority
Opposition and litigation at this site
Nothing on record as of September 11, 2026. No lawsuit, organized opposition, or contested hearing over Amazon Data Services Reno Data Center Campus in Sparks, Storey County, Nevada appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
NV Energy opened a PUCN docket on 2026-05-27 seeking approval of a Large Load Electric Service Agreement with Amazon Data Services, Inc. for electric service to future data center facilities in Sparks, Nevada.
AWS Global VP of Datacenter Operations and Delivery Kerry Person, March 2026: 'Our facilities in Reno will rely on direct air cooling the majority of the time. When water is required, it will come from an allotment specifically designated for industrial use.' Recorded as hybrid rather than air because the design uses water seasonally; no recirculating-circuit detail is published.
Notes on the record
Located in the Tahoe-Reno Industrial Center approximately 15 miles east of Reno, in all or portions of Sections 10, 11, 14 and 15, T19N R22E, MDB&M. NNDA states the project sits at Switch's Citadel Campus; it is tracked separately here because Amazon Data Services, Inc. holds its own air permit, address and buildings. Coordinates are a street-level approximation from OpenStreetMap's Peru Drive geometry - no parcel-confirmed point was published.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Switch Tahoe Reno 1 (The Citadel Campus) · McCarran · Switchunder 1 mile · Operating · 650 MW
- Switch Tahoe Reno 2 (The Citadel Campus) · McCarran · Switchunder 1 mile · Operating
- Switch Tahoe Reno 3 (The Citadel Campus) · McCarran · Switchunder 1 mile · Operating
- Colovore Reno 1 (RN01) · McCarran · Colovore1 mi · Permitted
- EdgeCore Reno Data Center Campus · McCarran · EdgeCore Digital Infrastructure2 mi · Under construction · 216 MW
- Peru Shelf Technology Park · Tract2 mi · Under construction · 810 MW
- Novva Tahoe Reno Data Center · McCarran · Novva Data Centers2 mi · Operating · 60 MW
- Fleet Data Centers Storey County Campus (South Valley & Peru Ridge) · McCarran · Fleet Data Centers3 mi · Under construction · 400 MW · Contested
Questions people ask about this site
Is there opposition to the Amazon Data Services Reno Data Center Campus in Sparks?
Nothing on record as of September 11, 2026. No lawsuit, organized opposition, or contested hearing over Amazon Data Services Reno Data Center Campus in Sparks, Storey County, Nevada appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Amazon Data Services Reno Data Center Campus?
No lawsuit over Amazon Data Services Reno Data Center Campus appears in the record we track as of September 11, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Amazon Data Services Reno Data Center Campus use?
No water withdrawal figure for Amazon Data Services Reno Data Center Campus is on record here. Cooling is recorded as hybrid, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Amazon Data Services Reno Data Center Campus, and how big is it?
Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Amazon Data Services Reno Data Center Campus," updated September 11, 2026, https://suedatacenters.org/data-centers/amazon-data-services-reno-storey-county-nv.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/amazon-data-services-reno-storey-county-nv, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.NDEP Notice of Proposed Action - Amazon Data Services, Inc., Class I Air Quality OPTC AP7374-4768, 3800 Peru Drive, Sparks NV · Nevada Division of Environmental Protection · retrieved September 11, 2026
- 2.NDEP Director's Review and Preliminary Determination - Amazon facility, Storey County, Nevada · Nevada Division of Environmental Protection · retrieved September 11, 2026
- 3.NNDA press release: Hiring Event and Economic Opportunity for Amazon Data Center, Storey County (March 6, 2026) · Northern Nevada Development Authority · retrieved September 11, 2026
- 4.NV Energy seeks large-load approvals for AWS, Prologis, Novva and Fleet data centers · New Project Media · retrieved September 11, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us