Amazon Data Services Reno Data Center Campus

Sparks, Storey County, Nevada · All 54 Amazon Web Services sites · Every Amazon case on our tracker

Under constructionNo reception on recordAI likelyRecord updated September 11, 2026

Amazon Data Services Reno Data Center Campus is a data center under construction in Sparks, Nevada (Storey County), operated by Amazon Web Services. The public record puts it at announced January 23, 2026.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Amazon Web Services
Facility type
Data center, AI use likely
Location
3800 Peru Drive, Sparks, Storey County, NV, 89437
Coordinates
39.5177, -119.4794 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
January 23, 2026
Utility
NV Energy (Sierra Pacific Power Company)
Power source
Grid
Cooling
Hybrid
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. March 6, 2026
    Under construction
    NNDA announced Amazon had begun local hiring; AWS said 'As our first buildings come online, we are focused on hiring locally.' Source: Northern Nevada Development Authority

Opposition and litigation at this site

Nothing on record as of September 11, 2026. No lawsuit, organized opposition, or contested hearing over Amazon Data Services Reno Data Center Campus in Sparks, Storey County, Nevada appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

NV Energy opened a PUCN docket on 2026-05-27 seeking approval of a Large Load Electric Service Agreement with Amazon Data Services, Inc. for electric service to future data center facilities in Sparks, Nevada.

AWS Global VP of Datacenter Operations and Delivery Kerry Person, March 2026: 'Our facilities in Reno will rely on direct air cooling the majority of the time. When water is required, it will come from an allotment specifically designated for industrial use.' Recorded as hybrid rather than air because the design uses water seasonally; no recirculating-circuit detail is published.

Notes on the record

Located in the Tahoe-Reno Industrial Center approximately 15 miles east of Reno, in all or portions of Sections 10, 11, 14 and 15, T19N R22E, MDB&M. NNDA states the project sits at Switch's Citadel Campus; it is tracked separately here because Amazon Data Services, Inc. holds its own air permit, address and buildings. Coordinates are a street-level approximation from OpenStreetMap's Peru Drive geometry - no parcel-confirmed point was published.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Amazon Data Services Reno Data Center Campus in Sparks?

Nothing on record as of September 11, 2026. No lawsuit, organized opposition, or contested hearing over Amazon Data Services Reno Data Center Campus in Sparks, Storey County, Nevada appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Amazon Data Services Reno Data Center Campus?

No lawsuit over Amazon Data Services Reno Data Center Campus appears in the record we track as of September 11, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Amazon Data Services Reno Data Center Campus use?

No water withdrawal figure for Amazon Data Services Reno Data Center Campus is on record here. Cooling is recorded as hybrid, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Amazon Data Services Reno Data Center Campus, and how big is it?

Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "Amazon Data Services Reno Data Center Campus," updated September 11, 2026, https://suedatacenters.org/data-centers/amazon-data-services-reno-storey-county-nv.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/amazon-data-services-reno-storey-county-nv, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.NDEP Notice of Proposed Action - Amazon Data Services, Inc., Class I Air Quality OPTC AP7374-4768, 3800 Peru Drive, Sparks NV · Nevada Division of Environmental Protection · retrieved September 11, 2026
  2. 2.NDEP Director's Review and Preliminary Determination - Amazon facility, Storey County, Nevada · Nevada Division of Environmental Protection · retrieved September 11, 2026
  3. 3.NNDA press release: Hiring Event and Economic Opportunity for Amazon Data Center, Storey County (March 6, 2026) · Northern Nevada Development Authority · retrieved September 11, 2026
  4. 4.NV Energy seeks large-load approvals for AWS, Prologis, Novva and Fleet data centers · New Project Media · retrieved September 11, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us