Tract Silver Springs Data Center Park

Silver Springs, Lyon County, Nevada · All 15 Tract sites

ProposedSupportedAI likelyRecord updated September 10, 2026

Tract Silver Springs Data Center Park is a proposed data center in Silver Springs, Nevada (Lyon County), operated by Tract. The public record puts it at announced September 2025, 1.6 GW planned, 1,060 acres. It has documented public support and no documented opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Tract
Facility type
Data center, AI use likely
Location
Silver Springs, Lyon County, NV
Coordinates
39.4070, -119.2290 (approximate)
Power capacity
1.6 GW planned
Land
1,060 acres
Investment
Not established from a public source
Announced
September 2025
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Supported
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 2025
    Proposed
    Tract closed on ~1,060 acres near Silver Springs following rezoning and a development agreement approved by Lyon County; site master-planned for up to 1.6GW with an initial 700MW under utility study. Source: Tract

Opposition and litigation at this site

Not that we can document. Local officials or residents have expressed public support for Tract Silver Springs Data Center Park in Silver Springs, Lyon County, Nevada, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Tract's own announcement (2025-09-17) quotes Lyon County Manager Andrew Haskin welcoming the project after 'successful rezoning and development agreement with Lyon County' (per the article's own title); no opposition or resident concerns documented.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.

Tract's own announcement (2025-09-17) quotes Lyon County Manager Andrew Haskin welcoming the project after 'successful rezoning and development agreement with Lyon County' (per the article's own title); no opposition or resident concerns documented. Checked: operator press release only -- this is a county economic-development official's statement, not an independent local-news check or a residents' poll.

Source

Notes on the record

Master-planned data center park near Silver Springs, Lyon County (near the US-50/USA Parkway corridor east of Reno). ~1,060 acres acquired with approved rezoning and a Lyon County development agreement; buildout capacity up to 1.6GW with an initial 700MW under utility study, planned dry/air-cooled to minimize water use. Land/entitlement stage, proposed, not yet under construction. Coordinates approximate to Silver Springs.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Tract Silver Springs Data Center Park in Silver Springs?

Not that we can document. Local officials or residents have expressed public support for Tract Silver Springs Data Center Park in Silver Springs, Lyon County, Nevada, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Tract's own announcement (2025-09-17) quotes Lyon County Manager Andrew Haskin welcoming the project after 'successful rezoning and development agreement with Lyon County' (per the article's own title); no opposition or resident concerns documented.

Has anyone filed a lawsuit over the Tract Silver Springs Data Center Park?

No lawsuit over Tract Silver Springs Data Center Park appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Tract Silver Springs Data Center Park use?

No water withdrawal figure for Tract Silver Springs Data Center Park is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Tract Silver Springs Data Center Park, and how big is it?

Tract is the operator on record. We hold 15 sites for that company across the registry. Capacity on record is 1.6 GW. The site is recorded at 1060 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Tract Silver Springs Data Center Park," updated September 10, 2026, https://suedatacenters.org/data-centers/tract-silver-springs-nv.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tract-silver-springs-nv, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Tract Expands Its Greater Reno Portfolio, Closing on 1,060 Acres in Silver Springs, Nevada · Tract · retrieved July 30, 2026
  2. 2.Tract acquires 1,000 acres in Nevada for 1.6GW data center park · Data Center Dynamics · retrieved July 30, 2026
  3. 3.Lyon County approves Tract Capital's data center project plan in Silver Springs · CitizenPortal.ai · retrieved July 30, 2026 · original offline, no archived copy found
  4. 4.Tract Silver Springs Data Center · Data Center Map · retrieved July 30, 2026
  5. 5.Tract Acquires 1,000 Acres in Nevada for 1.6GW Data Center Park · Baxtel · retrieved August 14, 2026
  6. 6.Tract expands its Greater Reno portfolio, closing on 1,060 acres in Silver Springs, Nevada · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us