Data Center Registry
Novva Tahoe Reno Data Center
McCarran, Storey County, Nevada · All 6 Novva Data Centers sites
Novva Tahoe Reno Data Center is an operating data center in McCarran, Nevada (Storey County), operated by Novva Data Centers. The public record puts it at announced July 8, 2025, 60 MW planned, 20 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Novva Data Centers
- Facility type
- Data center, AI use likely
- Location
- McCarran, Storey County, NV
- Coordinates
- 39.5300, -119.4400 (approximate)
- Power capacity
- 60 MW planned
- Land
- 20 acres
- Investment
- Not established from a public source
- Announced
- July 8, 2025
- Utility
- NV Energy
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 8, 2025OperatingNovva announced Tahoe Reno officially open for business, its fourth completed data center; additional capacity phasing into 2026. Source: Novva Data Centers / PR Newswire
Opposition and litigation at this site
Nothing on record as of August 14, 2026. No lawsuit, organized opposition, or contested hearing over Novva Tahoe Reno Data Center in McCarran, Storey County, Nevada appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Powered via a centralized on-campus 100 MW substation (N+1 redundancy) fed by NV Energy; facility seeks local renewable energy credits.
Water-free, direct-to-chip cooling per operator.
Notes on the record
300,000 sq ft, 60 MW data center on a 20-acre campus at 1 Astro Way in the Tahoe-Reno Industrial Center (McCarran / Storey County). Six 10 MW data halls served by an on-campus 100 MW NV Energy substation; water-free direct-to-chip cooling. Coordinates are an approximate TRIC-area geocode (exact parcel point not published).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Fleet Data Centers Storey County Campus (South Valley & Peru Ridge) · McCarran · Fleet Data Centersunder 1 mile · Under construction · 400 MW · Contested
- Colovore Reno 1 (RN01) · McCarran · Colovore2 mi · Permitted
- Switch Tahoe Reno 1 (The Citadel Campus) · McCarran · Switch2 mi · Operating · 650 MW
- Amazon Data Services Reno Data Center Campus · Sparks · Amazon Web Services2 mi · Under construction
- EdgeCore Reno Data Center Campus · McCarran · EdgeCore Digital Infrastructure3 mi · Under construction · 216 MW
- Switch Tahoe Reno 2 (The Citadel Campus) · McCarran · Switch3 mi · Operating
- Switch Tahoe Reno 3 (The Citadel Campus) · McCarran · Switch3 mi · Operating
- Peru Shelf Technology Park · Tract3 mi · Under construction · 810 MW
Questions people ask about this site
Is there opposition to the Novva Tahoe Reno Data Center in McCarran?
Nothing on record as of August 14, 2026. No lawsuit, organized opposition, or contested hearing over Novva Tahoe Reno Data Center in McCarran, Storey County, Nevada appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Novva Tahoe Reno Data Center?
No lawsuit over Novva Tahoe Reno Data Center appears in the record we track as of August 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Novva Tahoe Reno Data Center use?
No water withdrawal figure for Novva Tahoe Reno Data Center is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Novva Tahoe Reno Data Center, and how big is it?
Novva Data Centers is the operator on record. We hold 6 sites for that company across the registry. Capacity on record is 60 MW. The site is recorded at 20 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Novva Tahoe Reno Data Center," updated August 14, 2026, https://suedatacenters.org/data-centers/novva-tahoe-reno-storey-county-nv.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/novva-tahoe-reno-storey-county-nv, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Novva Data Centers Announces the Launch of Tahoe Reno Data Center (PR Newswire) · Novva Data Centers / PR Newswire · retrieved July 15, 2026
- 2.American data center operator Novva launches facility in Nevada (DCD) · Data Center Dynamics · retrieved July 15, 2026
- 3.Novva Tahoe Reno Data Center, 1 Astro Way (60 MW), Storey County · Data Center Map · retrieved July 15, 2026
- 4.Novva Data Centers Tahoe Reno, launch of Tahoe Reno data center · Novva Data Centers · retrieved August 14, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us