Cloverleaf Project Open Sky is a proposed data center in Piedmont, Oklahoma (Canadian County), operated by Cloverleaf Infrastructure. The public record puts it at 630 acres, a reported $1 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Cloverleaf Infrastructure
Facility type
Data center
Location
Piedmont, Canadian County, OK
Coordinates
35.7000, -97.8000 (approximate)
Power capacity
Not established from a public source
Land
630 acres
Investment
$1 billion
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Yes. Cloverleaf Project Open Sky in Piedmont, Canadian County, Oklahoma is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Piedmont Planning Commission recommended the City Council DENY the 'Project Open Sky' PUD rezoning pending additional information.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Piedmont Planning Commission recommended the City Council DENY the 'Project Open Sky' PUD rezoning pending additional information. The council then postponed the vote repeatedly: on 28 September 2026 it continued the item for the fifth time in nearly five months, after a 2-2 vote on the motion to continue that the mayor broke (News 9). As of October 2026, no council approval has been reported.

Power and water

Project Open Sky is planned to use a closed-loop cooling system to greatly reduce water use.

Notes on the record

630-acre proposed data campus near the Mathewson Substation, NW 248th Street, Piedmont (Canadian/Kingfisher county line), part of a transmission corridor drawing multiple competing proposals; see the Beltline Energy Piedmont Site, a separate, distinct 321-acre site nearby, do not conflate despite both being in Piedmont. Closed-loop cooling planned. Cloverleaf recently withdrew from two Wisconsin data center projects after local opposition (context, not this project). Radio Oklahoma News, citing information provided to the city, reported that the project represents a $1 billion investment, which is the figure recorded. Job and capacity figures are not recorded because the sources give ceilings or disagree: Cloverleaf's chief development officer told the planning commission the project would create "up to 300 jobs, with potentially a thousand more during construction" (KOKH FOX 25), while Radio Oklahoma News reported "up to 500 permanent jobs" and "up to 1.4 gigawatts of electricity", and KOKH FOX 25 reported that the campus "would require 1.5 gigawatts of power".

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Cloverleaf Project Open Sky?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Cloverleaf Project Open Sky data center in Piedmont?

Yes. Cloverleaf Project Open Sky in Piedmont, Canadian County, Oklahoma is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Piedmont Planning Commission recommended the City Council DENY the 'Project Open Sky' PUD rezoning pending additional information.

Has anyone filed a lawsuit over the Cloverleaf Project Open Sky data center?

No lawsuit over Cloverleaf Project Open Sky appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Cloverleaf Project Open Sky use?

No water withdrawal figure for Cloverleaf Project Open Sky is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Cloverleaf Project Open Sky, and how big is it?

Cloverleaf Infrastructure is the operator on record. We hold 11 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 630 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Cloverleaf Project Open Sky," updated October 28, 2026, https://suedatacenters.org/data-centers/cloverleaf-project-open-sky-piedmont-ok.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cloverleaf-project-open-sky-piedmont-ok, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Powered land company Cloverleaf proposing 633-acre data center in Canadian County, Oklahoma · Data Center Dynamics · retrieved August 6, 2026
  2. 2.Piedmont planning commission encourages city council to deny data center proposal · KFOR · retrieved July 11, 2026
  3. 3.A Transmission Line Built to Fix Grid Congestion Has Become Oklahoma's Hottest Data Center Address · Oklahoma Watch · retrieved July 11, 2026
  4. 4.Cloverleaf Piedmont Campus (Project Open Sky), Data Center Tracker · More Than Just Parks Data Center Tracker · retrieved August 6, 2026
  5. 5.Commission urges council to deny Cloverleaf plan; Beltline Energy vote delayed for review · KOKH FOX 25 · retrieved September 14, 2026
  6. 6.Piedmont Data Center Proposal Heads To City Council Vote Tonight · Radio Oklahoma News · retrieved September 14, 2026
  7. 7.'You've dragged your feet': Piedmont delays data center vote for fifth time · News 9 · retrieved October 28, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us