Meta Project Anthem, Tulsa

Tulsa, Tulsa County, Oklahoma · All 28 Meta sites · Every Meta case on our tracker

Under constructionContestedAI confirmedRecord updated August 6, 2026

Meta Project Anthem, Tulsa is a data center under construction in Tulsa, Oklahoma (Tulsa County), operated by Meta. The public record puts it at announced 2024, 340 acres, a reported $1 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Meta
Facility type
Data center, AI use confirmed
Location
Near East 11th Street & 193rd East Avenue (Fair Oaks industrial park, East Tulsa), Tulsa, Tulsa County, OK
Coordinates
36.1400, -95.8800
Power capacity
Not established from a public source
Land
340 acres
Investment
$1 billion
Announced
2024
Utility
Public Service Company of Oklahoma (PSO)
Power source
Mixed
Cooling
Closed loop
Water use
Not established from a public source
Jobs
100 permanent; 1,000 construction
Public subsidy
Tax Incentive District (TID), 85% annual property tax exemption; 15% collected projected at ~$36 million to taxing entities (city of Tulsa, Wagoner County, Catoosa Public Schools, others) over 25-year incentive period, Tulsa, OK, 2024
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2026
    Under construction
    Meta publicly confirmed as operator; groundbreaking ceremony held April 21, 2026 with Oklahoma Governor Kevin Stitt; completion targeted 2028 Source: Meta (about.fb.com)
  2. 2024
    Proposed
    Preliminary plat filed with Tulsa Metropolitan Area Planning Commission as 'Project Anthem'; Meta identity not publicly confirmed at time of filing Source: Data Center Dynamics
  3. 2024
    Permitted
    Preliminary plat approved August 7, 2024 by TMAPC; developer entity listed as Atmoss LLC Source: Data Center Dynamics

Opposition and litigation at this site

Yes. Meta Project Anthem, Tulsa in Tulsa, Tulsa County, Oklahoma is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Tulsa City Council passed a 9-month moratorium on new data centers in March 2026 to evaluate ecological impact; Project Anthem was carved out as it was approved before the moratorium vote.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Tulsa City Council passed a 9-month moratorium on new data centers in March 2026 to evaluate ecological impact; Project Anthem was carved out as it was approved before the moratorium vote. Approximately a dozen protesters from Stop Data Colonialism coalition gathered at the April 21, 2026 groundbreaking, raising concerns about environmental impact, financial burden on nearby residents, and 'data colonialism.' Meta's water-neutrality claims challenged by protesters as corporate narrative. Councilor Christian Bengel voted for the moratorium while separately supporting Project Anthem. Meta announced $3 million in community grants (Eastside Rise neighborhood enhancement, Data Center Community Action Grants) and workforce development partnerships with Tulsa Tech and Tulsa Community College targeting 200+ graduates annually in technical trades.

Source: Tulsa Flyer

Power and water

Meta committed to matching 100% of facility electricity use with clean energy added to the Oklahoma grid. Existing Oklahoma projects add 1,500+ MW of clean energy statewide (not facility-specific). Meta covers full energy costs directly via PSO utility bills; stated commitment to avoid ratepayer burden. Tulsa Metropolitan Utility Authority also listed as a utility partner (water/wastewater).

Water-efficient closed-loop liquid-cooled system. Meta states zero water use for the majority of the year and a water-positive goal by 2030. Water restoration partnership with Phytech across ~1,500 acres targeting 50+ million gallons of annual water savings. Additional partnership with Tulsa Community Foundation on water stewardship. No reportedMgd figure confirmed.

Public money on the record

ProgramAmountGranted byYear
Tax Incentive District (TID), 85% annual property tax exemption; 15% collected projected at ~$36 million to taxing entities (city of Tulsa, Wagoner County, Catoosa Public Schools, others) over 25-year incentive periodNot establishedTulsa, OK2024

Notes on the record

Codename: Project Anthem (used in TMAPC filings; Meta confirmed publicly April 21, 2026). Meta's 28th US data center and 32nd globally; first in Oklahoma and first built within Tulsa city limits. Anchor tenant at Fair Oaks Innovation Park (a 2,000-acre campus) near 11th Street and Creek Turnpike, East Tulsa. Investment stated as 'more than $1 billion' by Meta, a floor figure only; PartnerTulsa estimates construction costs at ~$800M. investmentUsd omitted: no firm single confirmed figure. Facility size: 2+ million sq ft; completion targeted 2028; general contractor Fortis Construction. No facility-specific MW capacity disclosed; Meta separately adding 1,500+ MW of clean energy to the Oklahoma grid statewide. Jobs: Meta states 'more than 1,000 construction workers at peak' and 'approximately 100 permanent jobs', approximations from press release, not firm figures; omitted from numeric fields. Phase 2 expansion (375 additional acres west of original parcel, developer Atmoss LLC) proposed but withdrawn March 2026 before city council vote. Coordinates approximate (near 11th St & Creek Turnpike, East Tulsa).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Meta Project Anthem, Tulsa data center in Tulsa?

Yes. Meta Project Anthem, Tulsa in Tulsa, Tulsa County, Oklahoma is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Tulsa City Council passed a 9-month moratorium on new data centers in March 2026 to evaluate ecological impact; Project Anthem was carved out as it was approved before the moratorium vote.

Has anyone filed a lawsuit over the Meta Project Anthem, Tulsa data center?

No lawsuit over Meta Project Anthem, Tulsa appears in the record we track as of August 6, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Meta Project Anthem, Tulsa use?

No water withdrawal figure for Meta Project Anthem, Tulsa is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Meta Project Anthem, Tulsa, and how big is it?

Meta is the operator on record. We hold 28 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 340 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Meta Project Anthem, Tulsa," updated August 6, 2026, https://suedatacenters.org/data-centers/meta-anthem-tulsa-ok.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/meta-anthem-tulsa-ok, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Breaking Ground on a New AI-Optimized Data Center in Tulsa, Oklahoma · Meta (about.fb.com) · retrieved July 7, 2026
  2. 2.Hello, Tulsa!, Meta Data Centers · Meta (atmeta.com) · retrieved July 7, 2026
  3. 3.Meta Breaks Ground on New $1 Billion Data Center in Tulsa · Oklahoma Department of Commerce · retrieved July 7, 2026
  4. 4.Meta's east Tulsa data center earns praise and protests · Tulsa Flyer · retrieved July 7, 2026
  5. 5.340-acre data center campus planned in Tulsa, Oklahoma · Data Center Dynamics · retrieved July 7, 2026
  6. 6.Gov. Stitt announces Meta behind Tulsa data center known as 'Project Anthem' · NewsOn6 · retrieved July 7, 2026
  7. 7.Meta Breaks Ground on New $1 Billion Data Center in Tulsa · Oklahoma Department of Commerce · retrieved August 6, 2026
  8. 8.Meta confirmed as company behind Project Anthem · FOX23 News · retrieved August 6, 2026 · original offline, archived copy from April 23, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us