Pawhuska AI Data Center
Pawhuska, Osage County, Oklahoma
Pawhuska AI Data Center is a proposed data center in Pawhuska, Oklahoma (Osage County), operated by Buckley Bros Holdings LLC. The public record puts it at 10 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Buckley Bros Holdings LLC
- Facility type
- Data center, AI use likely
- Location
- 1901 E. Boundary, Pawhuska, Osage County, OK
- Coordinates
- 36.6698, -96.3364 (approximate)
- Power capacity
- 10 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- April 2026ProposedProposed conversion of a 200,000 sq ft vacant building (former carpet mill, later a cannabis cultivation facility) into an 8-10 MW AI data center. Source: News On 6
Opposition and litigation at this site
Nothing on record as of August 19, 2026. No lawsuit, organized opposition, or contested hearing over Pawhuska AI Data Center in Pawhuska, Osage County, Oklahoma appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Reported at 8-10 MW; the planned figure recorded here is the upper end of that reported range. Coordinates are a Pawhuska town-centroid approximation, not a parcel-confirmed point.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Questions people ask about this site
Is there opposition to the Pawhuska AI Data Center in Pawhuska?
Nothing on record as of August 19, 2026. No lawsuit, organized opposition, or contested hearing over Pawhuska AI Data Center in Pawhuska, Osage County, Oklahoma appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Pawhuska AI Data Center?
No lawsuit over Pawhuska AI Data Center appears in the record we track as of August 19, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Pawhuska AI Data Center use?
No water withdrawal figure for Pawhuska AI Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Pawhuska AI Data Center, and how big is it?
Buckley Bros Holdings LLC is the operator on record. Capacity on record is 10 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Pawhuska AI Data Center," updated August 19, 2026, https://suedatacenters.org/data-centers/buckley-bros-pawhuska-ok.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/buckley-bros-pawhuska-ok, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.What data centers are being built in Oklahoma? (Pawhuska AI Data Center, Buckley Bros Holdings, 1901 E. Boundary, 8-10 MW) · News On 6 · retrieved August 19, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us