Atlas Power Data Center (Williston)

Williston, Williams County, North Dakota · All 2 Atlas Power sites

OperatingIn litigationRecord updated August 5, 2026

Atlas Power Data Center (Williston) is an operating crypto mining site in Williston, North Dakota (Williams County), operated by Atlas Power. The public record puts it at announced 2022, 700 MW planned. It is or has been the subject of litigation over its siting, permitting, or operation.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Atlas Power
Facility type
Crypto mining
Location
Williston, Williams County, ND
Coordinates
48.1470, -103.6180 (approximate)
Power capacity
240 MW operating; 700 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
2022
Utility
Not established from a public source
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
In litigation
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Yes. Atlas Power Data Center (Williston) in Williston, Williams County, North Dakota is or has been the subject of litigation over its siting, permitting, or operation.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.

Notes on the record

$1.9B three-phase crypto-mining + GPU-as-a-service facility built by FX Solutions for Atlas Power LLC (~65% of load is bitcoin mining per InForum). Phase 1 (~240MW) operational since 2022-23; ~700MW planned across three phases (delayed from original timeline). Interconnected via Mountrail-Williams Electric Cooperative (a Basin Electric G&T member). Atlas Power's load drove the Charlie Creek-to-Watford 230kV constraint, the costliest real-time constraint in SPP for 2023 (~$1.1M in shadow-price impact across 35% of operating hours, per Yes Energy analysis of public SPP data); Basin Electric is adding 600MW to Pioneer Generation Station plus a new 230kV Canada tie partly to relieve this congestion. Williams County Commission voted unanimously 2023-06-20 to direct MWEC to cut power to Phase II over unmet final-inspection/noise-mitigation conditions; MWEC instead filed for a district-court declaratory judgment on its authority to do so, and the commission imposed a 6-month moratorium on new crypto data centers. Not one of the 4 ND sites already tracked (Applied Digital Jamestown, Core Scientific Grand Forks, Bitzero Nekoma, Greenidge Underwood).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Atlas Power Data Center (Williston) in Williston?

Yes. Atlas Power Data Center (Williston) in Williston, Williams County, North Dakota is or has been the subject of litigation over its siting, permitting, or operation.

Has anyone filed a lawsuit over the Atlas Power Data Center (Williston)?

Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.

How much water does Atlas Power Data Center (Williston) use?

No water withdrawal figure for Atlas Power Data Center (Williston) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Atlas Power Data Center (Williston), and how big is it?

Atlas Power is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 700 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Atlas Power Data Center (Williston)," updated August 5, 2026, https://suedatacenters.org/data-centers/atlas-power-williston-nd.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/atlas-power-williston-nd, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Atlas Power: Williston, North Dakota Data Center · Baxtel · retrieved August 5, 2026
  2. 2.Northwest North Dakota commission directs co-op to cut power to crypto data center · InForum (Forum Communications) · retrieved August 5, 2026
  3. 3.Crypto Mining Power Consumption: Atlas Power Sparks Grid Congestion · Yes Energy · retrieved August 5, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us