Applied Digital Polaris Forge 2

Harwood, Cass County, North Dakota · All 9 Applied Digital sites

Under constructionContestedAI confirmedRecord updated October 28, 2026

Applied Digital Polaris Forge 2 is a data center under construction in Harwood, North Dakota (Cass County), operated by Applied Digital Corporation. The public record puts it at announced August 2025, 200 MW planned, 900 acres, a reported $3 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Applied Digital Corporation
Facility type
Data center, AI use confirmed
Location
Harwood, Cass County, ND
Coordinates
47.0200, -97.0250 (approximate)
Power capacity
200 MW planned
Land
900 acres
Investment
$3 billion
Announced
August 2025
Utility
Cass County Electric Cooperative / Minnkota Power Cooperative
Power source
Grid
Cooling
air
Water use
Not established from a public source
Jobs
200 permanent
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 2025
    Under construction
    Groundbreaking September 2025; initial operations expected end of 2026, full capacity early 2027 Source: Applied Digital Corporation
  2. August 2025
    Proposed
    Polaris Forge 2 announced; $3B, 280 MW AI factory campus on 900+ acres near Harwood Source: Applied Digital Corporation

Opposition and litigation at this site

Yes. Applied Digital Polaris Forge 2 in Harwood, Cass County, North Dakota is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Opposition surfaced when the project was announced (Aug 2025): environmental advocates and at least one area farmer argued Minnkota Power Cooperative member-owners (farmers, ranchers, rural residents) could see higher electric rates from the substation/powerline buildout funded to serve the data center; one resident called for a moratorium to allow more planning time.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Opposition surfaced when the project was announced (Aug 2025): environmental advocates and at least one area farmer argued Minnkota Power Cooperative member-owners (farmers, ranchers, rural residents) could see higher electric rates from the substation/powerline buildout funded to serve the data center; one resident called for a moratorium to allow more planning time. No vote, denial, or litigation reported as of 2026-03-23; the ND Public Service Commission went on to approve the power project 2026-04-29/30.

Source: InForum

Power and water

280 MW peak demand; power secured through Cass County Electric Cooperative, a member-owned nonprofit, in partnership with Minnkota Power Cooperative

Notes on the record

Two purpose-built facilities totaling more than 1.8 million sq ft. As of the August 2025 announcement, Applied Digital was in advanced negotiations with a U.S.-based investment-grade hyperscaler; no customer or lease value had been publicly confirmed at that point. In October 2025 Applied Digital announced a lease with an unnamed U.S. investment-grade hyperscaler covering 200 MW of critical IT load, approximately $5 billion in total contracted revenue over an estimated 15-year term. The August 2025 announcement described a 280 MW AI factory, and Minnkota Power Cooperative states that the data center is expected to use 280 megawatts at peak, so 280 MW is read as peak electricity demand rather than IT load; the recorded planned capacity is the initial 200 MW of critical IT load that the lease covers in two buildings. The October 2025 release also describes the campus as a 1 GW design, with the tenant holding a first right of refusal on 800 MW more; that expansion potential is not recorded as capacity. Partial operations expected end of 2026; full capacity early 2027. Coordinates are Harwood city centroid; site is approximately 900 acres near this community north of Fargo.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Applied Digital Polaris Forge 2?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Applied Digital Polaris Forge 2 data center in Harwood?

Yes. Applied Digital Polaris Forge 2 in Harwood, Cass County, North Dakota is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Opposition surfaced when the project was announced (Aug 2025): environmental advocates and at least one area farmer argued Minnkota Power Cooperative member-owners (farmers, ranchers, rural residents) could see higher electric rates from the substation/powerline buildout funded to serve the data center; one resident called for a moratorium to allow more planning time.

Has anyone filed a lawsuit over the Applied Digital Polaris Forge 2 data center?

No lawsuit over Applied Digital Polaris Forge 2 appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Applied Digital Polaris Forge 2 use?

No water withdrawal figure for Applied Digital Polaris Forge 2 is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Applied Digital Polaris Forge 2, and how big is it?

Applied Digital Corporation is the operator on record. We hold 9 sites for that company across the registry. Capacity on record is 200 MW. The site is recorded at 900 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Applied Digital Polaris Forge 2," updated October 28, 2026, https://suedatacenters.org/data-centers/applied-digital-polaris-forge-2-harwood-nd.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/applied-digital-polaris-forge-2-harwood-nd, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Applied Digital to Break Ground on $3 Billion Polaris Forge 2 Campus · Applied Digital Corporation · retrieved September 21, 2026
  2. 2.Minnkota Power Cooperative: Data Center FAQs (Polaris Forge 2) · Minnkota Power Cooperative · retrieved July 6, 2026
  3. 3.Data center developer looks west, backs power upgrades near Fargo · InForum · retrieved September 10, 2026
  4. 4.Power project for AI data center gets North Dakota agency approval · Valley News Live · retrieved September 10, 2026
  5. 5.Applied Digital closes $2.15B deal to build out Harwood AI campus · Valley News Live · retrieved October 10, 2026
  6. 6.Applied Digital Announces $5 Billion AI Factory Lease with U.S. Based Investment Grade Hyperscaler at Polaris Forge 2 ND Campus · Applied Digital Corporation · retrieved October 27, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us