Sue Data Centers

Data Center Registry

Applied Digital Polaris Forge 1

Ellendale, Dickey County, North Dakota · All 7 Applied Digital sites

Under constructionSupportedAI confirmedRecord updated July 26, 2026

Applied Digital Polaris Forge 1 is a data center under construction in Ellendale, North Dakota (Dickey County), operated by Applied Digital Corporation. The public record puts it at announced June 2025, 400 MW planned, 320 acres, a reported $5.3 billion investment. It has documented public support and no documented opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Applied Digital Corporation
Facility type
Data center, AI use confirmed
Location
Ellendale, Dickey County, ND
Coordinates
46.0030, -98.5090
Power capacity
100 MW operating; 400 MW planned
Land
320 acres
Investment
$5.3 billion
Announced
June 2025
Utility
Montana-Dakota Utilities
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
350 permanent; 450 construction
Public subsidy
Not established from a public source
Community reception
Supported
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 10, 2026
    Coverage
  2. December 2025
    Under construction
    Building 1 fully operational at 100 MW; Buildings 2 (150 MW) and 3 (150 MW) under construction for CoreWeave Source: Data Center Dynamics
  3. October 2025
    Operating
    Building 1 Phase 1 (50 MW) achieves Ready for Service for CoreWeave Source: Data Center Dynamics
  4. 2023
    Under construction
    AI factory construction begins in Ellendale

Opposition and litigation at this site

Not that we can document. Local officials or residents have expressed public support for Applied Digital Polaris Forge 1 in Ellendale, Dickey County, North Dakota, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of July 26, 2026. Ellendale (pop.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.

Ellendale (pop. ~1,000) has welcomed the campus as a transformative economic boost; the state's R-WISH rural-workforce housing program is funding new homes for incoming workers. No documented opposition or litigation. Coverage notes workforce and housing strain as growing pains.

Source: Northern Sentry

Power and water

Designed for near-zero water consumption; proprietary closed-loop direct-to-chip liquid cooling; projected PUE 1.18; campus engineered to scale to 1 GW

Proprietary waterless direct-to-chip liquid cooling; WUE near zero by design

Notes on the record

Campus is 400 MW fully contracted to CoreWeave under ~15-year lease agreements valued at ~$11B total revenue. Three buildings: Building 1 (100 MW) complete Dec 2025; Building 2 (150 MW) expected mid-2026; Building 3 (150 MW) expected 2027. Coordinates are Ellendale city centroid; exact site is northeast of the city. Local jobs are reported only as projections, 'as many as 85 new jobs' (Dec 2024) and up to ~110 total local workforce at full expansion, not confirmed headcounts. No confirmed total campus capital-expenditure figure is public (the ~$11B CoreWeave figure is 15-year lease revenue, not capex); North Dakota's data-center sales-tax exemption applies but individual award amounts are statutorily confidential. investmentUsd reflects Applied Digital's own infrastructure spend (~$1.3B committed + ~$4B anticipated); the company's '$20B total campus' figure additionally counts ~$15B of customer/tenant capital.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Applied Digital Polaris Forge 1 data center in Ellendale?

Not that we can document. Local officials or residents have expressed public support for Applied Digital Polaris Forge 1 in Ellendale, Dickey County, North Dakota, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of July 26, 2026. Ellendale (pop.

Has anyone filed a lawsuit over the Applied Digital Polaris Forge 1 data center?

No lawsuit over Applied Digital Polaris Forge 1 appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Applied Digital Polaris Forge 1 use?

No water withdrawal figure for Applied Digital Polaris Forge 1 is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Applied Digital Polaris Forge 1, and how big is it?

Applied Digital Corporation is the operator on record. We hold 7 sites for that company across the registry. Capacity on record is 400 MW. The site is recorded at 320 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Applied Digital Polaris Forge 1," updated July 26, 2026, https://suedatacenters.org/data-centers/applied-digital-polaris-forge-1-ellendale-nd.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/applied-digital-polaris-forge-1-ellendale-nd, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota · Applied Digital Corporation · retrieved July 6, 2026
  2. 2.Applied Digital completes first data center building at North Dakota campus · Data Center Dynamics · retrieved July 6, 2026
  3. 3.A shot in the arm for Ellendale · Northern Sentry · retrieved July 7, 2026
  4. 4.InForum, "Applied Digital plans to expand in Ellendale, ND" · retrieved July 25, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us