Data Center Registry
Blue Fern Cle Elum Data Center
Cle Elum, Kittitas County, Washington
Blue Fern Cle Elum Data Center is a proposed data center in Cle Elum, Washington (Kittitas County), operated by Blue Fern Development. The public record puts it at announced July 28, 2026, 20 MW planned, a reported $200 million investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Blue Fern Development
- Facility type
- Data center
- Location
- Cle Elum, Kittitas County, WA
- Coordinates
- 47.1800, -120.9700 (approximate)
- Power capacity
- 20 MW planned
- Land
- Not established from a public source
- Investment
- $200 million
- Announced
- July 28, 2026
- Utility
- Not established from a public source
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 28, 2026ProposedBlue Fern Development publicly proposed a 100,000 sq ft, 20 MW data center near Interstate 90 in Cle Elum. Source: The Spokesman-Review
Opposition and litigation at this site
Yes. Blue Fern Cle Elum Data Center in Cle Elum, Kittitas County, Washington is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Cle Elum's city council voted unanimously to introduce a six-month data-center moratorium and scheduled a Sept.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Cle Elum's city council voted unanimously to introduce a six-month data-center moratorium and scheduled a Sept. 8, 2026 public hearing plus an advisory committee to study power, water, wastewater, tax and jobs impacts; council members said the developer's claims needed verification.
Power and water
Developer describes a closed-loop cooling system using about 80,000 gallons in the first year and significantly less thereafter because the water recirculates.
Notes on the record
Roughly 100,000 sq ft near Interstate 90, inside a residential and commercial development already under construction in Cle Elum. Developer projects 20 to 40 full-time positions. Because the site is covered by a pre-existing development agreement with the city, it may proceed despite the moratorium. Single-source; coordinates are an approximate geocode of the described location.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Questions people ask about this site
Is there opposition to the Blue Fern Cle Elum Data Center in Cle Elum?
Yes. Blue Fern Cle Elum Data Center in Cle Elum, Kittitas County, Washington is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Cle Elum's city council voted unanimously to introduce a six-month data-center moratorium and scheduled a Sept.
Has anyone filed a lawsuit over the Blue Fern Cle Elum Data Center?
No lawsuit over Blue Fern Cle Elum Data Center appears in the record we track as of September 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Blue Fern Cle Elum Data Center use?
No water withdrawal figure for Blue Fern Cle Elum Data Center is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Blue Fern Cle Elum Data Center, and how big is it?
Blue Fern Development is the operator on record. Capacity on record is 20 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Blue Fern Cle Elum Data Center," updated September 5, 2026, https://suedatacenters.org/data-centers/blue-fern-cle-elum-data-center-wa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/blue-fern-cle-elum-data-center-wa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Cle Elum passed a data center ban. One might be built there anyway · The Spokesman-Review · retrieved September 5, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us