AWS Wallula Gap Campus
Wallula, Walla Walla County, Washington · All 62 Amazon Web Services sites · Every Amazon case on our tracker
AWS Wallula Gap Campus is a proposed data center in Wallula, Washington (Walla Walla County), operated by Amazon Web Services. The public record puts it at announced October 2024, 134 acres. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Amazon Web Services
- Facility type
- Data center, AI use confirmed
- Location
- Sundance Road, Wallula Gap Business Park, Wallula, Walla Walla County, WA
- Coordinates
- 46.0726, -118.9135 (approximate)
- Power capacity
- Not established from a public source
- Land
- 134 acres
- Investment
- Not established from a public source
- Announced
- October 2024
- Utility
- Columbia Rural Electric Assn, Inc
- Power source
- Grid
- Cooling
- Hybrid
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- September 5, 2026ProposedWalla Walla County's own project page and local reporting show the campus is still in permitting, not construction. The county held a pre-application meeting on April 29, 2026, issued a Notice of Incomplete Application on June 23, 2026, and issued a Notice of Complete Application on August 24, 2026 (files SDP26-01 and SEPA26-05). As of September 1, 2026 no final land-use decision has been made and construction has not been initiated. The record's current status, under construction, is not supported by these sources. Source: Walla Walla County, Washington
- 2026Under constructionA ~$4.8B data center in Walla Walla County (Wallula), widely reported to be AWS Source: Data Center Dynamics
Opposition and litigation at this site
Partly. Both documented support and documented opposition to AWS Wallula Gap Campus in Wallula, Walla Walla County, Washington appear in the record, with no clear majority position. Port of Walla Walla commissioners approved the amended land sale unanimously (Feb 12, 2026), calling the project transformative; documented concerns from the Confederated Tribes of the Umatilla Indian Reservation (sacred Snake/Columbia confluence), environmental and academic voices, and a commissioner over water and power.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Port of Walla Walla commissioners approved the amended land sale unanimously (Feb 12, 2026), calling the project transformative; documented concerns from the Confederated Tribes of the Umatilla Indian Reservation (sacred Snake/Columbia confluence), environmental and academic voices, and a commissioner over water and power. No litigation or moratorium; a SEPA environmental review with tribal and public comment is still pending.
Power and water
In Pacific Power (PacifiCorp) service territory (utility inferred from territory, not company-confirmed); regional supply is hydro-dominant.
Amazon's Aug 2026 community materials state the cooling system will use outside air ~93% of the year, with water-based cooling supplementing during the hottest ~7%.
Notes on the record
~$4.8B campus near Wallula, Walla Walla County; operator reported (not officially confirmed) to be AWS, so the record was marked reported. Coordinates are the Wallula area centroid. Operator confirmed as Amazon Data Services when the Port of Walla Walla amended the buyer from Advance Phase LLC to Amazon Data Services (Feb 12, 2026 commission vote; >550 acres for >$36M land), the record was then marked confirmed. The reported ~$4.8B (DCD) / ~$5B (local) campus figure is an estimate across ~4 phases, not a firm pledge, so no investment figure is recorded. Port projects ~720 direct+indirect jobs at full build-out of its four-phase, 16-building concept (projection), so no jobs figure is recorded; Amazon's FAQ for the three-building application projects 120-150 full-time positions. The application before Walla Walla County (the Amazon Attalia Data Center Campus) covers three buildings of about 220,000 sq ft each on a 134-acre parcel, smaller than the Port's concept, so the land area recorded is that parcel. As of October 2026 no cited source states a capacity figure for the campus, so no planned capacity is recorded. Eligible for Washington's rural-county server-equipment sales/use-tax exemption (RCW 82.08.986) but no DOR certificate is confirmed, so no subsidy is recorded. Amazon's August 2026 community materials describe the cooling as outside air about 93% of the year, with water-based cooling (water-soaked pads) for about 7%, and give the cooling-water source as a new non-potable Columbia River supply system being developed with the Port of Walla Walla, with potable groundwater from the utility as temporary cooling water for about a year while that system is built.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- SDC Umatilla Campus · Umatilla · Sabey Data Centers23 mi · Under construction · 150 MW · Supported
- Charlestown Data Center and Battery Energy Storage System · Hermiston · Copia Power24 mi · Proposed
- AWS Hermiston Data Center Campuses · Hermiston · Amazon Web Services24 mi · Operating
- PNNL AI Data Center · Richland · Battelle Memorial Institute (Pacific Northwest National Laboratory)26 mi · Proposed · 2 MW
- Trammell Crow Lewis & Clark Ranch Data Center · West Richland · Trammell Crow Company27 mi · Proposed
- Atlas Agro Richland Data Center Campus · Richland · Atlas Agro North America28 mi · Proposed · 320 MW · Supported
Questions people ask about this site
Is there opposition to the AWS Wallula Gap Campus in Wallula?
Partly. Both documented support and documented opposition to AWS Wallula Gap Campus in Wallula, Walla Walla County, Washington appear in the record, with no clear majority position. Port of Walla Walla commissioners approved the amended land sale unanimously (Feb 12, 2026), calling the project transformative; documented concerns from the Confederated Tribes of the Umatilla Indian Reservation (sacred Snake/Columbia confluence), environmental and academic voices, and a commissioner over water and power.
Has anyone filed a lawsuit over the AWS Wallula Gap Campus?
No lawsuit over AWS Wallula Gap Campus appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AWS Wallula Gap Campus use?
No water withdrawal figure for AWS Wallula Gap Campus is on record here. Cooling is recorded as hybrid, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates AWS Wallula Gap Campus, and how big is it?
Amazon Web Services is the operator on record. We hold 62 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 134 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "AWS Wallula Gap Campus," updated October 28, 2026, https://suedatacenters.org/data-centers/aws-wallula-gap-walla-walla-wa.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-wallula-gap-walla-walla-wa, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.AWS likely behind $4.8bn data center in Walla Walla, Washington · Data Center Dynamics · retrieved July 7, 2026
- 2.Port of Walla Walla names Amazon Data Services as Wallula Gap buyer · Tri-Cities Area Journal of Business · retrieved July 8, 2026
- 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 4.Tri-Cities Area Journal of Business, 'Transformative' $5 billion data center campus planned for Wallula · retrieved July 25, 2026
- 5.Amazon to hold Burbank open house on Walla Walla County data center plan · NBC Right Now · retrieved August 22, 2026
- 6.Amazon's proposed data center application deemed complete by Walla Walla County · Elkhorn Media Group · retrieved September 5, 2026
- 7.Walla Walla County Community Development, Amazon data center project page · Walla Walla County, Washington · retrieved September 14, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us