Data Center Registry
Trammell Crow Lewis & Clark Ranch Data Center
West Richland, Benton County, Washington · All 2 Trammell Crow Company sites
Trammell Crow Lewis & Clark Ranch Data Center is a proposed data center in West Richland, Washington (Benton County), operated by Trammell Crow Company. The public record puts it at 500 acres. The record for this site rests on a single unverified source and should be read that way.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Trammell Crow Company
- Facility type
- Data center
- Location
- West Richland, Benton County, WA
- Coordinates
- 46.3046, -119.3667 (approximate)
- Power capacity
- Not established from a public source
- Land
- 500 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Rumored: a single unverified source
Opposition and litigation at this site
Nothing on record as of August 22, 2026. No lawsuit, organized opposition, or contested hearing over Trammell Crow Lewis & Clark Ranch Data Center in West Richland, Benton County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Feasibility-stage proposal on part of the 7,000-acre Lewis & Clark Ranch; due diligence and a purchase-and-sale agreement with landowner Frank Tiegs LLC underway as of Dec 2025; no capacity or investment figure disclosed; BPA power availability cited as the open question.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Atlas Agro Richland Data Center Campus · Richland · Atlas Agro North America4 mi · Proposed · 320 MW · Supported
- PNNL AI Data Center · Richland · Battelle Memorial Institute (Pacific Northwest National Laboratory)5 mi · Proposed · 2 MW
- SDC Umatilla Campus · Umatilla · Sabey Data Centers27 mi · Under construction · 150 MW · Supported
- AWS Wallula Gap Campus · Wallula · Amazon Web Services27 mi · Proposed · 300 MW · Mixed reception
Questions people ask about this site
Is there opposition to the Trammell Crow Lewis & Clark Ranch Data Center in West Richland?
Nothing on record as of August 22, 2026. No lawsuit, organized opposition, or contested hearing over Trammell Crow Lewis & Clark Ranch Data Center in West Richland, Benton County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Trammell Crow Lewis & Clark Ranch Data Center?
No lawsuit over Trammell Crow Lewis & Clark Ranch Data Center appears in the record we track as of August 22, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Trammell Crow Lewis & Clark Ranch Data Center use?
No water withdrawal figure for Trammell Crow Lewis & Clark Ranch Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Trammell Crow Lewis & Clark Ranch Data Center, and how big is it?
Trammell Crow Company is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 500 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Trammell Crow Lewis & Clark Ranch Data Center," updated August 22, 2026, https://suedatacenters.org/data-centers/trammell-crow-lewis-clark-ranch-west-richland-wa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/trammell-crow-lewis-clark-ranch-west-richland-wa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Company eyes West Richland for future data center · Tri-Cities Area Journal of Business · retrieved August 22, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us