Microsoft Malaga Campus

Malaga, Chelan County, Washington · All 45 Microsoft sites · Every Microsoft case on our tracker

Under constructionMixed receptionAI confirmedRecord updated September 5, 2026

Microsoft Malaga Campus is a data center under construction in Malaga, Washington (Chelan County), operated by Microsoft. The public record puts it at announced March 2023, 288 MW planned, 102.5 acres. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Microsoft
Facility type
Data center, AI use confirmed
Location
Malaga Alcoa Highway, Malaga, Chelan County, WA
Coordinates
47.2300, -120.2000
Power capacity
288 MW planned
Land
102.5 acres
Investment
Not established from a public source
Announced
March 2023
Utility
Chelan County PUD
Power source
Hydro
Cooling
air
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. June 2023
    Under construction
    Construction of first datacenter building commenced June 2023 per Microsoft Local blog; Jumpoff Ridge Substation also under construction on campus Source: Microsoft Local
  2. March 2023
    Permitted
    Permits filed for three data center buildings on Malaga Alcoa Highway; Chelan County Source: Data Center Dynamics
  3. April 2022
    Proposed
    Microsoft acquired 102.5 acres on Malaga Alcoa Highway for $9.2M across three parcels Source: Data Center Dynamics

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Microsoft Malaga Campus in Malaga, Chelan County, Washington appear in the record, with no clear majority position. Chelan County PUD commissioners approved Microsoft's large-load power contract on June 16, 2025 (the first under the PUD's new large-load framework), structured so Microsoft bears the full cost and risk of its demand.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Chelan County PUD commissioners approved Microsoft's large-load power contract on June 16, 2025 (the first under the PUD's new large-load framework), structured so Microsoft bears the full cost and risk of its demand. Public comments centered on preserving reliability and affordable rates for existing customers, with some concern about service priority during energy shortfalls. No litigation.

Source: Chelan County PUD

Power and water

Carbon-free hydropower from Chelan PUD; 18 MW surplus hydropower through end of 2025, then long-term arrangement under utility energy marketing strategy. Under the June 2025 large-load contract, Microsoft will import new clean power from a third-party supplier for 2026-2040 (source undetermined); Chelan PUD is not obligated to serve its own hydropower. Microsoft funded the $86.5M Jumpoff Ridge substation.

Newest AI datacenter buildings designed for no evaporative cooling water use per Microsoft Community-First blog. Earlier permit data shows ~83 gpm per building for fire suppression and employee use, not cooling.

Notes on the record

Three-building campus at 5375 Malaga Alcoa Highway; two additional buildings possible by 2027 on demand. 288 MW figure from secondary aggregator Cleanview only; primary sources (DCD, Microsoft) do not specify MW capacity. Construction of first building began June 2023 per Microsoft Local blog; original statusHistory incorrectly dated under_construction to 2024-05. Expected operational 2026. Coordinates approximate for Malaga area on Malaga Alcoa Highway. A Building-1 permit cites ~72 peak-shift staff (a single-building figure, not a facility employment total); no confirmed total campus capital-expenditure figure is public. Go-live check 2026-08-08: NO citable operational date exists. Microsoft's own Malaga project page gives a first-phase construction window concluding in early 2026 but states plainly that "Completion of construction does not indicate datacenter operation/availability", and publishes no energization or service date. Secondary reporting that the first building would be "powered in August and fully operational by late 2026" is forward-looking and was not used to move the status. Remains under_construction. Microsoft's own Quincy/Central Washington community page states it "operates datacenters in Quincy and is developing new datacenters in Malaga and East Wenatchee", positively confirming the site is not yet operational.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Microsoft Malaga Campus in Malaga?

Partly. Both documented support and documented opposition to Microsoft Malaga Campus in Malaga, Chelan County, Washington appear in the record, with no clear majority position. Chelan County PUD commissioners approved Microsoft's large-load power contract on June 16, 2025 (the first under the PUD's new large-load framework), structured so Microsoft bears the full cost and risk of its demand.

Has anyone filed a lawsuit over the Microsoft Malaga Campus?

No lawsuit over Microsoft Malaga Campus appears in the record we track as of September 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Microsoft Malaga Campus use?

No water withdrawal figure for Microsoft Malaga Campus is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Microsoft Malaga Campus, and how big is it?

Microsoft is the operator on record. We hold 45 sites for that company across the registry. Capacity on record is 288 MW. The site is recorded at 102.5 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Microsoft Malaga Campus," updated September 5, 2026, https://suedatacenters.org/data-centers/microsoft-malaga-wa.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/microsoft-malaga-wa, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Microsoft Plans Three Data Centers in Malaga, Washington · Data Center Dynamics · retrieved July 6, 2026
  2. 2.Malaga Datacenter Project Overview · Microsoft Local · retrieved July 6, 2026
  3. 3.Microsoft Malaga Campus, 288 MW capacity profile · Cleanview · retrieved July 6, 2026
  4. 4.PUD commissioners approve power contract for Microsoft data center · Chelan County PUD · retrieved July 7, 2026
  5. 5.Quincy Community, Microsoft Local · Microsoft · retrieved August 8, 2026
  6. 6.Chelan County PUD commissioners OK energy contract with Microsoft for Malaga data center buildings · The Wenatchee World · retrieved September 5, 2026
  7. 7.A Closer Look: Columbia River Data Centers (February 2026), Chelan County: 24 MW existing / 288 MW planned · Columbia Riverkeeper · retrieved September 5, 2026
  8. 8.Washington state grapples with the AI data center boom · Cascade PBS · retrieved September 5, 2026
  9. 9.Malaga datacenter project overview · Microsoft Local · retrieved September 5, 2026
  10. 10.Washington Utility District OKs $4M Investment in Microsoft Substation · Government Technology · retrieved September 5, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us