Under constructionNo reception on recordRecord updated September 10, 2026

Bitdeer Wenatchee (Pangborn) Data Center is a data center under construction in East Wenatchee, Washington (Douglas County), operated by Bitdeer. The public record puts it at 13 MW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Bitdeer
Facility type
Data center
Location
East Wenatchee, Douglas County, WA
Coordinates
47.4139, -120.2093 (approximate)
Power capacity
13 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
PUD No 1 of Douglas County
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 17, 2026
    Under construction

Opposition and litigation at this site

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Bitdeer Wenatchee (Pangborn) Data Center in East Wenatchee, Douglas County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

Bitdeer's Washington datacenter, referred to as "Pangborn, Washington" in its SEC filings (Pangborn Memorial Airport is in Douglas County, East Wenatchee) and as "Wenatchee, Washington" by aggregators. Originally deployed for Bitcoin mining in May 2018; 13 MW electrical capacity in use as of March 31, 2026. Bitdeer is converting the site to AI cloud use: AI datacenter design documents and building-permit applications submitted, core equipment being delivered, planned to begin with an NVIDIA GB300 cluster; dismantling of the crypto mining datacenter began March 2026 with conversion completion targeted for Q4 2026. Classified data_center (mid-conversion to AI), consistent with the tracked Bitdeer Knoxville TN conversion. Coordinates approximate (Pangborn area, Douglas County). Distinct from Bitdeer's tracked Ohio (Massillon/Clarington/Niles/Shalersville), Texas (Rockdale) and Tennessee (Knoxville) sites. Public-reception check (2026-09-10): Checked Bitdeer's own SEC 20-F annual report (2026-09-10); it mentions Wenatchee, WA only twice (as a mining-to-AI-datacenter conversion site, and as a single-supplier electricity contract location), with no discussion of community reception, hearings, or local reaction.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Bitdeer Wenatchee (Pangborn) Data Center in East Wenatchee?

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Bitdeer Wenatchee (Pangborn) Data Center in East Wenatchee, Douglas County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Bitdeer Wenatchee (Pangborn) Data Center?

No lawsuit over Bitdeer Wenatchee (Pangborn) Data Center appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Bitdeer Wenatchee (Pangborn) Data Center use?

No water withdrawal figure for Bitdeer Wenatchee (Pangborn) Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Bitdeer Wenatchee (Pangborn) Data Center, and how big is it?

Bitdeer is the operator on record. We hold 7 sites for that company across the registry. Capacity on record is 13 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Bitdeer Wenatchee (Pangborn) Data Center," updated September 10, 2026, https://suedatacenters.org/data-centers/bitdeer-wenatchee-pangborn-wa.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/bitdeer-wenatchee-pangborn-wa, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Bitdeer Technologies Group FY2025 Form 20-F (filed 2026-04-30), Item 4.D Property: Pangborn, Washington datacenter, 13 MW, operational May 2018, being converted to AI cloud (GB300 cluster; permits submitted; crypto dismantling began March 2026; target Q4 2026) · U.S. Securities and Exchange Commission (EDGAR) · retrieved July 17, 2026
  2. 2.Data Center Map, Bitdeer Wenatchee, Washington (13 MW) · Data Center Map · retrieved July 17, 2026
  3. 3.DCD, Bitdeer crypto-to-AI conversion program (Washington among the sites being converted, GB300, Q4 2026) · Data Center Dynamics · retrieved July 17, 2026
  4. 4.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us