Data Center Registry
Scranton Materials Data Center Campus (819 Newton Road quarry)
Ransom Township, Lackawanna County, Pennsylvania
Scranton Materials Data Center Campus (819 Newton Road quarry) is a proposed data center in Ransom Township, Pennsylvania (Lackawanna County), operated by Scranton Materials LLC. The public record puts it at 251 acres. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Scranton Materials LLC
- Facility type
- Data center
- Location
- 819 Newton Road, Ransom Township, Lackawanna County, PA
- Coordinates
- 41.4400, -75.7041 (approximate)
- Power capacity
- Not established from a public source
- Land
- 251 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- In litigation
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 27, 2026ProposedOverlay request denied. Developer appeal pending in court. Source: WVIA
Opposition and litigation at this site
Yes. Scranton Materials Data Center Campus (819 Newton Road quarry) in Ransom Township, Lackawanna County, Pennsylvania is or has been the subject of litigation over its siting, permitting, or operation. Supervisors denied the zoning overlay in January 2026 after resident objections.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Supervisors denied the zoning overlay in January 2026 after resident objections. Scranton Materials appealed, and in June a judge ruled a resident has standing to challenge the project. The appeal is pending.
Notes on the record
Six data center buildings proposed at the company's stone quarry. This is a separate site and application from the Mudiita Land Venture property (as of October 2026, tracked separately as cancelled); the 'no plans' quote in the July article refers to Mudiita, not Scranton Materials. The pin is the census geocode of the address.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Mudiita Ransom Township Data Center Campus · Ransom Township · Mudiita Land Venture LLC2 mi · Cancelled · 750 MW
- Newton Township Data Center Campus (Newton Road) · Newton Township · Popca LLC3 mi · Proposed
- Dickson City Data Center (Bell Mountain) · Dickson City · Dickson City Development LLC5 mi · Proposed · In litigation
- Blakely Borough Data Center (withdrawn) · Blakely · Undisclosed developer (Blakely rezoning applicant)6 mi · Cancelled · Opposed
- Triboro Industrial Park / Triboro Commerce Park · Jessup / Olyphant · Ercor Triboro LLC (Sansone Group)6 mi · Permitted · In litigation
- Breaker Street Data Center Campus · Jessup · Breaker Street Associates LLC (Catalyst Commercial Development)8 mi · Proposed · 600 MW · Contested
- Archbald I Campus 1 Data Center (Eynon Jermyn Road) · Archbald · Archbald I LLC9 mi · Proposed
- Project Gravity · Archbald · Archbald 25 Developer LLC9 mi · Proposed · Mixed reception
Questions people ask about this site
Is there opposition to the Scranton Materials Data Center Campus (819 Newton Road quarry) in Ransom Township?
Yes. Scranton Materials Data Center Campus (819 Newton Road quarry) in Ransom Township, Lackawanna County, Pennsylvania is or has been the subject of litigation over its siting, permitting, or operation. Supervisors denied the zoning overlay in January 2026 after resident objections.
Has anyone filed a lawsuit over the Scranton Materials Data Center Campus (819 Newton Road quarry)?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does Scranton Materials Data Center Campus (819 Newton Road quarry) use?
No water withdrawal figure for Scranton Materials Data Center Campus (819 Newton Road quarry) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Scranton Materials Data Center Campus (819 Newton Road quarry), and how big is it?
Scranton Materials LLC is the operator on record. No capacity figure is on record for this site. The site is recorded at 251 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Scranton Materials Data Center Campus (819 Newton Road quarry)," updated October 15, 2026, https://suedatacenters.org/data-centers/scranton-materials-ransom-township-data-center-lackawanna-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/scranton-materials-ransom-township-data-center-lackawanna-pa, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Future of Ransom Twp. property uncertain as developer says 'no plans' for data center campus · WVIA · retrieved October 15, 2026
- 2.Proposed Newton data center campus is 10th planned for Lackawanna County · WVIA · retrieved October 15, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us