Sue Data Centers

Data Center Registry

LightEdge Ames Edge Colocation Data Center

Ames, Story County, Iowa · All 2 LightEdge Solutions sites

ProposedContestedRecord updated August 21, 2026

LightEdge Ames Edge Colocation Data Center is a proposed data center in Ames, Iowa (Story County), operated by LightEdge Solutions. The public record puts it at 25 MW planned, 10.86 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

What our reporting adds

Our case file documents this site. No lawsuit filed; proposal in the hearing stage before the Ames City Council, resident study committee applications close September 9, 2026.

Facility record

Proposed

Operator
LightEdge Solutions
Facility type
Data center
Location
Aviation Way, Ames, Story County, IA
Coordinates
42.0308, -93.6319 (approximate)
Power capacity
25 MW planned
Land
10.86 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
air
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. June 23, 2026
    Proposed
    Ames City Council first reading on the proposal to lease city airport land to LightEdge; decision point scheduled for 2026-07-28. Source: LightEdge Solutions

Opposition and litigation at this site

Yes. LightEdge Ames Edge Colocation Data Center in Ames, Story County, Iowa is contested. Hearings, public comment, petitions, or organized opposition are on record. No lawsuit filed; proposal in the hearing stage before the Ames City Council, resident study committee applications close September 9, 2026.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

No lawsuit filed; proposal in the hearing stage before the Ames City Council, resident study committee applications close September 9, 2026. The proposal would lease city-owned airport land, which put it in front of the council and the public: a first reading on 2026-06-23, a public listening session on 2026-06-30, and a decision point set for the 2026-07-28 council meeting. Residents organised against it, and the council acknowledged the proposal raises electrical capacity, transmission and distribution, and utility rate questions for Ames Electric Services. Reported estimates put a required dedicated substation at about $12 million. LightEdge's own materials push back on jobs expectations, stating data centers are 'not large direct employers' and that 'staffing on site for a facility like this is small.'

Source: LightEdge Solutions

Power and water

Air-cooled using chillers and fans rather than evaporative systems; LightEdge's proposal states approximately 0 gallons per day of cooling water, and cites its Altoona facility's 1,267 gallons a day, 5 percent of Iowa's 25,000-gallon permit threshold, as the reference case.

Notes on the record

Proposed single-storey edge colocation facility on roughly 10.86 acres of Ames airport land on Aviation Way, in a Planned Industrial zone, adjacent to the Ames Regional Airport and the ISU Research Park. Phased electrical demand of 3 MW in phase one, 6 MW in phase two, and as much as 25 MW at full buildout over roughly ten years, reported locally as about a 15 percent increase in the city's total consumption. LightEdge explicitly rules out AI or hyperscale use: asked whether it would house AI servers, its proposal answers 'No. This is edge colocation.' aiClassification is therefore omitted. Reported at roughly 100,000 sq ft in local coverage, but the operator's own page does not state a square footage, so it is not recorded. Distinct site from the tracked LightEdge Altoona facility.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the LightEdge Ames Edge Colocation Data Center in Ames?

Yes. LightEdge Ames Edge Colocation Data Center in Ames, Story County, Iowa is contested. Hearings, public comment, petitions, or organized opposition are on record. No lawsuit filed; proposal in the hearing stage before the Ames City Council, resident study committee applications close September 9, 2026.

Has anyone filed a lawsuit over the LightEdge Ames Edge Colocation Data Center?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does LightEdge Ames Edge Colocation Data Center use?

No water withdrawal figure for LightEdge Ames Edge Colocation Data Center is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates LightEdge Ames Edge Colocation Data Center, and how big is it?

LightEdge Solutions is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 25 MW. The site is recorded at 10.86 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "LightEdge Ames Edge Colocation Data Center," updated August 21, 2026, https://suedatacenters.org/data-centers/lightedge-ames-ia.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/lightedge-ames-ia, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Ames Data Center Proposal, LightEdge edge colocation project page · LightEdge Solutions · retrieved August 14, 2026
  2. 2.Ames Data Center Proposal, LightEdge · LightEdge Solutions · retrieved August 21, 2026
  3. 3.Ames, Iowa Has Not Decided Yet. A Data Center Is Proposed on City Land, and Residents Can Still Apply to the Committee That Advises the Vote. · SueDataCenters.org · retrieved September 3, 2026
  4. 4.City of Ames: Data Center Development Updates (project page, timeline, and study committee application link) · cityofames.org · retrieved September 3, 2026
  5. 5.City of Ames: Staff Report, Request from Lightedge to Consider Data Center Development on Airport Property, June 16, 2026, with the LightEdge letter attached · publicdocs.cityofames.org · retrieved September 3, 2026
  6. 6.City of Ames: Staff Report to City Council, June 23, 2026, item 31, with electric infrastructure cost estimates and alternative sites · publicdocs.cityofames.org · retrieved September 3, 2026
  7. 7.City of Ames: City Council Listening Session, June 30, 2026, thirteen breakout groups with posted notes, transcriptions, poll results and feedback forms · cityofames.org · retrieved September 3, 2026
  8. 8.City of Ames: Staff Report on Data Centers, July 14, 2026, summarizing the City Attorney memo and fourteen regulatory options · cityofames.org · retrieved September 3, 2026
  9. 9.City of Ames: Council Action Form, Temporary Delay in Allowing Data Center Developments, July 28, 2026, with the task schedule and the proposed data center definition · cityofames.org · retrieved September 3, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us