Data Center Registry
Tract Norwalk Data Center Park (Project West)
Norwalk, Warren County, Iowa · All 15 Tract sites
Tract Norwalk Data Center Park (Project West) is a proposed data center in Norwalk, Iowa (Warren County), operated by Tract. The public record puts it at announced March 5, 2026, 282 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Tract
- Facility type
- Data center
- Location
- Norwalk, Warren County, IA
- Coordinates
- 41.4610, -93.6979 (approximate)
- Power capacity
- Not established from a public source
- Land
- 282 acres
- Investment
- Not established from a public source
- Announced
- March 5, 2026
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- March 5, 2026ProposedNorwalk City Council approved a site development agreement with Tract for a 282-acre site west of Highway 28 and south of Delaware Street. The city stressed the vote does not itself approve a data center; a future operator would need separate city, state and federal review. Source: City of Norwalk, Iowa
Opposition and litigation at this site
Yes. Tract Norwalk Data Center Park (Project West) in Norwalk, Warren County, Iowa is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. City hall and a library overflow room were packed for the March 5, 2026 hearing, with more than two hours of public comment focused on water sustainability and environmental impact; the council approved the agreement unanimously with one member absent.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
City hall and a library overflow room were packed for the March 5, 2026 hearing, with more than two hours of public comment focused on water sustainability and environmental impact; the council approved the agreement unanimously with one member absent.
Power and water
The city's site development agreement dedicates 400,000 gallons per day of water capacity to the developer, against a planned industrial reserve of 650,000 gpd.
Notes on the record
Tract is a master-planned data center park developer; it buys, entitles and powers land rather than operating data centers itself, so the eventual operator is not yet named. The city projects roughly $5 million a year in new city property tax revenue ($15 million across all taxing entities) and says no tax incentives were offered, only a waiver of sanitary sewer district fees. Local reporting cites a roughly $12 billion eventual campus investment; that figure is a city expectation for a future, unnamed operator rather than a committed site-level investment, so it is not recorded as investmentUsd.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Microsoft Project Alluvion Data Center · West Des Moines · Microsoft4 mi · Operating
- Microsoft Project Ginger East Data Center · West Des Moines · Microsoft4 mi · Under construction
- Microsoft Project Osmium Data Center · West Des Moines · Microsoft5 mi · Under construction
- Microsoft Project Ruthenium Data Center · West Des Moines · Microsoft6 mi · Proposed
- Microsoft Project Ginger West Data Center · West Des Moines · Microsoft8 mi · Under construction · Mixed reception
- Microsoft Project Mountain Data Center · West Des Moines · Microsoft8 mi · Operating
- Aureon 616 Data Center · Des Moines · Aureon9 mi · Operating
- Oppidan Des Moines Data Center · Des Moines · Oppidan9 mi · Operating · 5 MW
Questions people ask about this site
Is there opposition to the Tract Norwalk Data Center Park (Project West) in Norwalk?
Yes. Tract Norwalk Data Center Park (Project West) in Norwalk, Warren County, Iowa is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. City hall and a library overflow room were packed for the March 5, 2026 hearing, with more than two hours of public comment focused on water sustainability and environmental impact; the council approved the agreement unanimously with one member absent.
Has anyone filed a lawsuit over the Tract Norwalk Data Center Park (Project West)?
No lawsuit over Tract Norwalk Data Center Park (Project West) appears in the record we track as of September 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Tract Norwalk Data Center Park (Project West) use?
No water withdrawal figure for Tract Norwalk Data Center Park (Project West) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Tract Norwalk Data Center Park (Project West), and how big is it?
Tract is the operator on record. We hold 15 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 282 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Tract Norwalk Data Center Park (Project West)," updated September 4, 2026, https://suedatacenters.org/data-centers/tract-norwalk-ia.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tract-norwalk-ia, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Attention Norwalk Residents, statement on the land developer agreement · City of Norwalk, Iowa · retrieved September 4, 2026
- 2.Norwalk City Council approved data center development agreement despite citizen concerns · Indianola Record-Herald · retrieved September 4, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us