Kenwood Commons Technology Campus

Albany, Albany County, New York

ProposedContestedAI mixed useRecord updated October 28, 2026

Kenwood Commons Technology Campus is a proposed data center in Albany, New York (Albany County), operated by Guild Ventures. The public record puts it at 76 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Guild Ventures
Facility type
Data center, AI use mixed
Location
Albany, Albany County, NY
Coordinates
42.6225, -73.7601 (approximate)
Power capacity
Not established from a public source
Land
76 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
National Grid
Cooling
Not established
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Yes. Kenwood Commons Technology Campus in Albany, Albany County, New York is contested. Hearings, public comment, petitions, or organized opposition are on record. About 75 people attended an August 2026 Council of Albany Neighborhood Associations meeting on the plan.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

About 75 people attended an August 2026 Council of Albany Neighborhood Associations meeting on the plan. An opponent from No Kings Collective Albany raised electricity, environmental and affordability concerns. The Albany Common Council passed a resolution supporting a statewide moratorium. The developers said no formal application has been filed.

Source: WAMC Northeast Public Radio

Power and water

NYISO load queue #1754 (EKG Group LLC, 'Kenwood Tech Center') lists National Grid as the connecting utility. The 180 MW request is a whole-site study ceiling for the mixed-use development; the developer says the data center itself could use up to 100 MW and would be on its own meter.

CBS6 reports the developer describes "cooling that repurposes heat for local use rather than consuming water." WAMC (August 2026) reports the developers said the data center will use an air-cooling system that will not require lots of water. As of October 2026, none of the cited articles says whether the cooling uses a recirculating water circuit, and none gives a water figure, so the heat-rejection method is unresolved.

Notes on the record

Proposed data center inside a mixed-use redevelopment of the 76-acre former Kenwood convent / Doane Stuart School property in Albany. No capacity is recorded: "Guild Ventures... filed an application with the New York Independent System Operator to use 180MW for the project," but the developer told CBS6 the 180 MW is "a theoretical ceiling for the entire mixed-use development" at full buildout and not the data center's expected use. Recording 180 as the facility's capacity would therefore be wrong. CBS6 reported in July 2026 that the developer has said the data center could use up to 100 MW; that is a ceiling, not a planned total, and at an August 2026 community meeting the developers said they did not yet know how many megawatts the data center would need (WAMC), so it is not recorded either. WAMC (August 2026) also reports the developers project a 250,000-square-foot data center with 125 to 175 full-time jobs and an online date of December 2028; these are developer projections and no size or job figure is recorded. The Rockefeller Institute's tracker separately describes it as "a 180 MW data center as part of a mixed-use development" - that reading conflicts with the developer's own clarification, which is why the record is marked reported. The developer describes the compute component as a "boutique, edge-scale colocation center" on "approximately 5 acres" of the 76-acre parcel serving hospitals, institutions, nanotech, government services and local employers - hence the mixed-use AI classification. The 76-acre figure is the whole redevelopment parcel, not the data center footprint. As of 2026-09-09, no permits had been submitted to the City of Albany per the reporting retrieved, and the May 2026 CBS6 article gives no investment figure and states no job counts, utility, or IDA/PILOT agreement. The connecting utility, National Grid, is stated in NYISO load queue #1754. Coordinates geocoded to the named Kenwood / Doane Stuart site in Albany, approximate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Kenwood Commons Technology Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Kenwood Commons Technology Campus in Albany?

Yes. Kenwood Commons Technology Campus in Albany, Albany County, New York is contested. Hearings, public comment, petitions, or organized opposition are on record. About 75 people attended an August 2026 Council of Albany Neighborhood Associations meeting on the plan.

Has anyone filed a lawsuit over the Kenwood Commons Technology Campus?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does Kenwood Commons Technology Campus use?

No water withdrawal figure for Kenwood Commons Technology Campus is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Kenwood Commons Technology Campus, and how big is it?

Guild Ventures is the operator on record. No capacity figure is on record for this site. The site is recorded at 76 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Kenwood Commons Technology Campus," updated October 28, 2026, https://suedatacenters.org/data-centers/guild-ventures-kenwood-commons-albany-ny.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/guild-ventures-kenwood-commons-albany-ny, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Kenwood Commons owner asks for 180MW as part of property's pitch, now includes data center · CBS6 Albany (WRGB) · retrieved September 9, 2026
  2. 2.Updates on the Cloud: More Moratoriums on Data Centers · Rockefeller Institute of Government · retrieved September 9, 2026
  3. 3.Albany data center proposal faces new questions after Hochul's statewide moratorium (July 14, 2026) · CBS6 Albany (WRGB) · retrieved October 9, 2026
  4. 4.Kenwood data center developers try to assuage community concerns (Aug 6, 2026) · WAMC Northeast Public Radio · retrieved October 9, 2026
  5. 5.NYISO Interconnection Queue, Load Projects: #1754 'Kenwood Tech Center', EKG Group LLC, 180 MW, POI Albany-Bethlehem 115 kV Line #18, utility National Grid, status 4 · New York Independent System Operator · retrieved October 9, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us