Sagebrush Hallam Hyperscale Campus (proposed)

Hallam, Lancaster County, Nebraska

ProposedContestedAI likelyRecord updated September 4, 2026

Sagebrush Hallam Hyperscale Campus (proposed) is a proposed data center in Hallam, Nebraska (Lancaster County), operated by Sagebrush Infrastructure Partners. The public record puts it at announced August 2026, 1.7 GW planned, 1,400 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Sagebrush Infrastructure Partners
Facility type
Data center, AI use likely
Location
Hallam, Lancaster County, NE
Coordinates
40.5450, -96.7992 (approximate)
Power capacity
1.7 GW planned
Land
1,400 acres
Investment
Not established from a public source
Announced
August 2026
Utility
Not established from a public source
Power source
On site gas
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. August 27, 2026
    Proposed
    Land options across 1,400+ acres in southwestern Lancaster County reported; no application filed. Source: 1011 NOW (KOLN)

Opposition and litigation at this site

Yes. Sagebrush Hallam Hyperscale Campus (proposed) in Hallam, Lancaster County, Nebraska is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Thirteen landowners signed purchase options between December 2025 and mid-March 2026; a farmer who declined said the project "caused a bunch of division in the community among neighbors" and objected to turning Hallam from "a small, sleepy farming community" into "an industrial center." Lancaster County commissioners were separately weighing a 12-month data-center moratorium in August 2026.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Thirteen landowners signed purchase options between December 2025 and mid-March 2026; a farmer who declined said the project "caused a bunch of division in the community among neighbors" and objected to turning Hallam from "a small, sleepy farming community" into "an industrial center." Lancaster County commissioners were separately weighing a 12-month data-center moratorium in August 2026. Stark's VP of digital infrastructure said "no final decision has been made at this time."

Source: Nebraska Public Media

Power and water

Sagebrush is described as a developer of hyperscale data centers with co-located natural gas-fired power plants. Reporting says the developer wants natural gas, water, and a grid interconnection as a redundant source: "They're going to provide their own power, but they also want to hook up to the grid in case their power goes down." The optioned land sits near NPPD's Sheldon Station and its Princeton Road Station site.

Notes on the record

Land assemblage only, memorandums of purchase agreement with 13 landowners along Southwest 58th Street just west of Hallam, giving exclusivity windows of roughly six months to four years. Sagebrush Infrastructure Partners LLC was acquired by Tel Aviv-based Stark Power in June 2026 as part of a reported 5.6 GW US development pipeline; the Hallam site is one of five planned hyperscale campuses targeting MISO and SPP territory. Coordinates are an approximation of the reported SW 58th Street assemblage west of Hallam; no parcel map has been published. Distinct from the separate 35 MW Monolith/Crusoe proposal inside the Village of Hallam's zoning jurisdiction.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Sagebrush Hallam Hyperscale Campus (proposed) in Hallam?

Yes. Sagebrush Hallam Hyperscale Campus (proposed) in Hallam, Lancaster County, Nebraska is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Thirteen landowners signed purchase options between December 2025 and mid-March 2026; a farmer who declined said the project "caused a bunch of division in the community among neighbors" and objected to turning Hallam from "a small, sleepy farming community" into "an industrial center." Lancaster County commissioners were separately weighing a 12-month data-center moratorium in August 2026.

Has anyone filed a lawsuit over the Sagebrush Hallam Hyperscale Campus (proposed)?

No lawsuit over Sagebrush Hallam Hyperscale Campus (proposed) appears in the record we track as of September 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Sagebrush Hallam Hyperscale Campus (proposed) use?

No water withdrawal figure for Sagebrush Hallam Hyperscale Campus (proposed) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Sagebrush Hallam Hyperscale Campus (proposed), and how big is it?

Sagebrush Infrastructure Partners is the operator on record. Capacity on record is 1.7 GW. The site is recorded at 1400 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Sagebrush Hallam Hyperscale Campus (proposed)," updated September 4, 2026, https://suedatacenters.org/data-centers/sagebrush-hallam-hyperscale-campus-lancaster-ne.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/sagebrush-hallam-hyperscale-campus-lancaster-ne, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data center developers eyeing land near Hallam · 1011 NOW (KOLN) · retrieved September 4, 2026
  2. 2.Hallam landowners face stark choice on data center · Nebraska Public Media · retrieved September 4, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us