Facility record
Operating
- Operator
- Jigowatt
- Facility type
- Crypto mining
- Location
- Stanton, Stanton County, NE
- Coordinates
- 41.9472, -97.2172 (approximate)
- Power capacity
- 20 MW operating; 70 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- 2023
- Utility
- Not established from a public source
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Yes. Organized local opposition to Jigowatt Stanton Bitcoin Mine in Stanton, Stanton County, Nebraska is documented in the public record, without a lawsuit on file in the sources we track.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Notes on the record
Lincoln-based Jigowatt began installing shipping-container-housed mining rigs (a mix of air-cooled and immersion-cooled containers) on Stanton Public Power District's (SPPD) grid near Stanton starting in 2023; SPPD created a discounted "interruptible" large-load electric rate to recruit/retain the customer. Jigowatt is now Stanton County's largest electricity customer by far and is seeking to roughly triple its allowed load, backed by a ~$20M ratepayer-funded distribution upgrade and an NPPD transmission project that has drawn eminent-domain objections from area landowners (reported June/July 2025). Neighbors half a mile or more away (e.g., the Wortmanns) report a persistent low-frequency hum/vibration and resulting health/property concerns; one neighbor abandoned plans to build a new home nearby. MW capacity not publicly disclosed in the coverage reviewed.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Questions people ask about this site
Is there opposition to the Jigowatt Stanton Bitcoin Mine in Stanton?
Yes. Organized local opposition to Jigowatt Stanton Bitcoin Mine in Stanton, Stanton County, Nebraska is documented in the public record, without a lawsuit on file in the sources we track.
Has anyone filed a lawsuit over the Jigowatt Stanton Bitcoin Mine?
No lawsuit over Jigowatt Stanton Bitcoin Mine appears in the record we track as of August 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Jigowatt Stanton Bitcoin Mine use?
No water withdrawal figure for Jigowatt Stanton Bitcoin Mine is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Jigowatt Stanton Bitcoin Mine, and how big is it?
Jigowatt is the operator on record. Capacity on record is 70 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Jigowatt Stanton Bitcoin Mine," updated August 8, 2026, https://suedatacenters.org/data-centers/jigowatt-stanton-ne.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/jigowatt-stanton-ne, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Crypto needs cheap energy. It found a whole bunch in Nebraska. · Flatwater Free Press · retrieved August 5, 2026
- 2.Bitcoin descended on a small Nebraska county bringing big business, with big complaints from neighbors · KTIV · retrieved August 5, 2026
- 3.A Nebraska crypto company wants to get bigger. Landowners decry NPPD's use of eminent domain that will help it grow. · 1011now (KOLN) · retrieved August 5, 2026
- 4.Many positives and negatives coming from new data mining facility in Stanton County · Norfolk NE Radio · retrieved August 5, 2026
- 5.A Nebraska crypto company wants to get bigger; landowners decry NPPD's use of eminent domain · Flatwater Free Press · retrieved August 8, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us