North Country Collocation Services Massena Data Center (former Reynolds site)

Massena, St. Lawrence County, New York

ProposedContestedAI likelyRecord updated September 9, 2026

North Country Collocation Services Massena Data Center (former Reynolds site) is a proposed data center in Massena, New York (St. Lawrence County), operated by North Country Collocation Services (NCCS). The public record puts it at 635 MW planned. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
North Country Collocation Services (NCCS)
Facility type
Data center, AI use likely
Location
Massena, St. Lawrence County, NY
Coordinates
44.9790, -74.7300 (approximate)
Power capacity
635 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. May 2026
    Proposed
    Massena Town Planning Board heard the proposal for the first time on May 21, 2026 and took no action. Source: North Country Public Radio

Opposition and litigation at this site

Yes. North Country Collocation Services Massena Data Center (former Reynolds site) in Massena, St. Lawrence County, New York is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. NCPR reports "about 80 people" attended the May 21, 2026 planning board meeting, that "some shouted their opposition and questions from the audience," and quotes a resident of Akwesasne (the Mohawk territory less than two miles from the site) asking for more community engagement.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

NCPR reports "about 80 people" attended the May 21, 2026 planning board meeting, that "some shouted their opposition and questions from the audience," and quotes a resident of Akwesasne (the Mohawk territory less than two miles from the site) asking for more community engagement. The meeting was not a public hearing; the board chair said a public hearing will follow and "the process could take months." A residents' group, Massena Data Center Watch, campaigns against the project.

Source: North Country Public Radio

Notes on the record

⚠️ ADJUDICATION REQUIRED - POSSIBLE OVERLAP WITH AN EXISTING ROW. NCPR states "the facility would include three buildings totaling nearly 1.5 million square feet at the former Reynolds site, about eight miles outside of the village of Massena and near the bridge to Canada. The operation would consume 635 megawatts of power. That equates to roughly 70% of the power produced at the Moses-Saunders Power Dam. The developer, North Country Collocation Services, or NCCS, presented its plan to the board." The former Reynolds Metals plant is the same industrial complex as the 'Alcoa East' site that the existing crypto_mining row coinmint-massena-ny sits on (that row is at 44.9777, -74.7327), and trade press frames this as NYDIG - the current owner of that mining operation - seeking to EXPAND at the Massena site. I have recorded it as a separate proposed data_center because the three buildings, the 635 MW load and the planning-board proceeding are a distinct new project with a distinct developer entity, but if the maintainer prefers one row per site this should be folded into coinmint-massena-ny instead. Coordinates are an approximate placement on that industrial complex derived from the source's description, NOT a surveyed parcel. Confirmed absences (2026-09-09): the fetched sources state no investment figure, no job counts, no acreage, no water-use figure, no utility, and no subsidy or IDA agreement. NOT recorded because unverified in this run: reporting elsewhere describes 316 diesel generators on site and a zoning question referred to the Zoning Board of Appeals over whether a large-scale data center is a permitted use in the industrial zone.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the North Country Collocation Services Massena Data Center (former Reynolds site) in Massena?

Yes. North Country Collocation Services Massena Data Center (former Reynolds site) in Massena, St. Lawrence County, New York is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. NCPR reports "about 80 people" attended the May 21, 2026 planning board meeting, that "some shouted their opposition and questions from the audience," and quotes a resident of Akwesasne (the Mohawk territory less than two miles from the site) asking for more community engagement.

Has anyone filed a lawsuit over the North Country Collocation Services Massena Data Center (former Reynolds site)?

No lawsuit over North Country Collocation Services Massena Data Center (former Reynolds site) appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does North Country Collocation Services Massena Data Center (former Reynolds site) use?

No water withdrawal figure for North Country Collocation Services Massena Data Center (former Reynolds site) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates North Country Collocation Services Massena Data Center (former Reynolds site), and how big is it?

North Country Collocation Services (NCCS) is the operator on record. Capacity on record is 635 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "North Country Collocation Services Massena Data Center (former Reynolds site)," updated September 9, 2026, https://suedatacenters.org/data-centers/nccs-massena-reynolds-ny.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/nccs-massena-reynolds-ny, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Massena Town Planning Board takes no action at data center meeting · North Country Public Radio · retrieved September 9, 2026
  2. 2.Updates on the Cloud: More Moratoriums on Data Centers · Rockefeller Institute of Government · retrieved September 9, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us