Middletown Technology Center (Cirrus Delaware LLC)
Middletown, New Castle County, Delaware
Middletown Technology Center (Cirrus Delaware LLC) is a proposed data center in Middletown, Delaware (New Castle County), operated by Cirrus Delaware, LLC. The public record puts it at 40 MW planned, 70 acres, a reported $350 million investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Cirrus Delaware, LLC
- Facility type
- Data center
- Location
- Middletown, New Castle County, DE
- Coordinates
- 39.4498, -75.7166 (approximate)
- Power capacity
- 40 MW planned
- Land
- 70 acres
- Investment
- $350 million
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Power source
- Mixed
- On site generation
- 52.5 MW
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 117 permanent; 750 construction
- Public subsidy
- Delaware Infrastructure Investment Committee grant (reimbursement-only; conditioned on a state air permit within 12 months and financing disclosure), State of Delaware, 2016
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 2017ProposedPer the dcmap.us activity log, Cirrus put its Middletown air-permit application on hold. No later activity was found. Source: dcmap.us
- May 4, 2016ProposedDelaware Infrastructure Investment Committee voted 4-0 to approve up to $7.5M in New Jobs Infrastructure Fund money for the project's utility infrastructure. The approval was conditioned on a DNREC air permit, financing disclosure, identification of the operator, and payment on a reimbursement basis. Source: Delaware Economic Development Office
- 2015ProposedMiddletown Town Council approved plans for the Middletown Technology Center: a 228,000 sq ft, 40 MW data center with a natural-gas cogeneration plant on 70 acres in the town's Westown area. DBT reports the approval came in August 2015. Data Center Knowledge's report is dated Aug 5, 2015. Source: Delaware Business Times
Opposition and litigation at this site
Yes. Middletown Technology Center (Cirrus Delaware LLC) in Middletown, New Castle County, Delaware is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Residents opposed the gas plant over air emissions and property values.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Residents opposed the gas plant over air emissions and property values. Two petitions gathered 530 signatures (2015), and members of the public questioned taxpayer funding for a company with undisclosed financiers (2016).
Power and water
Per the applicant at the May 2016 IIC meeting, the facility would 'mostly pull power from the PJM grid from Middletown' over 138 kV lines from an adjacent substation. An on-site natural-gas cogeneration plant would supply redundancy and peak-period power within air-permit hour limits. DBT and Data Center Knowledge (2015) give the gas plant as 52.5 MW. At the 2016 IIC meeting the applicant described the data center as 40 MW, with 36 MW of white space at a design PUE of 1.4, for a 50 MW total requirement at full build.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Delaware Infrastructure Investment Committee grant (reimbursement-only; conditioned on a state air permit within 12 months and financing disclosure) | Not established | State of Delaware | 2016 |
Notes on the record
Never built, and apparently dormant since the air-permit application was put on hold in October 2017. The record stays listed as proposed because, as of October 2026, no source records a formal withdrawal or cancellation. Treat the status as stalled, not active. The state grant was approved at up to $7.5M (the committee minutes record the request as "up to $7,500,000") and was conditional and reimbursement-only, so no grant amount is recorded. As of October 2026, no evidence was found that it was disbursed, so the record lists it as the IIC's May 2016 approval, not as money paid. Sources disagree on cost: $250M (DCK 2015), about $400M (DBT 2015) and $350M (applicant, IIC 2016). The recorded investment figure is the applicant's $350M estimate, which the AP also reported in May 2016. Jobs figures are the applicant's 2016 IIC projections. DBT 2015 cited 'more than 100' full-time and up to 2,000 construction jobs. Partners named at the IIC meeting were Duffield Associates (now Verdantas), MEP Associates and landowner Mautom, LLC. The end operator was never disclosed. The pin is Middletown's OSM boundary centroid, because the 70-acre Westown parcel did not resolve to a point.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- St. Georges Business Park & Lighthouse Farms · St. Georges · Parkway Gravel Inc.8 mi · Proposed · 300 MW · Contested
- Project Washington (Starwood Digital Ventures) · Delaware City · Starwood Digital Ventures11 mi · Proposed · 1.2 GW · In litigation
- Data Canopy Newark (350 Pencader Drive) · Newark · Data Canopy11 mi · Operating
- JPMorgan Chase Core Data Center 1 (CDC1), Bear · Bear · JPMorgan Chase Bank, N.A.14 mi · Operating
- Lumen Newark (504 Interchange Boulevard) · Newark · Lumen Technologies15 mi · Operating
- STAR Campus Data Center & Cogeneration Plant (The Data Centers, LLC) · Newark · The Data Centers, LLC15 mi · Cancelled · Opposed
- White Clay Corporate Center Data Center Redevelopment · Newark · Shelbourne16 mi · Proposed · Contested
- DāSTOR New Castle (3 Boulden Circle) · New Castle · DāSTOR LLC18 mi · Operating · 8 MW
Questions people ask about this site
Is there opposition to the Middletown Technology Center (Cirrus Delaware LLC) data center in Middletown?
Yes. Middletown Technology Center (Cirrus Delaware LLC) in Middletown, New Castle County, Delaware is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Residents opposed the gas plant over air emissions and property values.
Has anyone filed a lawsuit over the Middletown Technology Center (Cirrus Delaware LLC) data center?
No lawsuit over Middletown Technology Center (Cirrus Delaware LLC) appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Middletown Technology Center (Cirrus Delaware LLC) use?
No water withdrawal figure for Middletown Technology Center (Cirrus Delaware LLC) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Middletown Technology Center (Cirrus Delaware LLC), and how big is it?
Cirrus Delaware, LLC is the operator on record. Capacity on record is 40 MW. The site is recorded at 70 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Middletown Technology Center (Cirrus Delaware LLC)," updated October 28, 2026, https://suedatacenters.org/data-centers/cirrus-delaware-middletown-technology-center-de.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cirrus-delaware-middletown-technology-center-de, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Plans afoot for Middletown data center, power plant (70 acres, 228,000 sq ft, 40 MW, 52.5 MW co-generation) · Delaware Business Times · retrieved October 1, 2026
- 2.Delaware Infrastructure Investment Committee minutes, May 4, 2016: Cirrus Delaware, LLC request for up to $7,500,000 · Delaware Economic Development Office · retrieved October 1, 2026
- 3.Officials Approve Data Center and Cogen Plant Project in Delaware · Data Center Knowledge · retrieved October 1, 2026
- 4.Delaware Data Center Map: Cirrus Delaware Middletown Technology Center, 'Paused' (Mar 2016 air-permit application; Oct 2017 put on hold) · dcmap.us · retrieved October 1, 2026
- 5.Officials Approve Data Center and Cogen Plant Project in Delaware (Aug 5, 2015) · Data Center Knowledge · retrieved October 20, 2026
- 6.Middletown Data Center Gets $7.5 Million State Grant (AP, May 5, 2016) · Delmarva Public Media · retrieved October 20, 2026
- 7.Panel OKs state funding for Middletown data center project (May 5, 2016) · WMDT · retrieved October 20, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us