Quantum Frederick

Frederick, Frederick County, Maryland

Under constructionContestedRecord updated October 22, 2026

Quantum Frederick is a data center under construction in Frederick, Maryland (Frederick County), operated by TPG Real Estate Partners / Catellus Development Corporation. The public record puts it at 2,100 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
TPG Real Estate Partners / Catellus Development Corporation
Facility type
Data center
Location
5601 Manor Woods Rd, Frederick, Frederick County, MD
Coordinates
39.3477, -77.4938 (approximate)
Power capacity
Not established from a public source
Land
2,100 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Yes. Quantum Frederick in Frederick, Frederick County, Maryland is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. In a draft agreement open for comment in September 2026, Catellus offered about $110M in community benefits in exchange for a zoning freeze.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

In a draft agreement open for comment in September 2026, Catellus offered about $110M in community benefits in exchange for a zoning freeze. Separately, residents and groups including the Sugarloaf Alliance sought a referendum on the council's December 2025 data-center zoning map, which covers about 2,600 acres near Adamstown; public hearings drew significant opposition.

Source: FOX45 News

Power and water

Under a draft agreement announced Sept. 1, 2026, Catellus agreed to cut the site's daily potable water use by almost 80%. It also agreed to shrink the planned data center footprint from 18.3M to 15M sq ft and set aside 433 acres as a nature reserve.

Notes on the record

This record is the master-planned 2,100-acre park itself (the former Alcoa Eastalco Works site), not a duplicate of any single tenant building. The individual tenant campuses tracked separately in this dataset as of September 2026 -- Aligned Data Centers IAD-04 Frederick and IAD-06 Frederick, and Rowan Digital Infrastructure Frederick Campus (Bauxite I), Bauxite II and Bauxite III -- sit on parcels within this same park, so their acreage overlaps this record's. Original developer Quantum Loophole, Inc. was removed from active management/development of the project in a December 2024 dispute settlement with its financial partner TPG Real Estate; TPG now serves as Manager and its affiliate Catellus Development Corporation as Developer, per Catellus's own statement ('TPG Real Estate and Quantum Loophole, Inc. have resolved their dispute over management and development of the 2,100-acre data center campus... Quantum Loophole will no longer have any active involvement in managing or developing the Project.'). The Frederick County Council separately created a Critical Digital Infrastructure Overlay Zone in January 2026 that expanded the area eligible for data-center development around this site by nearly 1,000 acres, but that is a zoning designation, not confirmed additional owned/developed acreage, so it is not included in the recorded acreage. Catellus's own statement and Quantum Loophole's own statement are both dated 2024-12-23; the settlement included a mutual dismissal of the litigation between TPG and Quantum Loophole. As of 2026-09-13, no further operator or ownership change was found; TPG Real Estate / Catellus Development Corporation remain the manager/developer of record, and no new litigation was found.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Quantum Frederick?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Quantum Frederick data center in Frederick?

Yes. Quantum Frederick in Frederick, Frederick County, Maryland is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. In a draft agreement open for comment in September 2026, Catellus offered about $110M in community benefits in exchange for a zoning freeze.

Has anyone filed a lawsuit over the Quantum Frederick data center?

No lawsuit over Quantum Frederick appears in the record we track as of October 22, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Quantum Frederick use?

No water withdrawal figure for Quantum Frederick is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Quantum Frederick, and how big is it?

TPG Real Estate Partners / Catellus Development Corporation is the operator on record. No capacity figure is on record for this site. The site is recorded at 2100 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Quantum Frederick," updated October 22, 2026, https://suedatacenters.org/data-centers/quantum-frederick-campus-md.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/quantum-frederick-campus-md, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Statement from TPG Real Estate and Catellus Development Corporation on the Quantum Frederick Project · Catellus Development Corporation · retrieved September 10, 2026
  2. 2.Quantum Loophole Plans to Develop Data Center Campus in Maryland · Maryland Department of Commerce · retrieved September 10, 2026
  3. 3.Quantum Frederick, Frederick County, MD: Maryland Data Center Series, Pt. 3 · Nature Forward · retrieved September 10, 2026
  4. 4.Frederick County $110M Data Center Deal in Adamstown, MD · Hoodline · retrieved October 22, 2026
  5. 5.Frederick County residents push for referendum after data center zoning plan passes · FOX45 News · retrieved October 22, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us