QTS Bessemer (Project Marvel)
Bessemer, Jefferson County, Alabama · All 36 QTS Data Centers sites · Every QTS and Compass Datacenters case on our tracker
QTS Bessemer (Project Marvel) is a proposed data center in Bessemer, Alabama (Jefferson County), operated by QTS Data Centers. The public record puts it at announced 2025, 1.2 GW planned, 1,607 acres, a reported $14.5 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
What our reporting adds
Our case file documents this site. Dismissed June 22, 2026 by joint stipulation.
Facility record
Proposed
- Operator
- QTS Data Centers
- Facility type
- Data center, AI use likely
- Location
- Bessemer, Jefferson County, AL
- Coordinates
- 33.4400, -86.9700
- Power capacity
- 1.2 GW planned
- Land
- 1,607 acres
- Investment
- $14.5 billion
- Announced
- 2025
- Utility
- Alabama Power
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 330 permanent; 1,000 construction
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- 2026ProposedBessemer City Council approved rezoning of 914 additional acres in April 2026, expanding total site to ~1,607 acres; 18-building count unchanged, additional land used for wider buffers and layout flexibility Source: ABC 3340
- 2026ProposedQTS Data Centers (Blackstone) publicly confirmed as operator behind Project Marvel, July 1-2, 2026; project described as in active planning stage Source: WBRC Fox6
- 2025ProposedProject Marvel first surfaced March 2025; unnamed developer (via Logistics Land Investment LLC, an affiliate of Atlanta-based TPA Group) sought rezoning of ~700 acres in Bessemer for hyperscale data center Source: Data Center Dynamics
- 2025ProposedBessemer City Council voted 5-2 to approve rezoning ~700 acres from agricultural (A-1) to light industrial (I-1) on November 18, 2025; developer identity still not publicly disclosed Source: WBRC Fox6
Opposition and litigation at this site
Yes. QTS Bessemer (Project Marvel) in Bessemer, Jefferson County, Alabama is contested. Hearings, public comment, petitions, or organized opposition are on record. Dismissed June 22, 2026 by joint stipulation.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Dismissed June 22, 2026 by joint stipulation. Project Marvel, a $14.5 billion, 4 million plus sq ft, 18-building data center campus. Strong and ongoing opposition. Public Facebook group 'Bessemer Data Center - We Say No!' grew to 720+ members. NAACP cited environmental justice concerns for majority-minority Bessemer community. Black Warrior Riverkeeper (BWR) and Southern Environmental Law Center (SELC) opposed construction over fossil fuel and water impacts. U.S. Fish and Wildlife Service raised concerns. Rezoning lawsuit filed in Jefferson County Circuit Court (temporarily enjoined; later dismissed). Bessemer City Council approved initial rezoning 5-2 in November 2025 despite crowd opposition (Councilman King and Councilwoman Thigpen dissented). 914-acre expansion rezoning approved April 2026. Some elected officials operated under NDAs with the developer prior to QTS confirmation. Homeowners filed additional lawsuits against the project.
Power and water
Alabama Power confirmed 1,200 MW power availability for the campus. QTS committed project-related energy costs will not be passed on to local utility ratepayers. Opponents (NAACP, Black Warrior Riverkeeper, SELC) raised concerns that the facility will rely on fossil fuels. Bibb County residents identified as potentially facing higher power bills due to grid strain.
QTS committed to a closed-loop cooling system that does not consume water for cooling once operational. Opposition groups including Black Warrior Riverkeeper raised concerns about water impacts during construction and operation, citing proximity to a Black Warrior River tributary. Tuscaloosa County flagged for potential irreversible water impacts.
Notes on the record
Codename: Project Marvel. 18-building hyperscale campus on Red Ridge near I-459 and I-20/59 interchange in Bessemer (Jefferson County). Announced capacity: up to 1,200 MW at full build-out, reported as a planned ceiling, roughly 9% of Alabama Power's current generating capacity; recorded as capacityMw.planned = 1200 (an announced 'up to' full-build-out ceiling, consistent with how the dataset records other announced full-build-out figures). Investment: reported at $14 to 14.5B across sources (Logistics Land Investment anticipated 'close to $14.4B'; WBRC reported $14.5B at November 2025 rezoning; DCD reported ~$14B); no single firm company-confirmed figure exists, treated as a projected cost range and excluded from investmentUsd. Land: ~1,607.42 acres total after two rezoning rounds (initial ~700 acres November 2025 + 914-acre expansion April 2026). QTS affiliate purchased land from TPA Group affiliate for $431.73M. Chapter 9B statutory eligibility would have provided a 30-year abatement estimated at $500M+; QTS committed not to seek local property tax incentives (per WBRC July 2026), subsidy excluded as eligibility does not equal award and QTS renounced pursuit. Full buildout timeline: 7+ years. Birmingham Business Alliance estimated ~$4B net benefit over 30 years; Bessemer City Schools projected ~$25M/year. AI framing not officially confirmed by QTS or the city as of July 2026, size and scale (hyperscale, cloud/AI demand framing in QTS statement) support 'likely' classification. Coordinates are approximate for the Red Ridge parcel area. Jobs: ~1,000 construction and ~330 permanent are projected figures for the proposed (not-yet-built) campus (WBRC, Nov 2025), recorded as projections in notes, not structured jobs fields, per data-rigor policy. QTS Data Centers is owned by Blackstone (2021 take-private). STATUS JUDGEMENT SURFACED, NOT APPLIED: Bessemer approved land-use rezonings for this campus in November 2025 and again (914 acres) in April 2026, which under the wave's rule that a rezoning approval means permitted could argue for permitted rather than proposed. I did not change it, because the record's own cited source dated 2026-07-02 postdates both rezonings and still describes the campus as proposed, and no building permit or site-preparation start was found in any source fetched this run. A maintainer should decide whether a rezoning alone promotes this record.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
- Bessemer's Project Marvel Lawsuit · Dismissed
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Patmos Fairfield Colocation Data Center · Fairfield · Patmos5 mi · Proposed · Contested
- Nebius Birmingham AI Factory (BHM01) · Birmingham · Nebius Group9 mi · Under construction · 300 MW · In litigation
- DC BLOX Birmingham Data Center Campus · Birmingham · DC BLOX10 mi · Operating · 60 MW
- Digi Power X Columbiana AI Data Center · Columbiana · Digi Power X27 mi · Under construction · 40 MW · Contested
Questions people ask about this site
Is there opposition to the QTS Bessemer (Project Marvel) data center in Bessemer?
Yes. QTS Bessemer (Project Marvel) in Bessemer, Jefferson County, Alabama is contested. Hearings, public comment, petitions, or organized opposition are on record. Dismissed June 22, 2026 by joint stipulation.
Has anyone filed a lawsuit over the QTS Bessemer (Project Marvel) data center?
The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.
How much water does QTS Bessemer (Project Marvel) use?
No water withdrawal figure for QTS Bessemer (Project Marvel) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates QTS Bessemer (Project Marvel), and how big is it?
QTS Data Centers is the operator on record. We hold 36 sites for that company across the registry. Capacity on record is 1.2 GW. The site is recorded at 1607 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "QTS Bessemer (Project Marvel)," updated September 9, 2026, https://suedatacenters.org/data-centers/qts-marvel-bessemer-al.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/qts-marvel-bessemer-al, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.QTS confirms plans for proposed data center campus in Bessemer · WBRC Fox6 · retrieved July 7, 2026
- 2.Purported Developer of $14bn Project Marvel Data Center in Bessemer Unveiled as QTS · Construction Review Online · retrieved July 7, 2026
- 3.Bessemer City Council approves data center project despite transparency concerns (November 2025) · WBRC Fox6 · retrieved July 7, 2026
- 4.Bessemer approves rezoning of 914 acres for Project Marvel data center · ABC 3340 · retrieved July 7, 2026
- 5.Alabama's planned $14bn Project Marvel data center could double in size · Data Center Dynamics · retrieved July 7, 2026
- 6.QTS Data Centers behind Bessemer Project Marvel plans · ABC 3340 · retrieved July 7, 2026
- 7.How Will Project Marvel Affect Bessemer And Surrounding Areas? · Tuscaloosa Thread · retrieved July 7, 2026
- 8.Bessemer Residents Are Speaking Out Against AI Data Center Development · Community Sentinel · retrieved July 7, 2026
- 9.Bessemer City Council approves rezoning for $14.5 billion data center project despite transparency concerns · WBRC · retrieved September 9, 2026
- 10.QTS Data Centers behind Bessemer Project Marvel plans · ABC 33/40 · retrieved September 9, 2026
- 11.Bessemer's Project Marvel Lawsuit: How a Dismissed Case Still Forced a Do-Over · SueDataCenters.org · retrieved August 28, 2026
- 12.WBRC: Bessemer data center rezoning lawsuit dismissed (June 25, 2026) · wbrc.com · retrieved August 28, 2026
- 13.WBRC: Bessemer data center approved; lawsuit might force city to share documents councilors reviewed ahead of vote (Dec 2025) · wbrc.com · retrieved August 28, 2026
- 14.Inside Climate News: Bessemer, Alabama's proposed data center (May 2025) · insideclimatenews.org · retrieved August 28, 2026
- 15.SELC: Bessemer City Council greenlights controversial data center rezoning · selc.org · retrieved August 28, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us