Project Red Clay is a proposed data center in Alabama (Lowndes County), operated by Cloverleaf Infrastructure. The public record puts it at 1.5 GW planned, 800 acres, a reported $1.5 billion investment. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Cloverleaf Infrastructure
- Facility type
- Data center, AI use likely
- Location
- Lowndes County, AL
- Coordinates
- 32.2700, -86.5128 (approximate)
- Power capacity
- 1.5 GW planned
- Land
- 800 acres
- Investment
- $1.5 billion
- Announced
- Not established from a public source
- Utility
- Alabama Power
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 50 permanent; 1,000 construction
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Yes. Organized local opposition to Project Red Clay in Lowndes County, Alabama is documented in the public record. Route Fifty (25 Aug 2026): "About 350 people signed the group's petition demanding more transparency from the commission", the group is Protect Lowndes County, which filed an open-records request on 27 July 2026 seeking project documentation and entity lists.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Route Fifty (25 Aug 2026): "About 350 people signed the group's petition demanding more transparency from the commission", the group is Protect Lowndes County, which filed an open-records request on 27 July 2026 seeking project documentation and entity lists. WSFA (4 June 2026) records a resident telling the developer "We're from Lowndes County...Go home. We don't want you," alongside concerns about water use, power bills, noise and transparency. A separate campaign site (45strong.net) titled "Cloverleaf, withdraw from Lowndes County" appeared in search results but was NOT fetched in this run and is not cited. Yellowhammer News notes the site is "half a mile from a field where Selma-to-Montgomery marchers camped in 1965" and that the access road is the Robert "Bob" Mants Jr. Memorial Highway.
Power and water
Route Fifty: "The facility has requested 1,500 megawatts of energy capacity from Alabama Power." WSFA reports the site sits "underneath a 500 kV electrical line" near the U.S. 80 / Alabama 21 intersection, and that the company was still finalizing power contracts as of 4 June 2026. Cloverleaf states on its project site that it will fund the necessary electric-service upgrades itself.
Developer's project site states the building "will only use as much water as an office building on a day-to-day basis" and uses "a closed-loop cooling system requiring a one-time fill", an explicitly recirculating circuit, hence closed_loop. Separately, a Cloverleaf representative told WSFA: "The most amount of water that we've asked for for consumption is 100,000 gallons of water per day." That is a requested maximum, not metered use, so it is NOT recorded as reportedMgd. The Pintlala Water System is named as the supplier in secondary coverage this run could not fetch (Inside Climate News and WBHM both returned 403), so the supplier name is deliberately omitted.
Notes on the record
SUBSIDY, CONFIRMED ABSENCE AS OF 24 JULY 2026: Yellowhammer News reports that no formal abatement request had been filed as of that date, and that the granting body would be the Lowndes County Commission. Under legislation signed by Gov. Kay Ivey in April 2026, an abatement approved before 1 January 2027 could run up to 30 years; after that date the maximum is 20 years. No dollar amount has been stated by any source, so no subsidies entry is recorded. NO NAMED TENANT: Cloverleaf is described by Yellowhammer as a Houston- and Seattle-based speculative developer assembling land for an unnamed future operator; aiClassification is therefore "likely", not confirmed. CONFLICTING FIGURES, recorded rather than reconciled: investment is "$1.5 billion" per WSFA and Route Fifty ("at least $1.5 billion in the development stage") but the developer's own site says "Over a $1 billion taxable investment in Lowndes County". Jobs: the developer's site says "Over 1,000 high-paying construction jobs" and "at least 50 full-time jobs" once operational; other coverage this run could not fetch cites 1,000-1,500 construction and over 200 permanent, the developer's own lower figures are recorded here. Footprint: "more than 800 acres in northeast Lowndes County" and "2.88 million square feet" (Yellowhammer). ZONING: reporting notes Cloverleaf could buy and develop here because Lowndes County has no planning or zoning authority. Coordinates are the OSM-confirmed U.S. 80 / AL 21 junction that WSFA names as the site vicinity, NOT a parcel boundary; the actual footprint is somewhere in northeast Lowndes County near that junction. Inside Climate News and WBHM coverage of this project returned HTTP 403 to both WebFetch and curl in this run and is therefore not cited.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DC BLOX Montgomery Data Center · Montgomery · DC BLOX14 mi · Proposed · 40 MW
- Meta Montgomery Data Center · Montgomery · Meta15 mi · Under construction · Supported
Questions people ask about this site
Is there opposition to the Project Red Clay data center in Lowndes County, Alabama?
Yes. Organized local opposition to Project Red Clay in Lowndes County, Alabama is documented in the public record. Route Fifty (25 Aug 2026): "About 350 people signed the group's petition demanding more transparency from the commission", the group is Protect Lowndes County, which filed an open-records request on 27 July 2026 seeking project documentation and entity lists.
Has anyone filed a lawsuit over the Project Red Clay data center?
The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.
How much water does Project Red Clay use?
No water withdrawal figure for Project Red Clay is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Project Red Clay, and how big is it?
Cloverleaf Infrastructure is the operator on record. We hold 7 sites for that company across the registry. Capacity on record is 1.5 GW. The site is recorded at 800 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Red Clay," updated September 9, 2026, https://suedatacenters.org/data-centers/cloverleaf-red-clay-lowndes-al.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cloverleaf-red-clay-lowndes-al, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Home - Project Red Clay (developer's project site) · Cloverleaf Infrastructure · retrieved September 9, 2026
- 2.Cloverleaf responds to Lowndes County data center concerns after weeks of resident pushback (4 June 2026) · WSFA 12 News · retrieved September 9, 2026
- 3.Lowndes County residents demand transparency in hyperscale data center development (25 Aug 2026) · Route Fifty · retrieved September 9, 2026
- 4.Mystery data center could receive 30-year tax break beside sacred Selma march ground · Yellowhammer News · retrieved September 9, 2026
- 5.Overpass API query confirming the U.S. 80 / Alabama 21 junction in Lowndes County at 32.2700221, -86.5128035 (OSM ways 7795301 "AL 21", 107723832 "US 80;AL 21", 990934473 "US 80") · OpenStreetMap / Overpass API · retrieved September 9, 2026 · original offline, archived copy from September 13, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us