Project Range is a proposed data center in Buckeye, Arizona (Maricopa County), operated by Tract. The public record puts it at 1,000 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Tract
- Facility type
- Data center
- Location
- Buckeye, Maricopa County, AZ
- Coordinates
- 33.4350, -112.5120 (approximate)
- Power capacity
- Not established from a public source
- Land
- 1,000 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 28, 2026ProposedUnder review by Maricopa County planning staff; comprehensive plan amendment and rezoning requests in progress, no hearing dates scheduled as of this retrieval. Source: AZBEX
Opposition and litigation at this site
Yes. Project Range in Buckeye, Maricopa County, Arizona is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The cities of Buckeye and Goodyear both raised significant concerns over building heights, noise and deviation from surrounding land use, and area residents circulated a petition opposing the project.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
The cities of Buckeye and Goodyear both raised significant concerns over building heights, noise and deviation from surrounding land use, and area residents circulated a petition opposing the project. The applicant lowered proposed heights from 110 to 60 feet and increased setbacks from 100 to 500 feet.
Notes on the record
A Maricopa County island between Buckeye and Goodyear, on both sides of Yuma Road between Perryville Road and Jackrabbit Trail. Plan is 28 buildings across two campuses totalling about 5.6 million sq ft, individual buildings 149,000-260,000 sq ft, with roughly 100 acres set aside for parks and public uses and a 15+ year build-out. No MW figure disclosed. Distinct from Tract's tracked Buckeye Tech Corridor site, which is a separate ~1,700-acre holding inside the Buckeye city limits in the Cipriani area south of I-10, the two neighbouring cities' formal objections to Project Range confirm it is not the campus they already entitled.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Microsoft Goodyear Data Center Campus · Goodyear · Microsoft7 mi · Operating
- Compass Datacenters Goodyear Campus · Goodyear · Compass Datacenters8 mi · Operating · 350 MW
- Vantage Phoenix Campus (Goodyear, AZ) · Goodyear · Vantage Data Centers8 mi · Operating · 176 MW
- Stream Data Centers PHXA (Phoenix I-VII, Goodyear Campus) · Goodyear · Stream Data Centers9 mi · Operating · 280 MW
- Avondale Campus · Avondale · Prime Data Centers9 mi · Under construction · 240 MW · Supported
- QTS Phoenix 4 · Tolleson · QTS Data Centers12 mi · Under construction
- Buckeye Tech Corridor · Buckeye · Tract12 mi · Permitted · 1.8 GW · Supported
- Project Baccara · Takanock, LLC12 mi · Permitted · 700 MW · Contested
Questions people ask about this site
Is there opposition to the Project Range data center in Buckeye?
Yes. Project Range in Buckeye, Maricopa County, Arizona is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The cities of Buckeye and Goodyear both raised significant concerns over building heights, noise and deviation from surrounding land use, and area residents circulated a petition opposing the project.
Has anyone filed a lawsuit over the Project Range data center?
No lawsuit over Project Range appears in the record we track as of August 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Range use?
No water withdrawal figure for Project Range is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Project Range, and how big is it?
Tract is the operator on record. We hold 15 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 1000 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Range," updated August 28, 2026, https://suedatacenters.org/data-centers/tract-project-range-buckeye-goodyear-az.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tract-project-range-buckeye-goodyear-az, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Massive Data Center Master Plan Proposed in West Valley · AZBEX · retrieved August 28, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us