Sue Data Centers

Data Center Registry

Buckeye Tech Corridor

Buckeye, Maricopa County, Arizona · All 15 Tract sites

PermittedSupportedAI likelyRecord updated August 31, 2026

Buckeye Tech Corridor is a permitted data center in Buckeye, Arizona (Maricopa County), operated by Tract. The public record puts it at announced February 2025, 1.8 GW planned, 2,069 acres, a reported $20 billion investment. It has documented public support and no documented opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Permitted

Operator
Tract
Facility type
Data center, AI use likely
Location
Buckeye, Maricopa County, AZ
Coordinates
33.4136, -112.7203
Power capacity
1.8 GW planned
Land
2,069 acres
Investment
$20 billion
Announced
February 2025
Utility
Arizona Public Service (APS)
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Supported
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. February 2025
    Permitted
    Buckeye City Council terminated the prior Cipriani residential master plan and approved the Buckeye Tech Corridor rezoning. Source: AZBEX

Opposition and litigation at this site

Not that we can document. Local officials or residents have expressed public support for Buckeye Tech Corridor in Buckeye, Maricopa County, Arizona, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of August 31, 2026. Buckeye City Council approved a development agreement granting Tract up to $50M in public infrastructure reimbursements; the mayor voiced strong support and no organized opposition is documented across multiple independent press accounts.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.

Buckeye City Council approved a development agreement granting Tract up to $50M in public infrastructure reimbursements; the mayor voiced strong support and no organized opposition is documented across multiple independent press accounts.

Source: AZBEX

Power and water

Buckeye Tech Corridor is planned around a standard APS grid interconnect; APS is working to expand area power infrastructure to serve up to 1.8GW of demand.

Notes on the record

Master-planned data center park on a ~2,069-acre former residential (Cipriani) parcel Tract acquired for ~$136M, south of I-10 in Buckeye; planned for up to ~20M sq ft across as many as 40 data centers at full build-out over ~15 years (~$20B). Coordinates are an approximate town-level geocode (Buckeye, south of I-10), not a parcel-confirmed point. The City of Buckeye executed a development agreement with AZLCO Buckeye, LLC (Ordinance No. 08-24, adopted unanimously 2024-08-06). It reimburses the developer for six enumerated regional infrastructure components it builds and dedicates to the city, two public-safety sites, temporary and permanent public-safety facilities, $15M toward the Johnson Road interchange, and oversized regional water infrastructure, funded by 20% of the tax revenue the project itself generates, beginning only after the city has received $60M cumulatively and terminating 20 years from the effective date. It is capped at "the lesser of" the developer's verified costs or $50,000,000, so it cannot exceed what the developer actually spent; it is cost recovery for public infrastructure rather than an incentive, abatement or credit, and is therefore not recorded as a subsidy. Nothing has been paid to date. Buckeye's economic-development director has projected "more than 360 jobs at full build out", an end-state across as many as 40 separate future data centers, none yet leased, permitted or built, and so not recorded as a permanent-jobs figure for this site. A search of 226 Buckeye Council and P&Z agendas (Feb 2024, Aug 2026) found no GPLET and no Foreign Trade Zone instrument.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Buckeye Tech Corridor data center in Buckeye?

Not that we can document. Local officials or residents have expressed public support for Buckeye Tech Corridor in Buckeye, Maricopa County, Arizona, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of August 31, 2026. Buckeye City Council approved a development agreement granting Tract up to $50M in public infrastructure reimbursements; the mayor voiced strong support and no organized opposition is documented across multiple independent press accounts.

Has anyone filed a lawsuit over the Buckeye Tech Corridor data center?

No lawsuit over Buckeye Tech Corridor appears in the record we track as of August 31, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Buckeye Tech Corridor use?

No water withdrawal figure for Buckeye Tech Corridor is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Buckeye Tech Corridor, and how big is it?

Tract is the operator on record. We hold 15 sites for that company across the registry. Capacity on record is 1.8 GW. The site is recorded at 2069 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Buckeye Tech Corridor," updated August 31, 2026, https://suedatacenters.org/data-centers/tract-buckeye-tech-corridor-az.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tract-buckeye-tech-corridor-az, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Tract plans 1,700-acre data center campus in Phoenix, Arizona · Data Center Dynamics · retrieved July 15, 2026
  2. 2.2,069-acre parcel will become a $20 billion data center park in Buckeye · AZ Big Media · retrieved July 15, 2026
  3. 3.Tract Planning 1,700-acre Buckeye Data Center Campus · AZBEX · retrieved July 15, 2026
  4. 4.Buckeye, Tract project page · Tract · retrieved July 15, 2026
  5. 5.Maricopa County Assessor Parcel Viewer, 'AZLCO BUCKEYE LLC' parcel assemblage · retrieved July 18, 2026
  6. 6.AZFamily: Developer wants to power the future of AI in Buckeye with new data center · retrieved July 24, 2026
  7. 7.Buckeye, Tract project page · Tract · retrieved August 16, 2026
  8. 8.City of Buckeye Regular Council Meeting agenda packet, 6 August 2024, Ordinance No. 08-24 and the executed Development Agreement with AZLCO Buckeye, LLC (§12 Regional Infrastructure Components and reimbursement terms) · retrieved August 31, 2026
  9. 9.City of Buckeye council minutes, 6 August 2024, adoption of Ordinance No. 08-24 approving the development agreement with AZLCO Buckeye, LLC (motion passed unanimously) · retrieved August 31, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us