Compass Datacenters Goodyear Campus

Goodyear, Maricopa County, Arizona · All 6 Compass Datacenters sites · Every QTS and Compass Datacenters case on our tracker

OperatingNo reception on recordRecord updated September 10, 2026

Compass Datacenters Goodyear Campus is an operating data center in Goodyear, Arizona (Maricopa County), operated by Compass Datacenters. The public record puts it at 350 MW planned, 225 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Compass Datacenters
Facility type
Data center
Location
Goodyear, Maricopa County, AZ
Coordinates
33.4354, -112.3757 (approximate)
Power capacity
72 MW operating; 350 MW planned
Land
225 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 9, 2019
    Operating
    Compass announced construction start on the first two data centers (72 MW combined IT load), with completion projected for Q4 2019. Source: Compass Datacenters

Opposition and litigation at this site

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Compass Datacenters Goodyear Campus in Goodyear, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

On-site 230 kV substation.

Compass describes 'advanced hybrid cooling that uses no water during operations'. Under the project's tie-breaker, a recirculating cooling circuit is closed_loop even where heat is finally rejected to air, this is recorded as closed_loop, not 'air'; the operator's own word 'hybrid' refers to the equipment, not to seasonal wet/dry switching.

Notes on the record

225-acre campus at the northwest corner of Bullard Avenue and Yuma Road in Goodyear; eight data centers and over 1.8 million sq ft at full build-out, capable of 350 MW, with a 144 MW first master-plan series and a 72 MW opening phase. Distinct from the tracked Vantage Phoenix (Goodyear), Stream PHXA (Goodyear) and Microsoft Goodyear campuses, different operator and different parcel. Coordinates are the cited Bullard Avenue / Yuma Road intersection from OpenStreetMap; the campus lies to the northwest, so the pin is approximate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Compass Datacenters Goodyear Campus in Goodyear?

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Compass Datacenters Goodyear Campus in Goodyear, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Compass Datacenters Goodyear Campus?

No lawsuit over Compass Datacenters Goodyear Campus appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Compass Datacenters Goodyear Campus use?

No water withdrawal figure for Compass Datacenters Goodyear Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Compass Datacenters Goodyear Campus, and how big is it?

Compass Datacenters is the operator on record. We hold 6 sites for that company across the registry. Capacity on record is 350 MW. The site is recorded at 225 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Compass Datacenters Goodyear Campus," updated September 10, 2026, https://suedatacenters.org/data-centers/compass-goodyear-campus-az.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/compass-goodyear-campus-az, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Compass Datacenters Begins Construction of First Two Data Centers on Phoenix Campus · Compass Datacenters · retrieved September 10, 2026
  2. 2.Compass Datacenters will build 225-acre Goodyear campus · AZ Big Media · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us