Prado AI / PraCon Global AI Industrial Campus
Ridgeland, Madison County, Mississippi
Prado AI / PraCon Global AI Industrial Campus is a proposed data center in Ridgeland, Mississippi (Madison County), operated by PraCon Global Investment Group. The public record puts it at announced March 2026. It is the subject of active public debate, with hearings, petitions, or organized opposition on record. The record for this site rests on a single unverified source and should be read that way.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- PraCon Global Investment Group
- Facility type
- Data center, AI use confirmed
- Location
- Ridgeland, Madison County, MS
- Coordinates
- 32.4282, -90.1320 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- March 2026
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Rumored: a single unverified source
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- May 29, 2026ProposedThe PSC declined to issue an opinion, calling the request 'premature' and 'hypothetical' and saying it lacked enough information; Commissioner De'Keither Stamps said Prado did not answer basic questions such as how many tenants the power would serve. Prado said the company will proceed anyway. Source: Mississippi Today
- March 2026ProposedPrado AI, an affiliate of PraCon Global Investment, asked the Mississippi Public Service Commission for an opinion on whether it would be regulated as a public utility if it generated and supplied power to tenants at a potential data center and semiconductor manufacturing campus; its initial filing said the campus would be in Ridgeland and that electricity would be included in the lease and not metered. Source: Mississippi Today
Opposition and litigation at this site
Yes. Prado AI / PraCon Global AI Industrial Campus in Ridgeland, Madison County, Mississippi is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Not a residents-vs-site dispute: the documented opposition is regulatory and commercial.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Not a residents-vs-site dispute: the documented opposition is regulatory and commercial. Entergy Mississippi and Mississippi Power, the state's two largest power providers, are protesting the effort, arguing the arrangement would make Prado AI a public utility subject to PSC regulation, and that a certificate of public convenience and necessity would be required to build the generator. Mississippi Power's brief warned the request 'could intentionally or unintentionally upset this delicate regulatory balance.' No public-reception evidence from nearby residents appears in the source.
Notes on the record
Net-new but SPECULATIVE, confidence 'rumored' on purpose. A proposed AI/semiconductor industrial campus with its own private power plant, before the Mississippi PSC. Deliberately omitted, because the developer refused to state them: capacity MW, investment, acreage, site parcel, timeline. Prado told Mississippi Today he declined to give the PSC more detail because 'making that information available to the utility companies would take away the project's competitive advantage,' and Prado AI 'is still working on securing all the funding it would need for a project of this size'; the only figure attached to it is Prado's stated LONG-TERM GOAL of 'over $25 billion', which is an aspiration, not an announced investment, and is therefore NOT recorded in investmentUsd. Location: the March PSC filing named Ridgeland, but Prado has since said only 'the Jackson metro area' and declined to say where, coordinates are a Ridgeland city geocode from the filing, precision 'approximate'; if it lands elsewhere in the metro this record needs relocating. Sourced from a Wayback snapshot because mississippitoday.org returns HTTP 403 to direct fetches. Ed's call whether a project this unformed belongs in the dataset at all; the argument for including it is that it is docketed at the PSC and formally opposed by both of the state's major utilities, which is more than a press rumour. NOTE the separate real facility entergy-traceview-ridgeland-ms is also in Ridgeland, unrelated.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- AWS Costas Property Campus (Ridgeland) · Ridgeland · Amazon Web Services3 mi · Under construction
- AWS Clinton Data Center · Clinton · Amazon Web Services13 mi · Under construction
- AVAIO Digital Taurus · Brandon · AVAIO Digital Partners14 mi · Under construction · 116 MW · Mixed reception
- AWS Project Atlas, Madison County Mega Site (Canton) · Canton · Amazon Web Services14 mi · Under construction · 1 GW · Contested
- CleanSpark Clinton Bitcoin Mining Facilities · Clinton · CleanSpark, Inc.14 mi · Operating · 16.5 MW
Questions people ask about this site
Is there opposition to the Prado AI / PraCon Global AI Industrial Campus in Ridgeland?
Yes. Prado AI / PraCon Global AI Industrial Campus in Ridgeland, Madison County, Mississippi is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Not a residents-vs-site dispute: the documented opposition is regulatory and commercial.
Has anyone filed a lawsuit over the Prado AI / PraCon Global AI Industrial Campus?
No lawsuit over Prado AI / PraCon Global AI Industrial Campus appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Prado AI / PraCon Global AI Industrial Campus use?
No water withdrawal figure for Prado AI / PraCon Global AI Industrial Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Prado AI / PraCon Global AI Industrial Campus, and how big is it?
PraCon Global Investment Group is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Prado AI / PraCon Global AI Industrial Campus," updated September 9, 2026, https://suedatacenters.org/data-centers/prado-ai-jackson-metro-ms.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/prado-ai-jackson-metro-ms, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Mississippi developer plans to move forward with data center plans, even as state declines to give ruling (Wayback snapshot 2026-08-19) · Mississippi Today · retrieved September 9, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us