AVAIO Digital Taurus is a data center under construction in Brandon, Mississippi (Rankin County), operated by AVAIO Digital Partners. The public record puts it at announced 2025, 116 MW planned, 329 acres, a reported $6 billion investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
AVAIO Digital Partners
Facility type
Data center, AI use confirmed
Location
Brandon, Rankin County, MS
Coordinates
32.2700, -89.9900
Power capacity
116 MW planned
Land
329 acres
Investment
$6 billion
Announced
2025
Utility
Entergy Mississippi
Power source
Mixed
Cooling
Hybrid
Water use
Not established from a public source
Jobs
60 permanent
Public subsidy
Mississippi Data Center Enterprises tax exemption (approved by MDA; sales & use tax incentives for campus tenants; multi-year, no confirmed total amount), Mississippi, 2025 | Data Center Enterprises tax exemption, Mississippi, 2025
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 10, 2025
    Under construction
    Groundbreaking held at East Metropolitan Center Business and Industrial Park in Brandon. Source: AVAIO Digital
  2. August 19, 2025
    Proposed
    AVAIO Digital announced $6B AI-ready data center campus in Brandon, Rankin County, MS; Mississippi Development Authority approved Data Center Enterprises tax exemption. Source: PR Newswire / AVAIO Digital Partners

Opposition and litigation at this site

Partly. Both documented support and documented opposition to AVAIO Digital Taurus in Brandon, Rankin County, Mississippi appear in the record, with no clear majority position. Strong official support: Governor Reeves, Mayor Butch Lee (Brandon), Rankin County, and MDA all endorsed project.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Strong official support: Governor Reeves, Mayor Butch Lee (Brandon), Rankin County, and MDA all endorsed project. Community opposition emerged before groundbreaking: online petition to Rankin County Board of Supervisors demanded written guarantees against utility bill increases and air/water pollution, and called for construction halt if guarantees cannot be made. Residents cited concerns about water consumption, air pollution (referencing xAI Memphis gas turbine precedent), power demands, and traffic. Community group 'Mississippi For Mississippi' produced an impact-distance map. Rankin County supervisors did not respond to press inquiries. No litigation reported.

Source: Mississippi Today

Power and water

Initial 116 MW grid power via executed ESA with Entergy Mississippi (June 2027 target energization). Additional 420 MW grid power from Entergy projected by end of 2030. On-site thermal generation via Gulf South Pipeline access (up to 500 MW planned, Q2 2027 start), on-site gas not yet built. Rooftop solar 20+ MW planned. Behind-the-meter generation noted by operator.

Operator describes water-efficient cooling, rainwater recapture, cooling system economization (air-side economization implied), and recycled water as an available option. New sewer line extension under construction for wastewater. No specific MGD figure disclosed.

Public money on the record

ProgramAmountGranted byYear
Mississippi Data Center Enterprises tax exemption (approved by MDA; sales & use tax incentives for campus tenants; multi-year, no confirmed total amount)Not establishedMississippi2025
Data Center Enterprises tax exemptionNot establishedMississippi2025

Notes on the record

Distinct from AVAIO's 'Leo' campus in Little Rock/Pulaski County AR, do not conflate. Site: East Metropolitan Center Business and Industrial Park, Brandon. Land acreage: AVAIO's own project page and groundbreaking materials cite 329 acres; the August 19 press release cited 175 acres, 329 used as more authoritative per operator's site. Capacity: 116 MW initial via executed ESA with Entergy Mississippi (energized June 2027 per operator site); Entergy guiding an additional 420 MW of grid power available by end of 2030; access to Gulf South Pipeline for up to 500 MW of on-site behind-the-meter thermal generation starting Q2 2027, total baseload path to over 1 GW. The 116 MW planned figure reflects the executed first-phase ESA only; full buildout remains a projection. Investment: $6B stated without 'up to' qualifier across operator, MDA, and Governor's office sources; Governor's office describes it as the third-largest economic development project in Mississippi history. Jobs: 'at least 60 direct, high-tech jobs' and 'hundreds of indirect jobs ranging from construction to other related industries', projections, not firm figures; no construction vs permanent breakdown confirmed. Rooftop solar of 20+ MW planned (behind-the-meter). Recycled water and new sewer line extension cited by operator as water infrastructure options. Estimated $23M in ad valorem tax revenue annually per Rankin First (county economic development group). Coordinates approximate (Brandon city center, Rankin County).

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the AVAIO Digital Taurus data center in Brandon?

Partly. Both documented support and documented opposition to AVAIO Digital Taurus in Brandon, Rankin County, Mississippi appear in the record, with no clear majority position. Strong official support: Governor Reeves, Mayor Butch Lee (Brandon), Rankin County, and MDA all endorsed project.

Has anyone filed a lawsuit over the AVAIO Digital Taurus data center?

No lawsuit over AVAIO Digital Taurus appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does AVAIO Digital Taurus use?

No water withdrawal figure for AVAIO Digital Taurus is on record here. Cooling is recorded as hybrid, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates AVAIO Digital Taurus, and how big is it?

AVAIO Digital Partners is the operator on record. We hold 4 sites for that company across the registry. Capacity on record is 116 MW. The site is recorded at 329 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "AVAIO Digital Taurus," updated September 9, 2026, https://suedatacenters.org/data-centers/avaio-taurus-brandon-ms.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/avaio-taurus-brandon-ms, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.AVAIO Digital Taurus announcement press release · PR Newswire / AVAIO Digital Partners · retrieved July 7, 2026
  2. 2.AVAIO Digital Taurus official project page · AVAIO Digital · retrieved July 7, 2026
  3. 3.Mississippi Development Authority project announcement · Mississippi Development Authority · retrieved July 7, 2026
  4. 4.Governor Reeves office announcement, third-largest project in MS history · Office of the Governor of Mississippi · retrieved July 7, 2026
  5. 5.City of Brandon welcome announcement · City of Brandon, MS · retrieved July 7, 2026
  6. 6.Brandon residents petition, water, power, pollution concerns · Mississippi Today · retrieved July 7, 2026
  7. 7.AVAIO Digital Breaks Ground on $6 Billion Brandon Data Center Campus; Leading Mississippi Contractor Begins Site Work · AVAIO Digital Partners (PR Newswire) · retrieved September 9, 2026
  8. 8.AVAIO Digital to locate $6 billion data center campus in Rankin County · Mississippi Development Authority · retrieved September 9, 2026
  9. 9.Brandon, Mississippi Campus (Project Taurus) · AVAIO Digital · retrieved September 9, 2026
  10. 10.AVAIO Digital to locate $6 billion data center campus in Rankin County · Mississippi Development Authority · retrieved September 9, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us