Lucin, Box Elder County, Utah

ProposedContestedAI confirmedRecord updated October 28, 2026

Stratos AI Data Center Campus is a proposed data center in Lucin, Utah (Box Elder County), operated by O'Leary Digital. The public record puts it at announced April 2026, 9 GW planned. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
O'Leary Digital
Facility type
Data center, AI use confirmed
Location
Lucin, Box Elder County, UT
Coordinates
41.5000, -113.5000 (approximate)
Power capacity
9 GW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
April 2026
Utility
Raft Rural Electric Co-op Inc
Power source
On site gas
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. April 2026
    Proposed
    MIDA Board approved Stratos Project Area on April 24, 2026; Box Elder County Commission approved interlocal agreement May 4, 2026 Source: Box Elder County, UT

Opposition and litigation at this site

Yes. Stratos AI Data Center Campus in Lucin, Box Elder County, Utah is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Community opposition over fast-tracked MIDA process, CO2 emissions (~34M metric tons/year at full build), light/noise pollution, and Great Salt Lake impacts.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Community opposition over fast-tracked MIDA process, CO2 emissions (~34M metric tons/year at full build), light/noise pollution, and Great Salt Lake impacts. Utah Senate President Stuart Adams demanded a developable project area under 10,000 acres; on June 4, 2026, O'Leary wrote that he would remove 19,430 acres around Locomotive Springs and another 620 acres, cutting the project area roughly in half (KUER). Governor Cox ordered 'careful consideration' of environmental impacts.

Source: Utah News Dispatch

Power and water

Ruby Pipeline (680-mile interstate natural gas line) runs through Hansel Valley; 3,000-acre solar array planned; fully off-grid design

Closed-loop system using on-site saline water described as unsuitable for human or agricultural use; developer states no diversion from Great Salt Lake basin

Notes on the record

Hansel Valley and Locomotive Valley, western Box Elder County near Lucin, UT. The project area was about 40,000 acres as approved in spring 2026 (Utah News Dispatch); on June 4, 2026, O'Leary wrote that the company would remove 19,430 acres in and around the Locomotive Springs area and another 620 acres, cutting the area roughly in half (KUER). As of October 2026, no current total area is recorded. 60 planned data centers on initial 10,000-acre phase. 9GW is full-buildout figure; Phase 1 ~3GW. Total cost projected $100B+ at full buildout; only $20M invested as of mid-2026. Designed by Gensler. Environmental permitting via Utah DEQ expected to take ~2 years. MIDA oversight provides state-level approval authority. Coordinates are approximate for western Box Elder County; exact site boundaries unpublished. Subsidies checked at the municipal tier (2026-09-05): no site-level subsidy found. Box Elder County's own Stratos Project Fact Sheet states directly: "No County funds are required to build the project. All funds will come from the developers and private investors." A May 2026 MIDA interlocal agreement covers land-use and permitting review governance (a development review committee, subdivision/site-plan requirements), not a tax-increment or abatement arrangement, and MIDA's own project-area records, which could confirm or rule out a tax-increment component, were unreachable when checked in September 2026 (mida.utah.gov redirected to an unrelated login page). Utah's EDTIF programme excludes data centres and the UCA 59-12-104 exemption is self-executing.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Tell us about your situation

Living near Stratos AI Data Center Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Stratos AI Data Center Campus in Lucin?

Yes. Stratos AI Data Center Campus in Lucin, Box Elder County, Utah is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Community opposition over fast-tracked MIDA process, CO2 emissions (~34M metric tons/year at full build), light/noise pollution, and Great Salt Lake impacts.

Has anyone filed a lawsuit over the Stratos AI Data Center Campus?

No lawsuit over Stratos AI Data Center Campus appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Stratos AI Data Center Campus use?

No water withdrawal figure for Stratos AI Data Center Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Stratos AI Data Center Campus, and how big is it?

O'Leary Digital is the operator on record. Capacity on record is 9 GW.

How to cite this page

SueDataCenters.org Data Center Registry, "Stratos AI Data Center Campus," updated October 28, 2026, https://suedatacenters.org/data-centers/stratos-box-elder-ut.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/stratos-box-elder-ut, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Stratos Project Fact Sheet, Box Elder County · Box Elder County, UT · retrieved July 6, 2026
  2. 2.Renderings show Stratos data center but permits could take years · Utah News Dispatch · retrieved July 6, 2026
  3. 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
  4. 4.Kevin O’Leary says he’ll shrink the Box Elder data center by 20,000 acres · KUER · retrieved October 28, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us