QTS Eagle Mountain Data Center Campus

Eagle Mountain, Utah County, Utah · All 36 QTS Data Centers sites · Every QTS and Compass Datacenters case on our tracker

Under constructionMixed receptionAI confirmedRecord updated August 16, 2026

QTS Eagle Mountain Data Center Campus is a data center under construction in Eagle Mountain, Utah (Utah County), operated by QTS Data Centers. The public record puts it at announced 2023, 200 MW planned, 193 acres, a reported $6 billion investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
QTS Data Centers
Facility type
Data center, AI use confirmed
Location
Eagle Mountain, Utah County, UT
Coordinates
40.3155, -111.9847
Power capacity
200 MW planned
Land
193 acres
Investment
$6 billion
Announced
2023
Utility
Rocky Mountain Power (PacifiCorp)
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
100 permanent; 2,000 construction
Public subsidy
Eagle Mountain RDA Sweetwater #3 community-reinvestment tax-increment financing, reimburses QTS/tenants 61% of real-property and 74% of personal-property tax increment, 20 years per phase (up to 40 years total); first-phase increment projected at ~$98.86M, Eagle Mountain City RDA, UT, 2023
Community reception
Mixed reception
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2024
    Under construction
    Construction initially paused, then restarted; 3 buildings ranging 579,000 to 592,000 sq ft; water-free cooling system Source: Utah News Dispatch
  2. 2023
    Permitted
    City of Eagle Mountain approved construction; 193-acre campus adjacent to Meta campus Source: Eagle Mountain City

Opposition and litigation at this site

Partly. Both documented support and documented opposition to QTS Eagle Mountain Data Center Campus in Eagle Mountain, Utah County, Utah appear in the record, with no clear majority position. City officials are formally supportive (a projected ~$12M/year municipal energy tax funds roads, schools, and first responders), and no organized opposition to QTS specifically was found.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

City officials are formally supportive (a projected ~$12M/year municipal energy tax funds roads, schools, and first responders), and no organized opposition to QTS specifically was found. But water and energy transparency are actively debated in arid Utah, the 2026 state water-reporting law (HB76) was driven partly by Eagle Mountain's data-center growth, though facilities operational before July 2026 are exempt.

Source: KUTV (CBS Utah)

Power and water

Grid-served by Rocky Mountain Power. After the utility initially could not guarantee sufficient grid power, the city approved on-site gas turbines and a separate 200 MW gas plant as options, but QTS ultimately secured grid supply. QTS declines to disclose the campus's power capacity (third-party trackers estimate over 650 MW at full build-out); it reports portfolio-wide carbon-free electricity for 2024.

A closed-loop system that QTS says does not consume water for cooling once operational, roughly a 600,000-gallon one-time fill per building plus modest domestic use, avoiding an estimated 250 to 300 million gallons/year versus evaporative cooling.

Public money on the record

ProgramAmountGranted byYear
Eagle Mountain RDA Sweetwater #3 community-reinvestment tax-increment financing, reimburses QTS/tenants 61% of real-property and 74% of personal-property tax increment, 20 years per phase (up to 40 years total); first-phase increment projected at ~$98.86MNot establishedEagle Mountain City RDA, UT2023

Notes on the record

Groundbreaking was October 2025; the third of three initial buildings topped out (structural completion) on 2026-04-20. Not yet operational; no delivery date confirmed.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the QTS Eagle Mountain Data Center Campus in Eagle Mountain?

Partly. Both documented support and documented opposition to QTS Eagle Mountain Data Center Campus in Eagle Mountain, Utah County, Utah appear in the record, with no clear majority position. City officials are formally supportive (a projected ~$12M/year municipal energy tax funds roads, schools, and first responders), and no organized opposition to QTS specifically was found.

Has anyone filed a lawsuit over the QTS Eagle Mountain Data Center Campus?

No lawsuit over QTS Eagle Mountain Data Center Campus appears in the record we track as of August 16, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does QTS Eagle Mountain Data Center Campus use?

No water withdrawal figure for QTS Eagle Mountain Data Center Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates QTS Eagle Mountain Data Center Campus, and how big is it?

QTS Data Centers is the operator on record. We hold 36 sites for that company across the registry. Capacity on record is 200 MW. The site is recorded at 193 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "QTS Eagle Mountain Data Center Campus," updated August 16, 2026, https://suedatacenters.org/data-centers/qts-eagle-mountain-ut.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/qts-eagle-mountain-ut, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.QTS begins construction on new datacenter campus in Eagle Mountain, Eagle Mountain City · Eagle Mountain City · retrieved July 5, 2026
  2. 2.Eagle Mountain 193-acre data center campus set to be done this year, Utah News Dispatch · Utah News Dispatch · retrieved July 5, 2026
  3. 3.QTS Eagle Mountain, official data center page · QTS Data Centers · retrieved July 6, 2026
  4. 4.Eagle Mountain RDA, Sweetwater #3 CRA / QTS participation agreement (Aug 2024 packet) · Eagle Mountain City / Utah Public Notice · retrieved July 6, 2026
  5. 5.Questions grow over water use at massive QTS Data Center in Eagle Mountain, KUTV · KUTV (CBS Utah) · retrieved July 6, 2026
  6. 6.To power Utah's data center boom, companies are turning to fossil fuels, Grist · Grist · retrieved July 6, 2026
  7. 7.Layton Construction, QTS Data Centers Break Ground on Eagle Mountain Campus · Utah Business · retrieved August 8, 2026
  8. 8.To power Utah's data center boom, companies are turning to fossil fuels, Grist · Grist · retrieved August 16, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us