Data Center Registry
Project Atlas Data Center Campus (South Whitehall Township)
South Whitehall Township, Lehigh County, Pennsylvania
Project Atlas Data Center Campus (South Whitehall Township) is a proposed data center in South Whitehall Township, Pennsylvania (Lehigh County), operated by CDE Acquisitions, LLC. The public record puts it at 410 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- CDE Acquisitions, LLC
- Facility type
- Data center
- Location
- 2747 North Cedar Crest Boulevard, South Whitehall Township, Lehigh County, PA, 18104
- Coordinates
- 40.6401, -75.5443 (approximate)
- Power capacity
- Not established from a public source
- Land
- 410 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 11, 2026ProposedRevised plan scheduled for a South Whitehall Township public hearing on June 11, 2026, after the developer cut the program from six buildings to three data center buildings plus support structures. Source: WFMZ-TV 69 News
Opposition and litigation at this site
Nothing on record as of September 12, 2026. No lawsuit, organized opposition, or contested hearing over Project Atlas Data Center Campus (South Whitehall Township) in South Whitehall Township, Lehigh County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Three parcels at 2493, 2807 and 2747 N. Cedar Crest Boulevard totalling 410 acres across from Parkland High School, owned by Jeras Corporation, with CDE Acquisitions, LLC of Atlanta as applicant. The revised program is three data center buildings of 492,285 sq ft each plus a 40,680 sq ft administration building and a 39,167 sq ft warehouse, 1,556,702 sq ft in total - down from six buildings over 5 million sq ft. Parking drops from 966 to 399 spaces and weekday trips from 3,865 to 1,154. Includes an on-site electrical substation, emergency generators and a private septic field, with a water main extension requested along Ritter Road. Three barns are to be restored and dedicated to the township; a brick house and farmstead would be removed. Stated construction start November 2029, completion April 2030.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Flexential Allentown Data Center (ABE01) · Allentown · Flexential5 mi · Operating
- Prologis Allen Township Data Center (2500 Liberty Drive) · Allen Township · Prologis5 mi · Permitted
- Cetronia Road Data Center (former Air Products site) · Trexlertown · Air Products7 mi · Cancelled · Contested
- Panther Creek Plant · Nesquehoning · Bitfarms Ltd. (Keel Infrastructure Corp.)21 mi · Operating · 350 MW
- Panther Creek HPC/AI Data Center Campus · Nesquehoning · Bitfarms Ltd.21 mi · Under construction · 350 MW
- Limerick Township Data Center Campus (MCD 7) · Limerick Township · MCD 7 LLC27 mi · Proposed · 750 MW · Opposed
- Slate Belt Holdings Data Center Campus (Upper Mount Bethel) · Upper Mount Bethel Township · Slate Belt Holdings LLC (Talen Energy / River Pointe Logistics joint venture)28 mi · Proposed
- AWS Kline Township Data Center Campus · Kline Township · Amazon Web Services30 mi · Proposed
Questions people ask about this site
Is there opposition to the Project Atlas Data Center Campus (South Whitehall Township) in South Whitehall Township?
Nothing on record as of September 12, 2026. No lawsuit, organized opposition, or contested hearing over Project Atlas Data Center Campus (South Whitehall Township) in South Whitehall Township, Lehigh County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Project Atlas Data Center Campus (South Whitehall Township)?
No lawsuit over Project Atlas Data Center Campus (South Whitehall Township) appears in the record we track as of September 12, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Atlas Data Center Campus (South Whitehall Township) use?
No water withdrawal figure for Project Atlas Data Center Campus (South Whitehall Township) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Project Atlas Data Center Campus (South Whitehall Township), and how big is it?
CDE Acquisitions, LLC is the operator on record. No capacity figure is on record for this site. The site is recorded at 410 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Atlas Data Center Campus (South Whitehall Township)," updated September 12, 2026, https://suedatacenters.org/data-centers/cde-acquisitions-project-atlas-south-whitehall-lehigh-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cde-acquisitions-project-atlas-south-whitehall-lehigh-pa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Plans change for proposed South Whitehall data center; here's what's on the table now · WFMZ-TV 69 News · retrieved September 12, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us