Deep Park Data Center (North Port 300) is a proposed data center in North Port, Florida (Sarasota County), operated by North Port Holdings 300 LLC (end operator undisclosed). The public record puts it at announced July 20, 2026, 112 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
North Port Holdings 300 LLC (end operator undisclosed)
Facility type
Data center
Location
North Port, Sarasota County, FL
Coordinates
27.0678, -82.0744 (approximate)
Power capacity
Not established from a public source
Land
112 acres
Investment
Not established from a public source
Announced
July 20, 2026
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
0.0155 million gallons a day, reported
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 20, 2026
    Proposed
    Site and development plan application received by the City of North Port; city awaiting applicant response to sufficiency-review deficiencies. Source: ABC7 Suncoast (WWSB)

Opposition and litigation at this site

Yes. Deep Park Data Center (North Port 300) in North Port, Sarasota County, Florida is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. City commission advanced an 18-month data center moratorium (first reading 2026-08-31, workshop 2026-09-03, second reading 2026-09-22); the application may continue technical review but cannot receive final approval while a moratorium is in effect.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

City commission advanced an 18-month data center moratorium (first reading 2026-08-31, workshop 2026-09-03, second reading 2026-09-22); the application may continue technical review but cannot receive final approval while a moratorium is in effect.

Source: Sarasota Magazine

Power and water

Filing states average potable-water demand of 15,500 gallons/day (max 23,250 gpd); cooling technology not identified in the application (Sarasota Magazine, 2026-09).

Notes on the record

Seven data center buildings totaling ~896,000 sq ft (incl. ~123,200 sq ft office) on ~112 acres within the 282-acre 'Deep Park' master concept (Activity Center 6) north of I-75 and south of Yorkshire Street. Applicant LLC is registered to Valley Stream, NY; end tenant is under NDA. Application filed 2026-07-20; ~22.5 acres of stormwater ponds and 4.14 acres of wetland impacts per filings.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Free case review

Living near Deep Park Data Center (North Port 300)?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Deep Park Data Center (North Port 300) in North Port?

Yes. Deep Park Data Center (North Port 300) in North Port, Sarasota County, Florida is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. City commission advanced an 18-month data center moratorium (first reading 2026-08-31, workshop 2026-09-03, second reading 2026-09-22); the application may continue technical review but cannot receive final approval while a moratorium is in effect.

Has anyone filed a lawsuit over the Deep Park Data Center (North Port 300)?

No lawsuit over Deep Park Data Center (North Port 300) appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Deep Park Data Center (North Port 300) use?

0.0155 million gallons a day is the reported figure on record. Filing states average potable-water demand of 15,500 gallons/day (max 23,250 gpd); cooling technology not identified in the application (Sarasota Magazine, 2026-09).

Who operates Deep Park Data Center (North Port 300), and how big is it?

North Port Holdings 300 LLC (end operator undisclosed) is the operator on record. No capacity figure is on record for this site. The site is recorded at 112 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Deep Park Data Center (North Port 300)," updated September 21, 2026, https://suedatacenters.org/data-centers/north-port-holdings-300-deep-park-north-port-fl.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/north-port-holdings-300-deep-park-north-port-fl, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.North Port releases new information on proposed data center as commission considers moratorium · ABC7 Suncoast (WWSB) · retrieved September 21, 2026
  2. 2.New North Port data center filings detail water use, wetland impacts and more · Sarasota Magazine · retrieved September 21, 2026
  3. 3.Proposed North Port data center location found? · North Port Sun · retrieved September 21, 2026
  4. 4.City of North Port, Data Center Info (application timeline) · City of North Port · retrieved September 21, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us