Sue Data Centers

Data Center Registry

Wave Garden Macedonia Cryptomine

Macedonia, Columbia County, Arkansas

OperatingOpposedRecord updated September 15, 2026

Wave Garden Macedonia Cryptomine is an operating crypto mining site in Macedonia, Arkansas (Columbia County), operated by Wave Garden, LLC. The public record puts it at 8.1 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Wave Garden, LLC
Facility type
Crypto mining
Location
Macedonia, Columbia County, AR
Coordinates
33.1765, -93.3002 (approximate)
Power capacity
Not established from a public source
Land
8.1 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Entergy
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. February 2024
    Operating
    The facility was operating by early 2024 and still operating as of April 2024 reporting. Land - 8.10 acres off County Road 12 in the Macedonia community - was purchased 2023-10-16 for $243,000 through Bismarck Land Holding LLC. Source: Magnolia Reporter

Opposition and litigation at this site

Yes. Organized local opposition to Wave Garden Macedonia Cryptomine in Macedonia, Columbia County, Arkansas is documented in the public record, without a lawsuit on file in the sources we track. Macedonia residents objected to continuous noise.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

Macedonia residents objected to continuous noise. John Ed Stewart, living 200-600 yards away, said 'It's this buzzing (when it is going) and - it never stops'; Devona Powell, about a mile away, said 'It gets monotonous to listen to it.' Columbia County imposed a 65-decibel limit by emergency ordinance on 2023-07-31, and Stewart recorded levels reaching 78 decibels.

Source: Magnolia Reporter

Power and water

Sited off County Road 12 adjacent to an Entergy power supply.

The facility inquired about obtaining up to 200,000 gallons per month during hot months, which would make it the Dorcheat Rural Water Association's largest customer. Recorded in the units the source states; no monthly-to-daily conversion is made and reportedMgd is deliberately left unset, because the figure is an inquiry about availability rather than a reported withdrawal.

Notes on the record

Coordinates are the OpenStreetMap point for the Macedonia community in Columbia County; the site is described only as 'off County Road 12', so this is a community-level approximation, not the parcel. Land was purchased through Bismarck Land Holding LLC and the facility is operated by Wave Garden, LLC, per the Magnolia Reporter's reading of county land records; the two entities' relationship is not further documented in the source. Status is as of April 2024 reporting and has NOT been re-verified - the mine may have changed hands, expanded or closed since. Confidence 'reported': the second citation is a reprint of the first, so this is effectively single-outlet sourcing.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Free case review

Living near Wave Garden Macedonia Cryptomine?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Wave Garden Macedonia Cryptomine data center in Macedonia?

Yes. Organized local opposition to Wave Garden Macedonia Cryptomine in Macedonia, Columbia County, Arkansas is documented in the public record, without a lawsuit on file in the sources we track. Macedonia residents objected to continuous noise.

Has anyone filed a lawsuit over the Wave Garden Macedonia Cryptomine data center?

No lawsuit over Wave Garden Macedonia Cryptomine appears in the record we track as of September 15, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Wave Garden Macedonia Cryptomine use?

No water withdrawal figure for Wave Garden Macedonia Cryptomine is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Wave Garden Macedonia Cryptomine, and how big is it?

Wave Garden, LLC is the operator on record. No capacity figure is on record for this site. The site is recorded at 8.1 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Wave Garden Macedonia Cryptomine," updated September 15, 2026, https://suedatacenters.org/data-centers/wave-garden-macedonia-ar.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/wave-garden-macedonia-ar, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Macedonia crypto-mining facility raises noise concerns among residents · Magnolia Reporter · retrieved September 15, 2026
  2. 2.Crypto-mining facility in South Arkansas raises noise concerns among residents (Magnolia Reporter reprint) · The Arkadelphian / Magnolia Reporter · retrieved September 15, 2026
  3. 3.OpenStreetMap Nominatim geocode: Macedonia, Columbia County, Arkansas · OpenStreetMap · retrieved September 15, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us